G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:22

Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
(New EPS) 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d 26-May-25, (New EPS)

G+P+6 residential and Retail building Baseline-Corrected 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d 26-May-25, G+P+6 residential a

Project Engineering and Construction 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d 26-May-25, Project Engineering
A1000 Project Start Milestone 0d 24-May-23 23-May-23 0d Project Start Milestone, 24-May-23
A2900 Project finish miestone 0d 26-May-25 24-May-25 0d Project finish miestone,
NOC/Permit 0d 24-May-23 24-May-23 23-May-23 23-May-23 0d 24-May-23, NOC/Permit
NOC/Permit Obtaining Construction NOC from Nakheel 0d 24-May-23 23-May-23 0d Obtaining Construction NOC from Nakheel, 24-May-23
Major Milestone 605d 09-Jun-23 26-May-25 24-May-25 24-May-25 0d 26-May-25, Major Milestone
MM-Mob-1010 Completion of Excavation & Earthwork 0d 09-Jun-23 24-May-25 605d Completion of Excavation & Earthwork,
MM-Mob-1020 Completion of Sub-Structure 0d 29-Jul-23 24-May-25 565d Completion of Sub-Structure,
MM-Mob-1030 Completion of Super-Structure 0d 11-Apr-24 24-May-25 346d Completion of Super-Structure,
MM-Mob-1040 Completion of Block Works & MEP 1st Fix 0d 18-Apr-24 24-May-25 341d Completion of Block Works & MEP 1st Fix,
MM-Mob-1060 Completion of MEP 2nd Fix 0d 25-Jun-24 24-May-25 283d Completion of MEP 2nd Fix,
MM-Mob-1070 Completion of Ceiling Finishes Works 0d 05-Sep-24 24-May-25 220d Completion of Ceiling Finishes Works,
MM-Mob-1050 Completion of Plaster Works 0d 14-Sep-24 24-May-25 213d Completion of Plaster Works,
MM-Mob-1080 Completion of Wall Finishes Works 0d 26-Sep-24 24-May-25 202d Completion of Wall Finishes Works,
MM-Mob-1090 Completion of Floor Finishes Works 0d 03-Apr-25 24-May-25 45d Completion of Floor Finishes Works,
MM-Mob-1110 Completion of Carpentary & Joinery Works 0d 23-Apr-25 24-May-25 28d Completion of Carpentary & Joinery W
MM-Mob-1100 Completion of Paint Works 0d 17-May-25 24-May-25 7d Completion of Paint Works,
MM-Mob-1120 Completion of MEP 3rd Fix 0d 17-May-25 24-May-25 7d Completion of MEP 3rd Fix,
MM-Mob-1130 Completion of Provisional Sum Works 0d 23-May-25 24-May-25 2d Completion of Provisional Sum W
MM-Mob-1000 Completion of Preliminaries 0d 26-May-25 24-May-25 0d Completion of Preliminaries,
Engineering & Procurement 524d 24-May-23 01-Feb-25 23-May-23 13-May-25 86d 01-Feb-25, Engineering & Procurement
Civil Works & Finishes Submittals 352d 24-May-23 11-Jul-24 23-May-23 30-Sep-24 69d 11-Jul-24, Civil Works & Finishes Submittals
Reinforcement Works 10d 24-May-23 04-Jun-23 31-May-23 11-Jun-23 6d 04-Jun-23, Reinforcement Works
E-PQ-1020 PQ Submission of Reinforcement Steel 1d 24-May-23 24-May-23 31-May-23 31-May-23 6d PQ Submission of Reinforcement Steel
E-PQ-1030 Review and Approval of PQ Submission of Reinforcement
2d 25-May-23
Steel 26-May-23 01-Jun-23 02-Jun-23 5d Review and Approval of PQ Submission of Reinforcement Steel
E-MS-1020 Material Submittal for Reinforcement Steel 1d 27-May-23 27-May-23 03-Jun-23 05-Jun-23 6d Material Submittal for Reinforcement Steel
E-MS-1030 Review and Approval of Material Submittal for Reinforcement
2d 29-May-23
Steel 30-May-23 05-Jun-23 07-Jun-23 5d Review and Approval of Material Submittal for Reinforcement Steel
E-SD-1040 Submission of Shop Drawing & Method Statement of2dReinforcement
31-May-23 01-Jun-23 07-Jun-23 09-Jun-23 6d Submission of Shop Drawing & Method Statement of Reinforcement
E-SD-1130 Approval of Shop Drawing & Method Statement of reinforcement
2d 31-May-23 01-Jun-23 07-Jun-23 09-Jun-23 5d Approval of Shop Drawing & Method Statement of reinforcement
E-Procure-1750 Order Palced for Reinforcement 1d 02-Jun-23 02-Jun-23 09-Jun-23 10-Jun-23 6d Order Palced for Reinforcement
E-Procure-1760 Start of Delivery progress at site 2d 03-Jun-23 04-Jun-23 10-Jun-23 11-Jun-23 7d Start of Delivery progress at site
Concrete Works 7d 24-May-23 31-May-23 30-May-23 06-Jun-23 5d 31-May-23, Concrete Works
E-PQ-1040 PQ Submission of Concrete 1d 24-May-23 24-May-23 30-May-23 31-May-23 5d PQ Submission of Concrete
E-PQ-1050 Review and Approval of PQ Submission of Concrete1d 25-May-23 25-May-23 31-May-23 01-Jun-23 4d Review and Approval of PQ Submission of Concrete
E-MS-1040 Material Submittal of Concrete 1d 26-May-23 26-May-23 01-Jun-23 02-Jun-23 5d Material Submittal of Concrete
E-MS-1050 Review and Approval of Material Submittal of Concrete
