Overall Project Progress

Status As Off: 15-Sep-22


Weight Progress during Reporting
Factors Previous Cumulative Progress (%) Period (%) Cumulative Progress (%) Variance Completion Date
Sr.
No. Activity
Description Previous
  Recovery Base Plan Recovery Base Plan Recovery Base Plan Recovery Early Plan Recovery
Level-1 Plan Actual Actual Actual Actual
Plan (Early) Plan (Early) Plan (Early) Plan Plan
(Early)

1 GENERAL 10% 75.00% 75.00% 75.00% 0.00% 0.00% 0.00% 75.00% 75.00% 75.00% 0.00% 0.00% 1-May-23 1-May-23  

2 ENGINEERING 5% 100.00% 88.40% 87.18% 0.00% 4.12% 0.75% 100.00% 92.52% 87.93% -12.07% -4.59% 7-Mar-22 5-Oct-22  

PROCUREME
3
NT 40% 100.00% 81.32% 82.53% 0.00% 0.89% 1.75% 100.00% 82.21% 84.28% -15.72% 2.07% 28-Jul-22 18-Jan-23  

CONSTRUCTI
ON & Pre-
4
COMMISSIOI 35% 49.58% 1.23% 1.23% 1.39% 0.00% 0.00% 50.97% 1.23% 1.23% -49.74% 0.00% 27-Apr-23 6-Apr-23  
NG

COMMISSION
5 ING & CLOSE 10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1-May-23 1-May-23  
OUT

Overall Progress % 100% 69.85% 44.88% 45.30% 0.49% 0.56% 0.74% 70.34% 45.44% 46.04% -24.30% 0.60%      

We Engineer, We Manufacture, We Deliver 10


Total Solutions in EPCM
3-Week Look Ahead Plan

Activity Original Recovery Plan Recovery Plan


Activity Name
ID Duration Start Finish

CONSTRUCTION & PRE-COMMISSIONING 205 10-Aug-22 06-Apr-23


SHOP FABRICATION / GENERAL 123 10-Aug-22 01-Jan-23
CIVIL PRECAST WORKS 28 10-Aug-22 12-Sep-22
PW-CP-FAB-CS-0010
Precas ting for Pipe Support & Foundations 24 10-Aug-22 07-Sep-22
PW-CP-FAB-CS-0020
Del i very to si te l ocation 26 13-Aug-22 12-Sep-22
STEEL STRUCTURE 38 17-Aug-22 01-Oct-22
PW-CP-FAB-CS-0030
Fabrication and Weldi ng 25 17-Aug-22 15-Sep-22
PW-CP-FAB-CS-0040
Vi s ual ins pection 25 23-Aug-22 21-Sep-22
PW-CP-FAB-CS-0050
NDT 25 25-Aug-22 24-Sep-22
PW-CP-FAB-CS-0060
Bl asting and Pai nting 15 11-Sep-22 28-Sep-22
PW-CP-FAB-CS-0070
Del i very to si te 15 13-Sep-22 01-Oct-22
PIPING 95 13-Sep-22 01-Jan-23
PW-CP-FAB-PI-0010
Pi pe Spool Fabri cation and weldi ng 60 13-Sep-22 21-Nov-22
PW-CP-FAB-PI-0020
Vi s ual ins pection 60 19-Sep-22 27-Nov-22
PW-CP-FAB-PI-0030
NDT 60 25-Sep-22 03-Dec-22
PW-CP-FAB-PI-0040
Press ure Tes t 60 01-Oct-22 08-Dec-22
PW-CP-FAB-PI-0050
Bl asting and Pai nting 60 12-Oct-22 20-Dec-22
STORAGE TANKS & INTERCONNECTING CORRIDOR 156 06-Oct-22 06-Apr-23
CONSTRUCTION 119 06-Oct-22 22-Feb-23
INTERCONNECTING CORRIDOR 119 06-Oct-22 22-Feb-23
INTERCONNECTING PIPE RACK AREA 117 09-Oct-22 22-Feb-23
CIVIL WORKS 45 09-Oct-22 30-Nov-22
PW-CP-T-C-CS-0010
Excavation 25 09-Oct-22 07-Nov-22
PW-CP-T-C-CS-0012
Pre-Cast of Foundation & Del ivery 25 09-Oct-22 07-Nov-22
BUTANE STORAGE CORRIDOR 119 06-Oct-22 22-Feb-23
CIVIL WORKS 46 06-Oct-22 29-Nov-22
0500760-CP-T-C-00610
Excavation 20 06-Oct-22 30-Oct-22
0500760-CP-T-C-00612
Pre-Cast of Foundation & Del ivery 30 06-Oct-22 10-Nov-22
0500760-CP-T-C-00615
Blinding 30 11-Oct-22 15-Nov-22
11
Total Solutions in EPCM
3-Week Look Ahead Plan

