Section Grid Activity Duration Start Finish
Days
4-7/C-E Formwork 4 1/16/2015 1/19/2015
Reinforcement 3 1/19/2015 1/21/2015
1st Fix Elect.,Mech. 2 1/21/2015 1/22/2015
Inspection 1 1/23/2015 1/23/2015
Concrete 1 1/24/2015 1/24/2015

4-7/A-C Formwork 4 1/19/2015 1/22/2015


Reinforcement 3 1/22/2015 1/24/2015
1st Fix Elect.,Mech. 2 1/24/2015 1/25/2015
Inspection 1 1/26/2010 1/26/2015
Concrete 1 1/27/2015 1/27/2015

4-7/C-C1 Formwork 4 1/20/2015 1/23/2015


Reinforcement 3 1/23/2015 1/25/2015
1st Fix Elect.,Mech. 2 1/25/2015 1/26/2015
Inspection 1 1/27/2015 1/27/2015
Concrete 1 1/28/2015 1/28/2015

3rd. Floor
Section Grid
4-7/H-N Formwork 4 1/17/2015 1/20/2015
Reinforcement 3 1/20/2015 1/22/2015
1st Fix Elect.,Mech. 2 1/22/2015 1/23/2015
Inspection 1 1/24/2015 1/24/2015
Concrete 1 1/25/2015 1/25/2015

4-7/F-H Formwork 4 1/18/2015 1/21/2015


Reinforcement 3 1/21/2015 1/23/2015
1st Fix Elect.,Mech. 2 1/23/2015 1/24/2015
Inspection 1 1/25/2015 1/25/2015
Concrete 1 1/26/2015 1/26/2015

4-7/D-F Formwork 4 1/23/2015 1/26/2015


Reinforcement 3 1/26/2015 1/28/2015
1st Fix Elect.,Mech. 2 1/28/2015 1/29/2015
Inspection 1 1/30/2015 1/30/2015
Concrete 1 1/31/2015 1/31/2015

4-7/B-D Formwork 4 1/25/2015 1/28/2015


Reinforcement 3 1/28/2015 1/30/2015
1st Fix Elect.,Mech. 2 1/30/2015 1/31/2015
Inspection 1 2/1/2015 2/1/2015
Concrete 1 2/2/2015 2/2/2015

4-7/C1-B Formwork 4 2/2/2015 2/5/2015


Reinforcement 3 2/5/2015 2/7/2015
1st Fix Elect.,Mech. 2 2/7/2015 2/8/2015
Inspection 1 2/9/2015 2/9/2015
Concrete 1 2/10/2015 2/10/2015