HONG KONG INTERNATIONAL AIRPORT CONTRACT NO. C20W03 1
SEWERAGE UPGRADING WORKS - SPS1 AND ASSOCIATED SEWERAGE SYSTEM
C015
Activity ID Activity Name Remaining BL Project BL Project Start Finish Activity % Total 3/3/2022
Duration Start Finish Float 2021 2022 2023 2024 2025
Complete S ON D J FM A M J J A S O N D J FM A M J J A S O N D J FM A M J J A S ON D J F M A M J J A S O N D J FM A M
571d 01-Jan-21 07-Dec-22 04-Jul-22 A 20-Jan-25 -775d 20-Jan-25, C20W03
C20W03
66d 05-Oct-22 07-Dec-22 15-Nov-24 20-Jan-25 -775d 20-Jan-25, Contract
Contract Date C008-010
568d 01-Mar-21 07-Dec-22 26-Jul-22 A 17-Jan-25 -772d 17-Jan-25, R.C. Stru
R.C. Structures 2/10/2021
PS - Sewage Pumping Station (SPS1) 568d 01-Mar-21 07-Dec-22 28-Feb-23 A 17-Jan-25 -772d 17-Jan-25, PS - Sew
C20W03-000390 Testing and Commissioning (whole system) 63d 06-Oct-22 07-Dec-22 15-Nov-24 17-Jan-25 0% -772d Testing and Commis
C20W03-01400 ELS Pre-boring 27d 01-Mar-21 31-Mar-21 31-Mar-23 A 01-Aug-23 0% -602d ELS Pre-boring
C20W03-01410 ELS Sheetpiling Works 11d 01-Apr-21 31-Aug-21 28-Feb-23 A 14-Aug-23 91.13% -602d ELS Sheetpiling Works
C20W03-01430 ELS Pumping Test 49d 01-Sep-21 30-Oct-21 15-Aug-23 12-Oct-23 0% -602d ELS Pumping Test
C20W03-01440 Excavation for Sewage Pump Station (SPS1) 120d 01-Nov-21 28-Feb-22 13-Oct-23 07-Mar-24 0% -602d Excavation for Sewage Pump Station (SPS1
C20W03-01510 SPS-1 R. C. PL test & blinding 6d 01-Mar-22 07-Mar-22 08-Mar-24 14-Mar-24 0% -602d SPS-1 R. C. PL test & bli nding
C20W03-01520 SPS1 R. C. Substructure (incl. PL test & bli nding) 26d 08-Mar-22 07-Apr-22 15-Mar-24 18-Apr-24 0% -602d SPS1 R. C. Substructure (incl. PL test &
C20W03-01530 SPS1 R. C.Superstructure 67d 08-Apr-22 30-Jun-22 19-Apr-24 10-Jul-24 0% -602d SPS1 R. C.Superstructure
C20W03-01540 Waterproofing Application 82d 23-Apr-22 30-Jul-22 02-May-24 08-Aug-24 0% -602d Waterproofing Application
C20W03-01550 SPS1 Internal Finishes 75d 23-May-22 19-Aug-22 31-May-24 28-Aug-24 0% -575d SPS1 Internal Finishes
C20W03-01570 SPS1 Miscellaneous (doors, windows, louvres, roller shutters, metalwork
73d
and07-Jun-22
signages) 31-Aug-22 15-Jun-24 09-Sep-24 0% -575d SPS1 Miscellaneous (doors, w
C20W03-01850 BS mobilization 0d 23-Apr-22 02-May-24 0% -740d BS mobilization, 02-May-24
C20W03-01860 Mechanical Ventilation System 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Mechanical Ventilation System
C20W03-01870 Fire Services Installation 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Fire Services Installation
C20w03-01910 Plumbing and Drainage Installation 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Plumbing and Drainage Installa
C20W03-01920 Electrical Installation 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Electrical Installation
C20W03-01930 Seawage Pumping System 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Seawage Pumping System
