KALAEKULE RE-ENRY PROGRAMME Classic WBS Layout 28-Jan-20 13:02

Activity ID Activity Name Original Remaining Schedule % Start Finish 2020 2021 2022
Duration Duration Complete
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
KALAEKULE FIELD RE-ENTRY PROGRAMME 500 500 0% 03-Feb-20 31-Dec-21 31-Dec-21, KALAEKULE FIELD RE-ENTR

Level-1 Milestones Level Schedule 458 458 0% 31-Mar-20 31-Dec-21 31-Dec-21, Level-1 Milestones Level Sched
A1030 Safe Wells, RMT & INSPECTIONS 0 0 0% 31-Mar-20 Safe Wells, RMT & INSPECTIONS
A1040 Life extension survey & Integrity repair/refurbishment 0 0 0% 31-Dec-20 Life extension survey & Integrity repair/refurbishment
A1050 EPF-FSO Deployment, Extended well test &MER 0 0 0% 31-Jul-20 EPF-FSO Deployment, Extended well test &MER
A1060 PUT KCDP-B Well on production 0 0 0% 31-Dec-20 PUT KCDP-B Well on production
A1070 Re-development of greater Kalaekule (P1 + P2) 0 0 0% 31-Dec-20 Re-development of greater Kalaekule (P1 + P2)
A1080 Blockwide Exploration/Appraisal Development Programme 0 0 0% 31-Dec-21 Blockwide Exploration/Appraisal Developme
Level-2 Project Summary Level Schedule 500 500 0% 03-Feb-20 31-Dec-21 31-Dec-21, Level-2 Project Summary Level

Safe Well, RMT & Inspections 42 42 0% 03-Feb-20 31-Mar-20 31-Mar-20, Safe Well, RMT & Inspections
A1000 Finalise scope 5 5 0% 03-Feb-20 07-Feb-20 Finalise scope
A1010 Award contracts 10 10 0% 17-Feb-20* 28-Feb-20 Award contracts
A1020 Execute work 27 27 0% 24-Feb-20* 31-Mar-20 Execute work
Life extension survey,Integrity, Repair/Refurbishment 239 239 0% 03-Feb-20 31-Dec-20 31-Dec-20, Life extension survey,Integrity, Repair/Refurbishment
A1090 Finalize scope 5 5 0% 03-Feb-20 07-Feb-20 Finalize scope
A1100 Award contracts 10 10 0% 10-Feb-20* 21-Feb-20 Award contracts
A1110 Execute works 224 224 0% 24-Feb-20* 31-Dec-20 Execute works
EPF-FSO Deployment, Extended Well Test & MER 87 87 0% 02-Mar-20 30-Jun-20 30-Jun-20, EPF-FSO Deployment, Extended Well Test & MER
A1120 Finalize scope 5 5 0% 02-Mar-20* 06-Mar-20 Finalize scope
A1130 Award contract 10 10 0% 09-Mar-20* 20-Mar-20 Award contract
A1140 Execute work 72 72 0% 23-Mar-20* 30-Jun-20 Execute work
PUT KCDP-B Wells on production 30 30 0% 03-Feb-20 13-Mar-20 13-Mar-20, PUT KCDP-B Wells on production
A1150 Confirm scope of work-safe wells and safe access 10 10 0% 02-Mar-20* 13-Mar-20 Confirm scope of work-safe wells and safe access
A1160 Confirm is 205 class SEWOP is suitable for workscope 5 5 0% 03-Feb-20 07-Feb-20 Confirm is 205 class SEWOP is suitable for workscope
A1170 Mobilsed from KCDDP-A to B with contract extension 5 5 0% 03-Feb-20 07-Feb-20 Mobilsed from KCDDP-A to B with contract extension
A1180 Put in place mechanical works contracts (On single-source basis 10 10 0% 03-Feb-20 14-Feb-20 Put in place mechanical works contracts (On single-source basis
Re-devlopment of greater kalaekule (P1+ P2) 66 66 0% 01-Oct-20 31-Dec-20 31-Dec-20, Re-devlopment of greater kalaekule (P1+ P2)
A1190 Carry out frame session 66 66 0% 01-Oct-20* 31-Dec-20 Carry out frame session
A1200 Complete FDP and secure approvals (DPR) & NAPIMS 66 66 0% 01-Oct-20* 31-Dec-20 Complete FDP and secure approvals (DPR) & NAPIMS
Blockwide exploration/Appraisal Development Programme 261 261 0% 01-Jan-21 31-Dec-21 31-Dec-21, Blockwide exploration/Appraisa
A1210 Carry out framing session 261 261 0% 01-Jan-21* 31-Dec-21 Carry out framing session
A1220 Complete seismic interpretations 260 260 0% 01-Jan-21* 30-Dec-21 Complete seismic interpretations
A1230 Complete FDP and secure approvals 261 261 0% 01-Jan-21* 31-Dec-21 Complete FDP and secure approvals

Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.