JACK UP RIGS 3A UPDATE 07-Oct-19 12:51

Activity ID Activity Name Activity % Original Budgeted Total Start Finish 2020 2021
Complete Duration Cost
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
249 P35,300,000.00 02-Sep-19 20-Aug-20 20-Aug-20, JACK UP RIGS
JACK UP RIGS
249 P35,300,000.00 02-Sep-19 20-Aug-20 20-Aug-20, CONSTRUCTION
CONSTRUCTION
ONSHORE 145 P8,400,000.00 02-Sep-19 27-Mar-20 27-Mar-20, ONSHORE
MOBILIZATION 1 P0.00 02-Sep-19 02-Sep-19 02-Sep-19, MOBILIZATION
1 NTP - ONSHORE 0% 1 P0.00 02-Sep-19 02-Sep-19 NTP - ONSHORE
ENGINEERING & PROCUREMENT 40 P700,000.00 03-Sep-19 28-Oct-19 28-Oct-19, ENGINEERING & PROCUREMENT
2 Design Issuance 0% 10 P0.00 03-Sep-19 16-Sep-19 Design Issuance
3 Shop Drawing Submittal and Approval 0% 25 P0.00 03-Sep-19 07-Oct-19 Shop Drawing Submittal and Approval
4 RFO & PO & Procure - All Materials 0% 28 P0.00 12-Sep-19 21-Oct-19 RFO & PO & Procure - All Materials
5 Plates Delivery 0% 19 P700,000.00 02-Oct-19 28-Oct-19 Plates Delivery
TANK ( Bottom/Shell Plates/Compression and Roof Plates) 118 P7,700,000.00 09-Oct-19 27-Mar-20 27-Mar-20, TANK ( Bottom/Shell Plates/Compression and Roof Plates)
6 Scaffolding Erection 0% 20 P0.00 09-Oct-19 05-Nov-19 Scaffolding Erection
7 PLates Assembly 0% 30 P0.00 15-Oct-19 25-Nov-19 PLates Assembly
8 External Vertical Welding 0% 35 P1,500,000.00 22-Oct-19 09-Dec-19 External Vertical Welding
9 Internal Vertical Gouging 0% 35 P1,500,000.00 31-Oct-19 18-Dec-19 Internal Vertical Gouging
10 Internal NDT 0% 30 P0.00 07-Nov-19 18-Dec-19 Internal NDT
11 External horizontal Welding 0% 29 P1,500,000.00 18-Nov-19 02-Jan-20 External horizontal Welding
12 Internal horizontal Gouging 0% 34 P1,500,000.00 27-Nov-19 20-Jan-20 Internal horizontal Gouging
13 Inspection 0% 20 P0.00 17-Dec-19 20-Jan-20 Inspection
14 Install Accessories 0% 20 P0.00 02-Jan-20 29-Jan-20 Install Accessories
15 Surface Preparation and Painting 0% 14 P900,000.00 30-Jan-20 18-Feb-20 Surface Preparation and Painting
16 Insulation and Jacketing 0% 14 P500,000.00 19-Feb-20 09-Mar-20 Insulation and Jacketing
17 PV Vents 0% 14 P300,000.00 10-Mar-20 27-Mar-20 PV Vents
OFFHORE 249 P26,900,000.00 02-Sep-19 20-Aug-20 20-Aug-20, OFFHORE
MOBILIZATION 29 P80,000.00 02-Sep-19 10-Oct-19 10-Oct-19, MOBILIZATION
18 NTP 0% 1 P0.00 02-Sep-19 02-Sep-19 NTP
19 Geotechnical Investigation 0% 14 P30,000.00 03-Sep-19 20-Sep-19 Geotechnical Investigation
20 Bathymetric Survey 0% 14 P50,000.00 23-Sep-19 10-Oct-19 Bathymetric Survey
ENGINEERING & PROCUREMENT 66 P0.00 03-Sep-19 03-Dec-19 03-Dec-19, ENGINEERING & PROCUREMENT
21 Design Issuance 0% 5 P0.00 03-Sep-19 09-Sep-19 Design Issuance