1d 29-May-23 29-May-23 02-Jun-23 05-Jun-23 4d Review and Approval of Material Submittal of Concrete
E-Procure-1770 Order Palced for Concrete 1d 30-May-23 30-May-23 05-Jun-23 06-Jun-23 5d Order Palced for Concrete
E-Procure-1780 Start of Delivery progress at site 1d 31-May-23 31-May-23 06-Jun-23 06-Jun-23 6d Start of Delivery progress at site
Post Tension Works 30d 24-May-23 30-Jun-23 31-Jul-23 04-Sep-23 57d 30-Jun-23, Post Tensio n Works
E-PQ-1060 PQ Submission of Post Tension Vendor 3d 24-May-23 26-May-23 31-Jul-23 02-Aug-23 56d PQ Submission of Post Tension Vendor
E-PQ-1070 Review and Approval of PQ Submission of Post Tension
2d 29-May-23
Vendor 30-May-23 03-Aug-23 04-Aug-23 46d Review and Approval of PQ Submission of Post Tension Vendor
E-MS-1060 Material Submittal of Post Tension Cable s 3d 31-May-23 02-Jun-23 05-Aug-23 08-Aug-23 55d Material Submittal of Post Tension Cable s
E-MS-1070 Review and Approval of Material Submission of Post3d
Tension
05-Jun-23
Cables 07-Jun-23 09-Aug-23 11-Aug-23 45d Review and Approval of Material Submission of Post Tension Cables
E-SD-1220 Submission of Shop Drawing & Method Statement of4dPost
08-Jun-23
tensioning 12-Jun-23 12-Aug-23 17-Aug-23 55d Submission of Shop Drawing & Method Statement of Post tensioning
E-SD-1300 Approval of Shop Drawing & Method Statement of Post
3d tensioning
13-Jun-23 Drawing
15-Jun-23
- Consultant
17-Aug-23 22-Aug-23 46d Approval of Shop Drawing & Method Statement of Post tensioning Drawing - Consultant
E-SD-1303 Post Tension drawing- Authoority Submission and Approval
4d 16-Jun-23 21-Jun-23 22-Aug-23 28-Aug-23 46d Post Tension drawing- Authoority Submission and Approval
E-Procure-1790 Order Palced Post Tensioning 4d 22-Jun-23 26-Jun-23 28-Aug-23 01-Sep-23 56d Order Palced Post Tensioning
E-Procure-1800 Start of Delivery progress at site 3d 27-Jun-23 30-Jun-23 01-Sep-23 04-Sep-23 67d Start of Delivery progress at site
Construction Chemicals Works 4d 24-May-23 28-May-23 31-May-23 05-Jun-23 7d 28-May-23, Construction Chemicals Works

Actual Level of Effort Remaining Work Milestone Page 1 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:22
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
E-PQ-1080 PQ Submission of Construction Chemicals 1d 24-May-23 24-May-23 31-May-23 31-May-23 6d PQ Submission of Construction Chemicals
E-PQ-1090 Review and Approval of PQ Submission of Construction
1d Chemicals
25-May-23 25-May-23 01-Jun-23 01-Jun-23 5d Review and Approval of PQ Submission of Construction Chemicals
E-MS-1080 Material Submittal of Construction Chemicals 1d 25-May-23 25-May-23 01-Jun-23 01-Jun-23 6d Material Submittal of Construction Chemicals
E-MS-1090 Review and Approval of Material Submittal of Construction
1d 26-May-23
Chemicals 26-May-23 02-Jun-23 02-Jun-23 5d Review and Approval of Material Submittal of Construction Chemicals
E-Procure-1810 Order Palced fo Construction Chemicals 1d 27-May-23 27-May-23 03-Jun-23 05-Jun-23 6d Order Palced fo Construction Chemicals
E-Procure-1820 Start of Delivery progress at site 1d 28-May-23 28-May-23 05-Jun-23 05-Jun-23 8d Start of Delivery progress at site
Thermal and Moisture Protection Works 7d 24-May-23 31-May-23 30-May-23 06-Jun-23 5d 31-May-23, Thermal and Moisture Protection Works
E-PQ-1100 PQ Submission of Thermal & Moisture Protection Works
1d 24-May-23 24-May-23 30-May-23 31-May-23 5d PQ Submission of Thermal & Moisture Protection Works
E-PQ-1110 Review and Approval of PQ Submission of Thermal &1dMoisture
25-May-23
Protection
25-May-23
Works 31-May-23 01-Jun-23 4d Review and Approval of PQ Submission of Thermal & Moisture Protection Works
E-MS-1100 Material Submittal of Thermal and Moisture Protection
1dWorks
25-May-23 25-May-23 31-May-23 01-Jun-23 5d Material Submittal of Thermal and Moisture Protection Works
E-MS-1110 Review and Approval of Material Submittal of Thermal
1dand
26-May-23
Moisture Protection
26-May-23
Works01-Jun-23 02-Jun-23 4d Review and Approval of Material Submittal of Thermal and Moisture Protection Works
E-SD-1310 Submission of Shop Drawing & Method Statement of1dThermal
26-May-23
& Moisture
26-May-23
Protection 01-Jun-23
Works 02-Jun-23 5d Submission of Shop Drawing & Method Statement of Thermal & Moisture Protection Works
E-SD-1340 Approval of Shop Drawing & Method Statement of Thermal
1d 29-May-23
& Moisture 29-May-23
Protection Works
02-Jun-23 05-Jun-23 4d Approval of Shop Drawing & Method Statement of Thermal & Moisture Protection Works
E-Procure-1830 Order Palced for Thermal & Moisture Protection Works
1d 30-May-23 30-May-23 05-Jun-23 06-Jun-23 5d Order Palced for Thermal & Moisture Protection Works