C20W03-01940 Deodorization System 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Deodorization System
C20W03-01950 Chemical Dosing System 74d 14-May-22 10-Aug-22 23-May-24 19-Aug-24 0% -602d Chemical Dosing System
C20W03-01960 Road Lighting System 24d 14-Jul-22 10-Aug-22 22-Aug-24 20-Sep-24 0% -629d Road Lighting System
C20W03-01970 BS demobilization 0d 10-Aug-22 20-Sep-24 0% -751d BS demobilization,

EB - Electrical Building 505d 01-Mar-21 05-Oct-22 26-Jul-22 A 15-Nov-24 -772d 15-Nov-24, EB - Electrica
C20W03-00820 Submission of WW046 I, II, III 14d 01-Jul-22 14-Jul-22 11-Jul-24 24-Jul-24 0% -728d Submission of WW046 I, II, III
C20W03-00830 Submission of WW046 IV, V 14d 15-Jul-22 28-Jul-22 25-Jul-24 07-Aug-24 0% -728d Submission of WW046 IV, V
C20W03-00850 Application of BA13/14 14d 11-Aug-22 24-Aug-22 20-Sep-24 04-Oct-24 0% -751d Application of BA13/14
C20W03-01110 WWO inspection 14d 11-Aug-22 24-Aug-22 20-Sep-24 04-Oct-24 0% -772d WWO inspection
C20W03-01120 FS inspection 21d 25-Aug-22 14-Sep-22 04-Oct-24 25-Oct-24 0% -772d FS inspection
C20W03-01130 OP application and TPIDC inspection 21d 15-Sep-22 05-Oct-22 25-Oct-24 15-Nov-24 0% -772d OP application and TPID
C20W03-01450 Excavation for Electrical Building (EB) 22d 01-Mar-21 31-May-21 26-Jul-22 A 26-Jul-23 70.95% -627d Excavation for Electrical Building (EB)
C20W03-01600 EB R. C. PL test & blinding 23d 01-Jun-21 15-Jun-21 05-Aug-22 A 22-Aug-23 0% -627d EB R. C. PL test & blindin g
C20W03-01610 EB R. C. Substructure 40d 16-Jun-21 31-Aug-21 12-Aug-22 A 10-Oct-23 38.46% -627d EB R. C. Substructure
C20W03-01620 EB R. C. Superstructure (wall/column/300 THK Slab) 148d 01-Sep-21 01-Mar-22 10-Oct-23 11-Apr-24 0% -627d EB R. C. Superstructure (wall/column/300
C20W03-01640 Waterproofing Application 12d 02-Mar-22 15-Mar-22 11-Apr-24 25-Apr-24 0% -627d Waterproofin g Application
C20w03-01650 EB CLP specified works in Tx Room 48d 16-Mar-22 02-May-22 25-Apr-24 12-Jun-24 0% -772d EB CLP specified works in Tx Room
C20W03-01660 EB CLP Handover (Tx Room only) 0d 02-May-22 12-Jun-24 0% -772d EB CLP Handover (Tx Room only),
C20W03-01670 EB Internal Finishes 24d 03-May-22 30-May-22 12-Jun-24 11-Jul-24 0% -629d EB Internal Finishes
C20W03-01680 EB External Finishes 24d 03-May-22 30-May-22 12-Jun-24 11-Jul-24 0% -629d EB External Finishes
C20W03-01690 EB Miscellaneous (doors, window, louvres, roller shutters, metalwork and
24d
signages)
03-May-22 30-May-22 12-Jun-24 11-Jul-24 0% -629d EB Miscellaneous (doors, window,
C20W03-02010 SCADA System 90d 14-May-22 29-Aug-22 23-May-24 06-Sep-24 0% -589d SCADA System
C20W03-02020 CCTV System 90d 14-May-22 29-Aug-22 23-May-24 06-Sep-24 0% -589d CCTV System
C20W03-02030 ACS System (Access Control) 90d 14-May-22 29-Aug-22 23-May-24 06-Sep-24 0% -589d ACS System (Access Control)
C20W03-02040 VDC System (Voice & Data Cabling) 90d 14-May-22 29-Aug-22 23-May-24 06-Sep-24 0% -589d VDC System (Voice & Data C