22 Shop Drawing Submittal and Approval 0% 38 P0.00 09-Sep-19 30-Oct-19 Shop Drawing Submittal and Approval
23 RFO and PO & Delivery All Materials 0% 58 P0.00 13-Sep-19 03-Dec-19 RFO and PO & Delivery All Materials
FABRICATION 104 P7,700,000.00 03-Sep-19 31-Jan-20 31-Jan-20, FABRICATION
24 Fabricate Hull 0% 90 P2,700,000.00 03-Sep-19 13-Jan-20 Fabricate Hull
25 Fabricate Spud Can 0% 60 P900,000.00 03-Sep-19 25-Nov-19 Fabricate Spud Can
26 Fabricate Legs 0% 65 P1,200,000.00 01-Oct-19 06-Jan-20 Fabricate Legs
27 Fabricate Derrick 0% 60 P1,400,000.00 08-Oct-19 06-Jan-20 Fabricate Derrick
28 Fabricate Helipad 0% 30 P1,500,000.00 12-Nov-19 23-Dec-19 Fabricate Helipad
29 Pre- Assembly of the structure 0% 14 P0.00 14-Jan-20 31-Jan-20 Pre- Assembly of the structure
LAUNCHING 158 P19,120,000.00 14-Jan-20 20-Aug-20 20-Aug-20, LAUNCHING
30 Install Helipad 0% 5 P3,700,000.00 14-Jan-20 20-Jan-20 Install Helipad
32 Install Pipes 0% 50 P0.00 03-Feb-20 10-Apr-20 Install Pipes
33 Architectural Works 0% 50 P0.00 03-Feb-20 10-Apr-20 Architectural Works
31 Install Electrical Cables 0% 45 P1,600,000.00 03-Feb-20 03-Apr-20 Install Electrical Cables
34 Install Equipments 0% 14 P7,000,000.00 13-Apr-20 30-Apr-20 Install Equipments
35 Install Control and Instrumentation 0% 14 P4,700,000.00 13-Apr-20 30-Apr-20 Install Control and Instrumentation
36 Launch Rig Structure ( Prior for Testing ) 0% 45 P120,000.00 01-May-20 02-Jul-20 Launch Rig Structure ( Prior for Testing )
37 Soil Inprovements 0% 5 P1,300,000.00 03-Jul-20 09-Jul-20 Soil Inprovements
38 Offshore Dredging 0% 14 P700,000.00 10-Jul-20 29-Jul-20 Offshore Dredging
39 Tranport Spud Scan & Fix ( Final Destination ) 0% 5 P0.00 30-Jul-20 05-Aug-20 Tranport Spud Scan & Fix ( Final Destination )
40 Transport Rig structure & Final Fix ( Final Destination ) 0% 2 P0.00 06-Aug-20 07-Aug-20 Transport Rig structure & Final Fix ( Final Destination )

Project Baseline Bar Actual Work Critical Remaining Work Page 1 of 2 TASK filter: All Activities

Primary Baseline Remaining Work Milestone © Oracle Corporation


JACK UP RIGS 3A UPDATE 07-Oct-19 12:51

Activity ID Activity Name Activity % Original Budgeted Total Start Finish 2020 2021
Complete Duration Cost
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
41 Final Testing and Commisioning 0% 7 P0.00 10-Aug-20 18-Aug-20 Final Testing and Commisioning
42 Hand Over to Drilling Team 0% 2 P0.00 19-Aug-20 20-Aug-20 Hand Over to Drilling Team

Project Baseline Bar Actual Work Critical Remaining Work Page 2 of 2 TASK filter: All Activities

Primary Baseline Remaining Work Milestone © Oracle Corporation