E-Procure-1840 Start of Delivery progress at site 1d 31-May-23 31-May-23 06-Jun-23 06-Jun-23 6d Start of Delivery progress at site
Formwork 16d 24-May-23 12-Jun-23 23-May-23 11-Jun-23 0d 12-Jun-23, Formwork
E-PQ-1120 PQ Submission of Formwork 3d 24-May-23 26-May-23 23-May-23 26-May-23 0d PQ Submission of Formwork
E-PQ-1130 Review and Approval of PQ Submission of Formwork2d 29-May-23 30-May-23 26-May-23 30-May-23 0d Review and Approval of PQ Submission of Formwork
E-MS-1120 Material Submittal of Formworks 2d 31-May-23 01-Jun-23 30-May-23 01-Jun-23 0d Material Submittal of Formworks
E-MS-1130 Review and Approval of Material Submittal of Formworks
3d 02-Jun-23 06-Jun-23 01-Jun-23 06-Jun-23 0d Review and Approval of Material Submittal of Formworks
E-Procure-1850 Order Palced for Formwork 2d 07-Jun-23 08-Jun-23 06-Jun-23 08-Jun-23 0d Order Palced for Formwork
E-Procure-1860 Start of Delivery progress at site 3d 09-Jun-23 12-Jun-23 08-Jun-23 11-Jun-23 0d Start of Delivery progress at site
Cement 7d 24-May-23 31-May-23 30-May-23 06-Jun-23 5d 31-May-23, Cement
E-PQ-1140 PQ Submission of Cement Vendors 1d 24-May-23 24-May-23 30-May-23 31-May-23 5d PQ Submission of Cement Vendors
E-PQ-1150 Review and Approval of PQ Submission of Cement Vendors
1d 25-May-23 25-May-23 31-May-23 01-Jun-23 4d Review and Approval of PQ Submission of Cement Vendors
E-MS-1140 Material Submittal of Cement 1d 26-May-23 26-May-23 01-Jun-23 02-Jun-23 5d Material Submittal of Cement
E-MS-1150 Review and Approval of Material Submittal of Cement
1d 29-May-23 29-May-23 02-Jun-23 05-Jun-23 4d Review and Approval of Material Submittal of Cement
E-Procure-1870 Order Palced for Cement 1d 30-May-23 30-May-23 05-Jun-23 06-Jun-23 5d Order Palced for Cement
E-Procure-1880 Start of Delivery progress at site 1d 31-May-23 31-May-23 06-Jun-23 06-Jun-23 6d Start of Delivery progress at site
Block and Plaster Works 100d 31-May-23 27-Sep-23 20-Jun-23 07-Dec-23 61d 27-Sep-23, Block and Plaster Works
E-PQ-1180 PQ Submission of Block & Plester Works 7d 31-May-23 08-Jun-23 20-Jun-23 27-Jun-23 16d PQ Submission of Block & Plester Works
E-PQ-1190 Review and Approval of PQ Submission of Block & Plester
7d 08-Jun-23
Works 19-Jun-23 30-Jun-23 10-Jul-23 13d Review and Approval of PQ Submission of Block & Plester Works
E-MS-1180 Material Submittal of Block & Plaster Works 7d 19-Jun-23 27-Jun-23 11-Jul-23 18-Jul-23 16d Material Submittal of Block & Plaster Works
E-MS-1190 Review and Approval of Material Submittal of Block &5dPlaster
27-Jun-23
Works 06-Jul-23 19-Jul-23 25-Jul-23 13d Review and Approval of Material Submittal of Block & Plaster Works
E-SD-1370 Submission of Shop Drawing & Method Statement 12d
of Block
06-Jul-23
& Plaster Works
20-Jul-23 26-Jul-23 08-Aug-23 16d Submission of Shop Drawing & Method Statement of Block & Plaster Works
E-SD-1380 Approval of Shop Drawing & Method Statement of10d
Block20-Jul-23
& Plaster Works
03-Aug-23 09-Aug-23 22-Aug-23 13d Approval of Shop Drawing & Method Statement of Block & Plaster Works
E-Procure-1910 Order Palced for Block & Plaster Works 4d 03-Aug-23 08-Aug-23 23-Aug-23 26-Aug-23 16d Order Palced for Block & Plaster Works
E-Procure-1920 Start of Delivery progress at site 4d 23-Sep-23 27-Sep-23 04-Dec-23 07-Dec-23 71d Start of Delivery progress at site
Tiling Works 222d 08-Aug-23 25-Apr-24 28-Aug-23 15-May-24 17d 25-Apr-24, Tiling Works
E-PQ-1200 PQ Submission of Tilling Works 15d 08-Aug-23 25-Aug-23 28-Aug-23 13-Sep-23 16d PQ Submission of Tilling Works
E-PQ-1210 Review and Approval of PQ Submission of Tilling Works
10d 25-Aug-23 08-Sep-23 14-Sep-23 27-Sep-23 13d Review and Approval of PQ Submission of Tilling Works
E-MS-1200 Material Submittal of Tiling Work 15d 08-Sep-23 26-Sep-23 28-Sep-23 14-Oct-23 16d Material Submittal of Tiling Work
E-MS-1210 Review and Approval of Material Submittal of Tiling 10d
Work26-Sep-23 10-Oct-23 16-Oct-23 27-Oct-23 13d Review and Approval of Material Submittal of Tiling Work
E-SD-1390 Submission of Shop Drawing & Method Statement 10d
of Tilling
10-Oct-23
Works 21-Oct-23 30-Oct-23 09-Nov-23 16d Submission of Shop Drawing & Method Statement of Tilling Works
E-SD-1480 Approval of Shop Drawing & Method Statement of10d
Tilling23-Oct-23
Works 03-Nov-23 10-Nov-23 23-Nov-23 14d Approval of Shop Drawing & Method Statement of Tilling Works
E-Procure-1930 Order Palced for Tiling Works 10d 04-Nov-23 15-Nov-23 24-Nov-23 05-Dec-23 17d Order Palced for Tiling Works
E-Procure-1940 Start of Delivery progress at site 20d 06-Apr-24 25-Apr-24 26-Apr-24 15-May-24 20d Start of Delivery progress at site