C20W03-02050 APABX System 90d 14-May-22 29-Aug-22 23-May-24 06-Sep-24 0% -589d APABX System
14d 11-Aug-22 24-Aug-22 20-Aug-24 02-Sep-24 -740d 02-Sep-24, BA8/10 Submissio
BA8/10 Submission
C20W03-00840 Submission of FS314 & Form 501 14d 11-Aug-22 24-Aug-22 20-Aug-24 02-Sep-24 0% -740d Submission of FS314 & Form

Actual Level of Effort Actual Work Critical Remaining Work WORKS PROGRAMME (Baseline) CHINA HARBOUR ENGINEERING CO LTD
C018 C019
Primary Baseline Remaining Work Milestone 18/2/2022 17/5/2022

C022
13/3/2022
C001->C007 C011,C012 C014
5/6/2021 29/11/2021 29/12/2021
HONG KONG INTERNATIONAL AIRPORT CONTRACT NO. C20W03 2
SEWERAGE UPGRADING WORKS - SPS1 AND ASSOCIATED SEWERAGE SYSTEM
C015
Activity ID Activity Name Remaining BL Project BL Project Start Finish Activity % Total 3/3/2022
Duration Start Finish Float 2021 2022 2023 2024 2025
Complete S ON D J FM A M J J A S O N D J FM A M J J A S O N D J FM A M J J A S ON D J F M A M J J A S O N D J FM A M
69d 31-May-22 31-Aug-22 29-Jun-24 20-Sep-24 -584d 20-Sep-24, UU works
UU works
C20W03-02210 UU Drainage System 60d 31-May-22 10-Aug-22 11-Jul-24 20-Sep-24 0% -629d UU Drainage System
C008-010
C20W03-02220 UU Sewage System 60d 31-May-22 10-Aug-22 11-Jul-24 20-Sep-24 0% -629d UU Sewage System
2/10/2021
C20W03-02240 UU Seawater System 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU Seawater System
C20W03-02250 UU Portable Water 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU Portable Water
C20W03-02260 UU CLP Ducting 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU CLP Ducting
C20W03-02270 UU AA Power Cable Ducting 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU AA Power Cable Ducting
C20W03-02280 UU Telecommunication Ductin g 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU Telecommunicatio n Duct
C20W03-02290 UU EL Ducting 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU EL Ducting
C20W03-02300 UU Irrigation System 50d 13-Jun-22 10-Aug-22 23-Jul-24 20-Sep-24 0% -629d UU Irrigation System
C20W03-3310 Removal of Existing 1060mm dia Pipe 25d 03-Aug-22 31-Aug-22 29-Jun-24 30-Jul-24 0% -540d Removal of Existing 1060mm dia
50d 04-Jun-22 02-Aug-22 29-Apr-24 29-Jun-24 -540d 29-Jun-24, OD355
OD355
C20W03-03310 Foul Water PE Pipelayin g OD365with Manhole 50d 04-Jun-22 02-Aug-22 29-Apr-24 29-Jun-24 0% -540d Foul Water PE Pip elayin g OD365wi
224d 01-Jun-21 28-Feb-22 26-Jul-23 26-Apr-24 -599d 26-Apr-24, Sewage Discharge
Sewage Discharge
C20W03-01840 SDC Installation of Handrails, Internal Raising Mains and Miscellaneous
50d 28-Dec-21 28-Feb-22 23-Feb-24 26-Apr-24 0% -599d SDC Installation of Handrails, Internal R
MH - Discharge Manhole 75d 30-Jun-21 27-Sep-21 23-Aug-23 22-Nov-23 -599d 22-Nov-23, MH - Discharge Manhole
C20W03-01810 SDC R. C. Manhole 75d 30-Jun-21 27-Sep-21 23-Aug-23 22-Nov-23 0% -599d SDC R. C. Manhole
DC - Discharge Chamber 174d 01-Jun-21 25-Dec-21 26-Jul-23 23-Feb-24 -599d 23-Feb-24, DC - Discharge Chamber
C20W03-01460 Excavation for Sewage Discharge Chamber (SDC) 24d 01-Jun-21 29-Jun-21 26-Jul-23 23-Aug-23 0% -599d Excavation for Sewage Discharge Chamber (SDC)
C20W03-01820 SDC R. C. Discharge Chamber and Staircase 75d 28-Sep-21 25-Dec-21 22-Nov-23 23-Feb-24 0% -599d SDC R. C. Discharge Chamber and Staircas
298d 01-Jun-21 16-Sep-22 04-Jul-22 A 29-Jun-24 -515d 29-Jun-24, OD 710 Sewage Rising
OD 710 Sewage Rising Mains
AEL (MTR) Portion 297d 01-Jun-21 16-Sep-22 04-Jul-22 A 28-Jun-24 -514d 28-Jun-24, AEL (MTR) Portion
C20W03-01740 OD 710 Rising Main Installation, CHA 50 - CHA 150 35d 01-Jun-21 30-Jul-21 04-Jul-22 A 10-Aug-23 30% -539d OD 710 Rising Main Installation, CHA 50 - CHA 150
C20W03-03010 OD 710 Rising Main Installation, CHA 150 - CHA 250 12d 31-Jul-21 25-Sep-21 31-Aug-22 A 24-Aug-23 75% -539d OD 710 Rising Main Installation, CHA 150 - CHA 250
C20W03-03020 OD 710 Rising Main Installation, CHA 250 - CHA 350 29d 27-Sep-21 23-Nov-21 29-Oct-22 A 28-Sep-23 39% -465d OD 710 Rising Main Installation, CHA 250 - CHA 350
C20W03-03030 OD 710 Rising Main Installation, CHA 350 - CHA 450 31d 24-Nov-21 20-Jan-22 22-Oct-22 A 06-Nov-23 36% -465d OD 710 Rising Main Installation, CHA 350 - CHA 450
C20W03-03040 OD 710 Rising Main Installation, CHA 450 - CHA 550 9d 21-Jan-22 21-Mar-22 19-Nov-22 A 17-Nov-23 81% -465d OD 710 Rising Main Installation, CHA 450 - CHA 55
C20W03-03050 OD 710 Rising Main Installation, CHA 550 - CHA 650 48d 22-Mar-22 21-May-22 17-Nov-23 16-Jan-24 0% -465d OD 710 Rising Main Installation, CHA 550 - CH
C20W03-03060 OD 710 Rising Main Installation, CHA 650 - CHA 750 34d 23-May-22 19-Jul-22 01-May-23 A 26-Feb-24 30% -465d OD 710 Rising Main Installation, CHA 650 - C
C20W03-03070 OD 710 Rising Main Installation, CHA 0 - CHA 050 connecting to PW2006
5d 20-Jul-22 16-Sep-22 25-Feb-23 A 02-Mar-24 90% -420d OD 710 Rising Main Installation, CHA 0 - CH
C20W03-03080 OD 710 Rising Main Installation, CHA 750 - CHA 815 50d 20-Jul-22 16-Sep-22 29-Apr-24 28-Jun-24 0% -514d OD 710 Rising Main Installation, CH
Pipe Jacking (Trenchless) Portion 250d 27-Sep-21 30-Jul-22 25-Aug-23 28-Jun-24 -539d 28-Jun-24, Pipe Jacking (Trenchless
C20W03-03110 Piling for Launch/Receiving Shafts 50d 27-Sep-21 25-Nov-21 25-Aug-23 25-Oct-23 0% -539d Piling for Launch/Receiving Shafts
C20W03-03120 Excavation for Launch/Receiving Shafts 25d 26-Nov-21 24-Dec-21 26-Oct-23 23-Nov-23 0% -539d Excavation for Launch/Receiving Shafts
C20W03-03130 Set up for Pipe Jacking 25d 25-Dec-21 25-Jan-22 24-Nov-23 22-Dec-23 0% -539d Set up for Pipe Jacking
C20W03-03140 Pipe Jacking 100d 26-Jan-22 31-May-22 23-Dec-23 27-Apr-24 0% -539d Pipe Jacking
C20W03-03150 Connection with Raising Mains (backfilling and retrive piles) 50d 01-Jun-22 30-Jul-22 29-Apr-24 28-Jun-24 0% -539d Connection with Raising Mains (bac
Open Area (FSD) Portion 298d 31-Jul-21 02-Aug-22 25-Mar-23 A 29-Jun-24 -540d 29-Jun-24, Open Area (FSD) Portion
