2nd Floor
Section Grid Activity Duration Start Finish
Days
4-7/C-E Formwork 4 1/16/2015 1/19/2015
Reinforcement 3 1/19/2015 1/21/2015
1st Fix Elect.,Mech. 2 1/21/2015 1/22/2015
Inspection 1 1/23/2015 1/23/2015
Concrete 1 1/24/2015 1/24/2015
3rd. Floor
Section Grid
4-7/H-N Formwork 4 1/17/2015 1/20/2015
Reinforcement 3 1/20/2015 1/22/2015
1st Fix Elect.,Mech. 2 1/22/2015 1/23/2015
Inspection 1 1/24/2015 1/24/2015
Concrete 1 1/25/2015 1/25/2015