Paint Works 130d 16-Nov-23 17-Apr-24 11-Dec-23 21-Jun-24 56d 17-Apr-24, Paint Works
E-PQ-1240 PQ Submission of Paint Works 10d 16-Nov-23 27-Nov-23 11-Dec-23 21-Dec-23 21d PQ Submission of Paint Works
E-PQ-1250 Review and Approval of PQ Submission of Paint Works
10d 28-Nov-23 11-Dec-23 22-Dec-23 04-Jan-24 18d Review and Approval of PQ Submission of Paint Works
E-MS-1240 Material Submittal of Paint Works 15d 12-Dec-23 28-Dec-23 05-Jan-24 22-Jan-24 20d Material Submittal of Paint Works

Actual Level of Effort Remaining Work Milestone Page 2 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:22
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
E-MS-1250 Review and Approval of Material Submittal of Paint 10d
Works
29-Dec-23 11-Jan-24 23-Jan-24 05-Feb-24 17d Review and Approval of Material Submittal of Paint Works
E-Procure-1970 Order Palced for Paint Works 10d 12-Jan-24 23-Jan-24 06-Feb-24 16-Feb-24 21d Order Palced for Paint Works
E-Procure-1980 Start of Delivery progress at site 20d 29-Mar-24 17-Apr-24 02-Jun-24 21-Jun-24 65d Start of Delivery progress at site
Ceiling Works 69d 24-Jan-24 14-Apr-24 17-Feb-24 07-May-24 20d 14-Apr-24, Ceiling Works
E-PQ-1220 PQ Submission of False Ceiling Works 7d 24-Jan-24 31-Jan-24 17-Feb-24 24-Feb-24 21d PQ Submission of False Ceiling Works
E-PQ-1230 Review and Approval of PQ Submission of False Ceiling
7d 01-Feb-24
Works 09-Feb-24 26-Feb-24 05-Mar-24 17d Review and Approval of PQ Submission of False Ceiling Works
E-MS-1220 Material Submittal of Ceiling Works 5d 10-Feb-24 15-Feb-24 06-Mar-24 12-Mar-24 21d Material Submittal of Ceiling Works
E-MS-1230 Review and Approval of Material Submittal of Ceiling5d
Works
16-Feb-24 22-Feb-24 13-Mar-24 19-Mar-24 17d Review and Approval of Material Submittal of Ceiling Works
E-SD-1570 Submission of Shop Drawing & Method Statement 10d
of Ceiling
23-Feb-24
Works 05-Mar-24 20-Mar-24 30-Mar-24 21d Submission of Shop Drawing & Method Statement of Ceiling Works
E-SD-1660 Approval of Shop Drawing & Method Statement of 15d
Ceiling
06-Mar-24
Works 27-Mar-24 01-Apr-24 19-Apr-24 17d Approval of Shop Drawing & Method Statement of Ceiling Works
E-Procure-1950 Order Palced Ceiling Works 4d 28-Mar-24 01-Apr-24 20-Apr-24 25-Apr-24 20d Order Palced Ceiling Works
E-Procure-1960 Start of Delivery progress at site 13d 02-Apr-24 14-Apr-24 25-Apr-24 07-May-24 23d Start of Delivery progress at site
Carpentary and Joinery Works 87d 02-Apr-24 11-Jul-24 20-Jun-24 30-Sep-24 69d 11-Jul-24, Carpentary and Joinery Works
E-PQ-1160 PQ Submission of Wooden Works 7d 02-Apr-24 09-Apr-24 20-Jun-24 27-Jun-24 68d PQ Submission of Wooden Works
E-PQ-1170 Review and Approval of PQ Submission of Wooden Works
7d 10-Apr-24 18-Apr-24 28-Jun-24 08-Jul-24 57d Review and Approval of PQ Submission of Wooden Works
E-MS-1160 Material Submittal of Wooden Works 7d 19-Apr-24 26-Apr-24 09-Jul-24 16-Jul-24 69d Material Submittal of Wooden Works
E-MS-1170 Review and Approval of Material Submittal of Wooden
5dWorks
29-Apr-24 03-May-24 17-Jul-24 23-Jul-24 57d Review and Approval of Material Submittal of Wooden Works
E-SD-1320 Submission of Shop Drawings & Method Statement10d
of Wooden
04-May-24
Works 15-May-24 24-Jul-24 03-Aug-24 69d Submission of Shop Drawings & Method Statement of Wooden Works
E-SD-1350 Approval of Shop Drawings & Method Statement of10d
Wooden
16-May-24
Works 29-May-24 05-Aug-24 16-Aug-24 57d Approval of Shop Drawings & Method Statement of Wooden Works
E-Procure-1890 Order Palced of Wooden Works 10d 30-May-24 10-Jun-24 19-Aug-24 29-Aug-24 69d Order Palced of Wooden Works
E-Procure-1900 Start of Delivery progress at site 8d 04-Jul-24 11-Jul-24 23-Sep-24 30-Sep-24 81d Start of Delivery progress at site
Aluminium and Metal Works 127d 16-Nov-23 14-Apr-24 27-Apr-24 23-Sep-24 139d 14-Apr-24, Aluminium and Metal Works
E-PQ-1260 PQ Submission of Aluminium & Metal Works 7d 16-Nov-23 23-Nov-23 27-Apr-24 04-May-24 138d PQ Submission of Aluminium & Metal Works
E-PQ-1270 Review and Approval of PQ Submission of Aluminium
7d& Metal
24-Nov-23
Works 04-Dec-23 06-May-24 14-May-24 115d Review and Approval of PQ Submission of Aluminium & Metal Works
E-MS-1260 Material Submittal of Aluminium & Metal Works 7d 05-Dec-23 12-Dec-23 15-May-24 22-May-24 137d Material Submittal of Aluminium & Metal Works
E-MS-1270 Review and Approval of Material Submittal of Aluminium
5d 13-Dec-23
& Metal Works19-Dec-23 23-May-24 29-May-24 115d Review and Approval of Material Submittal of Aluminium & Metal Works
E-SD-1670 Submission of Shop Drawings & Method Statement10d
of Aluminium
20-Dec-23& Metal
30-Dec-23
Works 30-May-24 10-Jun-24 137d Submission of Shop Drawings & Method Statement of Aluminium & Metal Works
E-SD-1680 Approval of Shop Drawings & Method Statement of10d
Aluminium
01-Jan-24
& Metal 12-Jan-24
Works 11-Jun-24 24-Jun-24 115d Approval of Shop Drawings & Method Statement of Aluminium & Metal Works
E-Procure-2010 Order Palced of Aluminium & Metal Works 5d 13-Jan-24 18-Jan-24 25-Jun-24 29-Jun-24 139d Order Palced of Aluminium & Metal Works
E-Procure-2020 Start of Delivery progress at site 4d 11-Apr-24 14-Apr-24 20-Sep-24 23-Sep-24 162d Start of Delivery progress at site
Provisional Sums Item Submittals 517d 31-May-23 01-Feb-25 01-Nov-23 13-May-25 86d 01-Feb-25, Provisional Sums Item Submittals
Plunge Pools 105d 13-Apr-24 14-Aug-24 17-May-24 15-Sep-24 28d 14-Aug-24, Plunge Pools
PS-1080 Submission of Proposal by Vendors for Plunge Pool 6d 13-Apr-24 19-Apr-24 17-May-24 23-May-24 29d Submission of Proposal by Vendors for Plunge Pool
PS-1260 Nomination and Contract with Vendor 40d 20-Apr-24 05-Jun-24 24-May-24 09-Jul-24 29d Nomination and Contract with Vendor
PS-1440 Submission of Material Submittal, Shop Drawings &10d
Method
06-Jun-24
Statement17-Jun-24
of Plunge Pool
10-Jul-24 20-Jul-24 29d Submission of Material Submittal, Shop Drawings & Method Statement of Plunge Pool
PS-1620 Approval of Material Submittal, Shop Drawings & Method
10d 18-Jun-24
Statement 01-Jul-24 22-Jul-24 02-Aug-24 24d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1800 Delivery of Equipments / Parts at site for Plunge Pool
43d 02-Jul-24 14-Aug-24 03-Aug-24 15-Sep-24 33d Delivery of Equipments / Parts at site for Plunge Pool
Swimming Pool & Open Shower Area 106d 08-Dec-23 11-Apr-24 11-Sep-24 12-Jan-25 232d 11-Apr-24, Swimming Pool & Open Shower Area
PS-1070 Submission of Proposal by Vendors for Swimming Pool
6d &08-Dec-23
Open Shower14-Dec-23
Area 11-Sep-24 17-Sep-24 236d Submission of Proposal by Vendors for Swimming Pool & Open Shower Area
PS-1250 Nomination and Contract with Vendor 40d 15-Dec-23 31-Jan-24 18-Sep-24 02-Nov-24 236d Nomination and Contract with Vendor
PS-1430 Submission of Material Submittal, Shop Drawings &10d
Method
01-Feb-24
Statement12-Feb-24
of Swimming04-Nov-24
Pool& Open Shower
14-Nov-24
Area 236d Submission of Material Submittal, Shop Drawings & Method Statement of Swimming Pool& Open Shower Area
PS-1610 Approval of Material Submittal, Shop Drawings & Method
10d 13-Feb-24
Statement 26-Feb-24 15-Nov-24 28-Nov-24 197d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1790 Delivery of Equipments / Parts at site for Swimming45d
Pool27-Feb-24
& Open Shower
11-Apr-24
Area 29-Nov-24 12-Jan-25 276d Delivery of Equipments / Parts at site for Swimming Pool & Open Shower Area
Lifts 164d 08-Dec-23 18-Jun-24 26-Mar-24 01-Oct-24 90d 18-Jun-24, Lifts
PS-1110 Submission of Proposal by Vendors for Lifts 20d 08-Dec-23 30-Dec-23 26-Mar-24 17-Apr-24 91d Submission of Proposal by Vendors for Lifts
PS-1290 Nomination and Contract with Vendor 40d 02-Jan-24 16-Feb-24 18-Apr-24 03-Jun-24 91d Nomination and Contract with Vendor
PS-1470 Submission of Material Submittal, Shop Drawings &12d
Method
17-Feb-24
Statement01-Mar-24
of Lifts 04-Jun-24 17-Jun-24 91d Submission of Material Submittal, Shop Drawings & Method Statement of Lifts
PS-1650 Approval of Material Submittal, Shop Drawings & Method
12d 04-Mar-24
Statement 20-Mar-24 18-Jun-24 03-Jul-24 75d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1830 Delivery of Equipments / Parts at site for Lifts 90d 21-Mar-24 18-Jun-24 04-Jul-24 01-Oct-24 105d Delivery of Equipments / Parts at site for Lifts
Aluminium, Glazing, Glass Partition & Metal Works 120d 19-Jan-24 07-Jun-24 03-Sep-24 19-Jan-25 189d 07-Jun-24, Aluminium, Glazing, Glass Partition & Metal Works
PS-1130 Submission of Proposal by Vendors for Aluminum, Glazing,
6d 19-Jan-24
Glass Partitions
25-Jan-24
and Metal03-Sep-24
Works 09-Sep-24 194d Submission of Proposal by Vendors for Aluminum, Glazing, Glass Partitions and Metal Works

Actual Level of Effort Remaining Work Milestone Page 3 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:22
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
PS-1310 Nomination and Contract with Vendor 40d 26-Jan-24 13-Mar-24 10-Sep-24 25-Oct-24 194d Nomination and Contract with Vendor
PS-1490 Submission of Material Submittal, Shop Drawings &10d
Method
14-Mar-24
Statement25-Mar-24
of Aluminum,26-Oct-24
Glazing, Glass
06-Nov-24
Partition and 194d
Metal Works Submission of Material Submittal, Shop Drawings & Method Statement of Aluminum, Glazing, Glass Partitio
PS-1670 Approval of Material Submittal, Shop Drawings & Method
10d 26-Mar-24
Statement 08-Apr-24 07-Nov-24 20-Nov-24 162d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1850 Delivery of Equipments / Parts at site for Aluminum,60d
Glazing,
09-Apr-24
Glass Partition
07-Jun-24
and Metal
21-Nov-24
Works 19-Jan-25 226d Delivery of Equipments / Parts at site for Aluminum, Glazing, Glass Partition and Metal Works
Kitchen Cabinets 125d 20-Jul-24 16-Dec-24 09-Aug-24 05-Jan-25 16d 16-Dec-24, Kitchen Cabinets
PS-1020 Submission of Proposal by Vendors for Kitchen Cabinet
15d 20-Jul-24 06-Aug-24 09-Aug-24 26-Aug-24 17d Submission of Proposal by Vendors for Kitchen Cabinet
PS-1200 Nomination and Contract with Vendor 40d 07-Aug-24 21-Sep-24 27-Aug-24 11-Oct-24 17d Nomination and Contract with Vendor
PS-1380 Submission of Material Submittal, Shop Drawings &10d
Method
23-Sep-24
Statement03-Oct-24
of Kitchen Cabinet
12-Oct-24 23-Oct-24 17d Submission of Material Submittal, Shop Drawings & Method Statement o
PS-1560 Approval of Material Submittal, Shop Drawings & Method
10d 04-Oct-24
Statement 17-Oct-24 24-Oct-24 06-Nov-24 14d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1740 Delivery of Equipments / Parts at site for Kitchen Cabinet
60d 18-Oct-24 16-Dec-24 07-Nov-24 05-Jan-25 20d Delivery of Equipments / Parts at site for Kitchen Cabinet
Wardrobes 125d 20-Jul-24 16-Dec-24 09-Aug-24 05-Jan-25 16d 16-Dec-24, Wardrobes
PS-1030 Submission of Proposal by Vendors for Wardrobes 15d 20-Jul-24 06-Aug-24 09-Aug-24 26-Aug-24 17d Submission of Proposal by Vendors for Wardrobes
PS-1210 Nomination and Contract with Vendor 40d 07-Aug-24 21-Sep-24 27-Aug-24 11-Oct-24 17d Nomination and Contract with Vendor
PS-1390 Submission of Material Submittal, Shop Drawings &10d
Method
23-Sep-24
Statement03-Oct-24
of Wardrobes12-Oct-24 23-Oct-24 17d Submission of Material Submittal, Shop Drawings & Method Statement o
PS-1570 Approval of Material Submittal, Shop Drawings & Method
10d 04-Oct-24
Statement 17-Oct-24 24-Oct-24 06-Nov-24 14d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1750 Delivery of Equipments / Parts at site for Wardrobes60d 18-Oct-24 16-Dec-24 07-Nov-24 05-Jan-25 20d Delivery of Equipments / Parts at site for Wardrobes
Garbage Disposal System 122d 20-Jul-24 12-Dec-24 12-Oct-24 11-Mar-25 74d 12-Dec-24, Garbage Disposal System
PS-1000 Submission of Proposal by Vendors for Garbage Disposal
15d 20-Jul-24
System 06-Aug-24 12-Oct-24 29-Oct-24 72d Submission of Proposal by Vendors for Garbage Disposal System
PS-1180 Nomination and Contract with Vendor 40d 07-Aug-24 21-Sep-24 30-Oct-24 18-Dec-24 72d Nomination and Contract with Vendor
PS-1360 Submission of Material Submittal, Shop Drawings &10d
Method
23-Sep-24
Statement03-Oct-24
of Garbage Disposal
19-Dec-24
System
30-Dec-24 72d Submission of Material Submittal, Shop Drawings & Method Statement o
PS-1540 Approval of Material Submittal, Shop Drawings & Method
10d 04-Oct-24
Statement 17-Oct-24 31-Dec-24 14-Jan-25 60d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1720 Delivery of Equipments / Parts at site for Garbage Disposal
56d 18-Oct-24
System 12-Dec-24 15-Jan-25 11-Mar-25 89d Delivery of Equipments / Parts at site for Garbage Disposal S
Mirrors 94d 20-Jul-24 06-Nov-24 24-Jan-25 13-May-25 157d 06-Nov-24, Mirrors
PS-1120 Submission of Proposal by Vendors for Mirrors 6d 20-Jul-24 26-Jul-24 24-Jan-25 30-Jan-25 157d Submission of Proposal by Vendors for Mirrors
PS-1300 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 31-Jan-25 19-Mar-25 157d Nomination and Contract with Vendor
PS-1480 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Mirrors 20-Mar-25 29-Mar-25 157d Submission of Material Submittal, Shop Drawings & Method Statement of M
PS-1660 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 31-Mar-25 11-Apr-25 131d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1840 Delivery of Equipments / Parts at site for Mirrors 30d 08-Oct-24 06-Nov-24 14-Apr-25 13-May-25 188d Delivery of Equipments / Parts at site for Mirrors
Sanitary Ware, Mixer & Accessories 112d 20-Jul-24 27-Nov-24 24-Oct-24 09-Mar-25 82d 27-Nov-24, Sanitary Ware, Mixer & Accessories
PS-1040 Submission of Proposal by Vendors for Sanitary wares,
6d Mixer
20-Jul-24
& Accessories
26-Jul-24 24-Oct-24 30-Oct-24 82d Submission of Proposal by Vendors for Sanitary wares, Mixer & Accessories
PS-1220 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 31-Oct-24 19-Dec-24 82d Nomination and Contract with Vendor
PS-1400 Submission of Material Submittal, Shop Drawings &15d
Method
12-Sep-24
Statement28-Sep-24
of Sanitarywares,
20-Dec-24
Mixer & Accessories
07-Jan-25 82d Submission of Material Submittal, Shop Drawings & Method Statement of
PS-1580 Approval of Material Submittal, Shop Drawings & Method
15d 30-Sep-24
Statement 18-Oct-24 08-Jan-25 28-Jan-25 69d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1760 Delivery of Equipments / Parts at site for Sanitarywares
40d 19-Oct-24 27-Nov-24 29-Jan-25 09-Mar-25 102d Delivery of Equipments / Parts at site for Sanitarywares
Light Fixtures 103d 20-Jul-24 16-Nov-24 11-Nov-24 12-Mar-25 94d 16-Nov-24, Light Fixtures
PS-1010 Submission of Proposal by Vendors for Light Fixture 6d 20-Jul-24 26-Jul-24 11-Nov-24 16-Nov-24 97d Submission of Proposal by Vendors for Light Fixture
PS-1190 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 18-Nov-24 07-Jan-25 97d Nomination and Contract with Vendor
PS-1370 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Light Fixture
08-Jan-25 18-Jan-25 97d Submission of Material Submittal, Shop Drawings & Method Statement of L
PS-1550 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 20-Jan-25 31-Jan-25 81d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1730 Delivery of Equipments / Parts at site for Light Fixture
40d 08-Oct-24 16-Nov-24 01-Feb-25 12-Mar-25 116d Delivery of Equipments / Parts at site for Light Fixture
Signages 103d 20-Jul-24 16-Nov-24 23-Nov-24 27-Mar-25 108d 16-Nov-24, Signages
PS-1090 Submission of Proposal by Vendors for Signage 15d 20-Jul-24 06-Aug-24 23-Nov-24 13-Dec-24 108d Submission of Proposal by Vendors for Signage
PS-1270 Nomination and Contract with Vendor 40d 07-Aug-24 21-Sep-24 14-Dec-24 30-Jan-25 108d Nomination and Contract with Vendor
PS-1450 Submission of Material Submittal, Shop Drawings &10d
Method
23-Sep-24
Statement03-Oct-24
of Signage 31-Jan-25 11-Feb-25 108d Submission of Material Submittal, Shop Drawings & Method Statement o
PS-1630 Approval of Material Submittal, Shop Drawings & Method
10d 04-Oct-24
Statement 17-Oct-24 12-Feb-25 25-Feb-25 90d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1810 Delivery of Equipments / Parts at site for Signage 30d 18-Oct-24 16-Nov-24 26-Feb-25 27-Mar-25 131d Delivery of Equipments / Parts at site for Signage
Column Guards, Humps,Traffic Mirrors, Wheel Stopper 81d 20-Jul-24 22-Oct-24 21-Dec-24 27-Mar-25 130d 22-Oct-24, Column Guards, Humps,Traffic Mirrors, Wheel Stopper
PS-1100 Submission of Proposal by Vendors for Column Guards,
6d 20-Jul-24
Humps,Traffic Mirrors,Wheel
26-Jul-24 21-Dec-24
Stopper 27-Dec-24 129d Submission of Proposal by Vendors for Column Guards, Humps,Traffic Mirrors,Wheel
PS-1280 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 28-Dec-24 13-Feb-25 129d Nomination and Contract with Vendor
PS-1460 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Column Guards,
14-Feb-25
Humps,Traffic
25-Feb-25Mirrors,Wheel
129d Stopper Submission of Material Submittal, Shop Drawings & Method Statement of C
PS-1640 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 26-Feb-25 12-Mar-25 108d Approval of Material Submittal, Shop Drawings & Method Statement

Actual Level of Effort Remaining Work Milestone Page 4 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:22
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
PS-1820 Delivery of Equipments / Parts at site for Column Guards,
15d 08-Oct-24
Humps,Traffic22-Oct-24
Mirrors,Wheel
13-Mar-25
Stopper 27-Mar-25 156d Delivery of Equipments / Parts at site for Column Guards, Humps,Traf
Sauna & Stream Rooms 107d 20-Jul-24 21-Nov-24 07-Dec-24 11-Apr-25 117d 21-Nov-24, Sauna & Stream Rooms
PS-1140 Submission of Proposal by Vendors for Sauna & Steam
6d Rooms
20-Jul-24 26-Jul-24 07-Dec-24 13-Dec-24 117d Submission of Proposal by Vendors for Sauna & Steam Rooms
PS-1320 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 14-Dec-24 30-Jan-25 117d Nomination and Contract with Vendor
PS-1500 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Sauna & Steam
31-Jan-25 11-Feb-25 117d Submission of Material Submittal, Shop Drawings & Method Statement of S
PS-1680 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 12-Feb-25 25-Feb-25 98d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1860 Delivery of Equipments / Parts at site for Sauna & Steam
45d 08-Oct-24
Rooms 21-Nov-24 26-Feb-25 11-Apr-25 141d Delivery of Equipments / Parts at site for Sauna & Steam Rooms
Landscaping 107d 20-Jul-24 21-Nov-24 03-Jan-25 07-May-25 139d 21-Nov-24, Landscaping
PS-1060 Submission of Proposal by Vendors for Landscaping6d 20-Jul-24 26-Jul-24 03-Jan-25 09-Jan-25 139d Submission of Proposal by Vendors for Landscaping
PS-1240 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 10-Jan-25 25-Feb-25 139d Nomination and Contract with Vendor
PS-1420 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Landscaping
26-Feb-25 10-Mar-25 139d Submission of Material Submittal, Shop Drawings & Method Statement of L
PS-1600 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 11-Mar-25 23-Mar-25 116d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1780 Delivery of Equipments / Parts at site for Landscaping
45d 08-Oct-24 21-Nov-24 24-Mar-25 07-May-25 167d Delivery of Equipments / Parts at site for Landscaping
Gym & Kids Area Equipment 107d 20-Jul-24 21-Nov-24 10-Jan-25 13-May-25 144d 21-Nov-24, Gym & Kids Area Equipment
PS-1050 Submission of Proposal by Vendors for Gym and Kid6d
Area
20-Jul-24
Equipment 26-Jul-24 10-Jan-25 16-Jan-25 145d Submission of Proposal by Vendors for Gym and Kid Area Equipment
PS-1230 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 17-Jan-25 04-Mar-25 145d Nomination and Contract with Vendor
PS-1410 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Gym and Kid
05-Mar-25
Area Equipment
17-Mar-25 145d Submission of Material Submittal, Shop Drawings & Method Statement of G
PS-1590 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 18-Mar-25 28-Mar-25 121d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1770 Delivery of Equipments / Parts at site for Gym and Kid
45dArea
08-Oct-24
Equipment 21-Nov-24 30-Mar-25 13-May-25 173d Delivery of Equipments / Parts at site for Gym and Kid Area Equi
Facade Lighting 103d 20-Jul-24 16-Nov-24 17-Dec-24 15-Apr-25 124d 16-Nov-24, Facade Lighting
PS-1150 Submission of Proposal by Vendors for Facade Lighting
6d 20-Jul-24 26-Jul-24 17-Dec-24 23-Dec-24 125d Submission of Proposal by Vendors for Facade Lighting
PS-1330 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 24-Dec-24 08-Feb-25 125d Nomination and Contract with Vendor
PS-1510 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Facade Lighting
10-Feb-25 20-Feb-25 125d Submission of Material Submittal, Shop Drawings & Method Statement of F
PS-1690 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 21-Feb-25 06-Mar-25 105d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1870 Delivery of Equipments / Parts at site for Facade Lighting
40d 08-Oct-24 16-Nov-24 07-Mar-25 15-Apr-25 150d Delivery of Equipments / Parts at site for Facade Lighting
Facade Signage Digital 94d 20-Jul-24 06-Nov-24 24-Dec-24 15-Apr-25 133d 06-Nov-24, Facade Signage Digital
PS-1160 Submission of Proposal by Vendors for Facade signage
6d (Digital)
20-Jul-24 26-Jul-24 24-Dec-24 30-Dec-24 131d Submission of Proposal by Vendors for Facade signage (Digital)
PS-1340 Nomination and Contract with Vendor 40d 27-Jul-24 11-Sep-24 31-Dec-24 15-Feb-25 131d Nomination and Contract with Vendor
PS-1520 Submission of Material Submittal, Shop Drawings &10d
Method
12-Sep-24
Statement23-Sep-24
of Facade signage
17-Feb-25 27-Feb-25 131d Submission of Material Submittal, Shop Drawings & Method Statement of F
PS-1700 Approval of Material Submittal, Shop Drawings & Method
10d 24-Sep-24
Statement 07-Oct-24 28-Feb-25 14-Mar-25 110d Approval of Material Submittal, Shop Drawings & Method Statement
PS-1880 Delivery of Equipments / Parts at site for Facade signage
30d 08-Oct-24
Digital 06-Nov-24 17-Mar-25 15-Apr-25 160d Delivery of Equipments / Parts at site for Facade signage Digital
Screening of Roof MEP Services 105d 28-Sep-24 01-Feb-25 11-Dec-24 15-Apr-25 62d 01-Feb-25, Screening of Roof MEP Services
PS-1170 Submission of Proposal by Vendors for Screening of 6d
roof28-Sep-24
MEP Services04-Oct-24 11-Dec-24 17-Dec-24 60d Submission of Proposal by Vendors for Screening of roof MEP Services
PS-1350 Nomination and Contract with Vendor 40d 05-Oct-24 20-Nov-24 18-Dec-24 03-Feb-25 60d Nomination and Contract with Vendor
PS-1530 Submission of Material Submittal, Shop Drawings &15d
Method
21-Nov-24
Statement11-Dec-24
of Screening 04-Feb-25
in Roof 20-Feb-25 60d Submission of Material Submittal, Shop Drawings & Method
PS-1710 Approval of Material Submittal, Shop Drawings & Method
15d 12-Dec-24
Statement 02-Jan-25 21-Feb-25 14-Mar-25 50d Approval of Material Submittal, Shop Drawings & Method
PS-1890 Delivery of Equipments / Parts at site for Screening30d
in Roof
03-Jan-25
MEP Services
01-Feb-25 17-Mar-25 15-Apr-25 73d Delivery of Equipments / