KAFD-CP-Revised Schedule.03-2024.03.

13 Revised Baseline 17-Mar-24 12:09


Activity ID Activity Name Original Start Finish 2022 2023 2024 2025
Duration
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O
KAFD-CP-Revised Schedule.03-2024.03.13 195 18-Nov-23 A 22-Jul-24 22-Jul-24, KAFD-CP-Revised Schedule.03-2024.03.13

Construction 195 18-Nov-23 A 22-Jul-24 22-Jul-24, Construction

Subterranean Tunnel Wall Supporting System 195 18-Nov-23 A 22-Jul-24 22-Jul-24, Subterranean Tunnel Wall Supporting System
Existing Conditions 54 18-Nov-23 A 10-Feb-24 A 10-Feb-24 A, Existing Conditions
PL106.CO.TW.GE.380 Site Preparation and Road Closure 12 18-Nov-23 A 26-Nov-23 A Site Preparation and Road Closure
P106.CO.TW.SW.384 Demolish Existing CMU Wall under Normal Working Conditions 12 03-Dec-23 A 10-Dec-23 A Demolish Existing CMU Wall under Normal Working Conditions
P106.CO.TW.SW.382 Geotechnical Investigation under Normal Working Conditions 30 27-Dec-23 A 10-Feb-24 A Geotechnical Investigation under Normal Working Conditions
Commercial Proposal 6 14-Mar-24 20-Mar-24 20-Mar-24, Commercial Proposal
P106.CO.TW.SW.381 Prepare and Submit Commercial Proposal for Adequate Supporting System 6 14-Mar-24 20-Mar-24 Prepare and Submit Commercial Proposal for Adequate Supporting System
Construction 85 02-Mar-24 A 22-Jul-24 22-Jul-24, Construction
1.07 85 03-Apr-24 22-Jul-24 22-Jul-24, 1.07
PL107.CO.TW.SW.400 Excavation for Tunnel Support System Plot 1.07 6 03-Apr-24 15-Apr-24 Excavation for Tunnel Support System Plot 1.07
PL107.CO.TW.SW.410 Blinding Concrete for Tunnel Support System Plot 1.07 1 15-Apr-24 16-Apr-24 Blinding Concrete for Tunnel Support System Plot 1.07
PL107.CO.TW.SW.420 Formwork & Steel Rienforcement of Foundation for Tunnel Support System Plot 1.07 12 16-Apr-24 30-Apr-24 Formwork & Steel Rienforcement of Foundation for Tunnel Support Syste
PL107.CO.TW.SW.430 Pouring Foundation Tunnel Support System Plot 1.07 1 30-Apr-24 01-May-24 Pouring Foundation Tunnel Support System Plot 1.07
PL107.CO.TW.SW.440 Formwork & Steel Rienforcement of Wall 1st stage for Tunnel Support System Plot 1.07 18 01-May-24 22-May-24 Formwork & Steel Rienforcement of Wall 1st stage for Tunnel Support
PL107.CO.TW.SW.450 Pouring of Wall 1st stage Tunnel Support System Plot 1.07 1 22-May-24 23-May-24 Pouring of Wall 1st stage Tunnel Support System Plot 1.07
PL107.CO.TW.SW.460 Formwork & Steel Rienforcement of Wall 2nd stage System Plo t 1.07 12 23-May-24 06-Jun-24 Formwork & Steel Rienforcement of Wall 2nd stage System Plo t 1.0
PL107.CO.TW.SW.470 Pouring of Wall 2nd stage Tunnel Support System Plot Plot 1.07 1 06-Jun-24 08-Jun-24 Pouring of Wall 2nd stage Tunnel Support System Plot Plot 1.07
PL107.CO.TW.SW.480 Formwork, Steel Reinforcement & Pouring of Wall Upstand for Tunnel Support System Plot Plot61.07
08-Jun-24 19-Jun-24 Formwork, Steel Reinforcement & Pouring of Wall Upstand for Tun
PL107.CO.TW.SW.490 Insulation Works Wall & Foundation Tunnel Support System Plot Plot 1.07 18 19-Jun-24 11-Jul-24 Insulation Works Wall & Foundation Tunnel Support System Plo
PL107.CO.TW.SW.500 Rockfill for Wall & Foundation Tunnel Support System Plot Plot 1.07 9 11-Jul-24 22-Jul-24 Rockfill for Wall & Foundation Tunnel Support System Plot Plo
1.06 83 02-Mar-24 A 20-Jul-24 20-Jul-24, 1.06
PL106.CO.TW.SW.400 Excavation for Tunnel Support System Plot 1.06 6 02-Mar-24 A 08-Apr-24 Excavation for Tunnel Support System Plot 1.06
PL106.CO.TW.SW.410 Blinding Concrete for Tunnel Support System Plot 1.06 1 08-Apr-24 09-Apr-24 Blinding Concrete for Tunnel Support System Plot 1.06
PL106.CO.TW.SW.420 Formwork & Steel Rienforcement of Foundation for Tunnel Support System Plot 1.06 12 15-Apr-24 28-Apr-24 Formwork & Steel Rienforcement of Foundation for Tunnel Support Syste
PL106.CO.TW.SW.430 Pouring Foundation Tunnel Support System Plot 1.06 1 29-Apr-24 29-Apr-24 Pouring Foundation Tunnel Support System Plot 1.06
PL106.CO.TW.SW.440 Formwork & Steel Rienforcement of Wall 1st stage for Tunnel Support System Plot 1.06 18 30-Apr-24 20-May-24 Formwork & Steel Rienforcement of Wall 1st stage for Tunnel Support
PL106.CO.TW.SW.450 Pouring of Wall 1st stage Tunnel Support System Plot 1.06 1 21-May-24 21-May-24 Pouring of Wall 1st stage Tunnel Support System Plot 1.06
PL106.CO.TW.SW.460 Formwork & Steel Rienforcement of Wall 2nd stage System Plo t 1.06 12 22-May-24 04-Jun-24 Formwork & Steel Rienforcement of Wall 2nd stage System Plot 1.0
PL106.CO.TW.SW.470 Pouring of Wall 2nd stage Tunnel Support System Plot 1.06 1 05-Jun-24 05-Jun-24 Pouring of Wall 2nd stage Tunnel Support System Plot 1.06
PL106.CO.TW.SW.480 Formwork, Steel Reinforcement & Pouring of Wall Upstand for Tunnel Support System Plot 1.066 06-Jun-24 12-Jun-24 Formwork, Steel Reinforcement & Pouring of Wall Upstand for Tun
PL106.CO.TW.SW.490 Insulation Works Wall & Foundation Tunnel Support System Plot 1.06 18 13-Jun-24 09-Jul-24 Insulation Works Wall & Foundation Tunnel Support System Plo
PL106.CO.TW.SW.500 Rockfill for Wall & Foundation Tunnel Support System Plot 1.06 9 10-Jul-24 20-Jul-24 Rockfill for Wall & Foundation Tunnel Support System Plot 1.06

Remaining Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: Engineering.
Actual Work Critical Remaining Work Summary © Oracle Corporation