Activity Original Recovery Plan Recovery Plan


Activity Name
ID Duration Start Finish

UTILITIES 161 01-Oct-22 06-Apr-23


CONSTRUCTION 124 01-Oct-22 22-Feb-23
UTILITY AREA 124 01-Oct-22 22-Feb-23
CIVIL WORKS 27 01-Oct-22 01-Nov-22
PW-CP-U-C-CS-0010
Excavation 14 01-Oct-22 17-Oct-22
PW-CP-U-C-CS-0012
Pre-Cast of Foundation & Delivery 14 01-Oct-22 17-Oct-22
PW-CP-U-C-CS-0015
Blinding 14 04-Oct-22 20-Oct-22
PW-CP-U-C-CS-0020
Coating 14 08-Oct-22 24-Oct-22
PW-CP-U-C-CS-0030
Installation of Foundation 14 12-Oct-22 29-Oct-22
PURE PROPANE 114 12-Oct-22 22-Feb-23
CIVIL WORKS 32 12-Oct-22 19-Nov-22
0500760-CP-T-C-00380
Excavation 20 12-Oct-22 05-Nov-22
0500760-CP-T-C-00382
Pre-Cast of Foundation & Delivery 20 12-Oct-22 05-Nov-22
CAUSTIC STORAGE 114 12-Oct-22 22-Feb-23
CIVIL WORKS 38 12-Oct-22 26-Nov-22
PW-CP-T-C-PI-1140
Excavation 15 12-Oct-22 30-Oct-22
PW-CP-T-C-PI-1142
Pre-Cast of Foundation & Delivery 15 12-Oct-22 30-Oct-22
SRU 149 12-Oct-22 04-Apr-23
CONSTRUCTION 114 12-Oct-22 22-Feb-23
CIVIL WORKS 45 12-Oct-22 04-Dec-22
PW-CP-SRU-C-CS-0010
Excavation 20 12-Oct-22 05-Nov-22
PW-CP-SRU-C-CS-0012
Pre-Cast of Foundation & Delivery 20 12-Oct-22 05-Nov-22

11
Total Solutions in EPCM
Look Ahead Plan-SS Long Run

SS-Erection Plan   Remarks


Discipline Description Start Finish
  Long Run aprox. 01 km      
  Pipe Delivery at HIC Coating Vendor (Long Run Pipes)   19-Sep-22 Completed
  Delivery of Paints Material   24-Sep-22  
  Start of Coating Work 25-Sep-22    
  Completion of Coating (Lot wise)   02-Oct-22  
  Delivery of HIC Coated Spools to site   03-Oct-22  
  Start of Fabrication for Long Run SS Pipes 04-Oct-22    

11
Total Solutions in EPCM
PLANNING AND PROJECT CONTROL

Activities Planned (Week 60) Activities Planned (Week 61)


14/09/2022 – 20/09/2022 21/09/2022 – 27/09/2022

 Follow up with engineering and other  To submit the Weekly Report.


subcontractors.
 Submitted the Official Invoice#011 (Aug-2022)
for COMPANY Approval.
 Submitted the Construction Register for
COMPANY Approval

We Engineer, We Manufacture, We Deliver 12


Total Solutions in EPCM
ENGINEERING PROGRESS SUMMARY

DISCIPLINE WISE PROGRESS SUMMARY

Status As Off: 15-Sep-22

Progress Progress
Prv. Cum. Progress % This Report Progress % To-date Cum. Progress % Remarks
SL. No. Activity description Count Wtg% Variance % Variance %

Plan Forecast Actual Plan Forecast Actual Plan Forecast Actual Base Plan Forecast

1 Common Documents 12 7.56% 100.00% 100.00% 100.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 0.00% 0.00%

2 Process 120 10.73% 100.00% 92.87% 91.39% 0.00% 1.66% 0.01% 100.00% 94.52% 91.40% -8.60% -3.12%

3 Piping 427 53.12% 100.00% 86.90% 85.20% 0.00% 5.21% 1.13% 100.00% 92.11% 86.33% -13.67% -5.77%

4 Instrumentation & Control 56 7.62% 100.00% 92.90% 97.64% 0.00% 0.91% 0.00% 100.00% 93.81% 97.64% -2.36% 3.83%

5 Civil & Structural 186 16.86% 100.00% 81.63% 77.39% 0.00% 6.48% 0.89% 100.00% 88.11% 78.27% -21.73% -9.84%

6 HSE 11 4.11% 100.00% 94.19% 99.03% 0.00% 0.40% 0.00% 100.00% 94.60% 99.03% -0.97% 4.44%

Total Progress % 812 100.00% 100.00% 88.40% 87.18% 0.00% 4.12% 0.75% 100.00% 92.52% 87.93% -12.07% -4.59%