C20W03-03220 OD 710 Rising Main Installation CHA 1000 - CHA 1100 50d 31-Jul-21 28-Sep-21 02-May-23 A 28-Aug-23 0% -540d OD 710 Rising Main Installation CHA 1000 - CHA 1100
C20W03-03230 OD 710 Rising Main Installation CHA 1100 - CHA 1200 50d 29-Sep-21 27-Nov-21 29-Aug-23 28-Oct-23 0% -540d OD 710 Rising Main Installation CHA 1100 - CHA 120
C20W03-03240 OD 710 Rising Main Installation CHA 1200 - Plug End 48d 29-Nov-21 27-Jan-22 25-Mar-23 A 23-Dec-23 5% -540d OD 710 Rising Main Installation CHA 1200 - Plug
C20W03-03250 Rising Main Installation of Extension Section P1, P2 and P3 100d 28-Jan-22 02-Jun-22 23-Dec-23 29-Apr-24 0% -540d Rising Main Installation of Extension Se
C20W03-03260 Connection with Pump Station SPS-1 50d 04-Jun-22 02-Aug-22 29-Apr-24 29-Jun-24 0% -540d Connection with Pump Station SPS
571d 01-Jan-21 07-Dec-22 24-May-23 A 20-Jan-25 -775d 20-Jan-25, Miscellan
Miscellaneous
C20W03-00160 Approval of Design for Trenchless Excavation 36d 01-Jan-21 05-Feb-21 24-May-23 A 04-Aug-23 0% -641d Approval of Design for Trenchless Excavation
C20W03-02310 Roads & Pavings 99d 11-Aug-22 07-Dec-22 20-Sep-24 20-Jan-25 0% -629d Roads & Pavings
C20W03-02320 Preparation Works 48d 11-Aug-22 08-Oct-22 20-Sep-24 18-Nov-24 0% -626d Preparation Works
C20W03-02330 Planting Works 48d 08-Sep-22 05-Nov-22 21-Oct-24 16-Dec-24 0% -626d Planting Works
C20W03-02340 Establishment Works 24d 07-Nov-22 03-Dec-22 16-Dec-24 16-Jan-25 0% -626d Establishment Work

Actual Level of Effort Actual Work Critical Remaining Work WORKS PROGRAMME (Baseline) CHINA HARBOUR ENGINEERING CO LTD
C018 C019
Primary Baseline Remaining Work Milestone 18/2/2022 17/5/2022

C022
13/3/2022
C001->C007 C011,C012 C014
5/6/2021 29/11/2021 29/12/2021
HONG KONG INTERNATIONAL AIRPORT CONTRACT NO. C20W03 3
SEWERAGE UPGRADING WORKS - SPS1 AND ASSOCIATED SEWERAGE SYSTEM
C015
Activity ID Activity Name Remaining BL Project BL Project Start Finish Activity % Total 3/3/2022
Duration Start Finish Float 2021 2022 2023 2024 2025
Complete S ON D J FM A M J J A S O N D J FM A M J J A S O N D J FM A M J J A S ON D J F M A M J J A S O N D J FM A M
HML (30m) Pole 60d 31-May-22 10-Aug-22 11-Jul-24 20-Sep-24 -629d 20-Sep-24, HML (30m) Pole
C20W03-00660 30m HML Reinstatement 24d 14-Jul-22 10-Aug-22 22-Aug-24 20-Sep-24 0% -629d 30m HML Reinstatement
C20W03-02120 30m High Mast Foundation 36d 31-May-22 13-Jul-22 11-Jul-24 22-Aug-24 0% -629d C008-010 30m High Mast Foundation
136d 01-Mar-22 13-Jul-22 08-Mar-24 22-Aug-24 -629d
2/10/2021 22-Aug-24, Retaining Wall (RW
Retaining Wall (RW)
C20W03-01470 Excavation for Retaining Wall (RW) 36d 01-Mar-22 12-Apr-22 08-Mar-24 23-Apr-24 0% -565d Excavation for Retaining Wall (RW)
C20W03-02110 R. C. Retaining Wall 36d 31-May-22 13-Jul-22 11-Jul-24 22-Aug-24 0% -629d R. C. Retaining Wall

Actual Level of Effort Actual Work Critical Remaining Work WORKS PROGRAMME (Baseline) CHINA HARBOUR ENGINEERING CO LTD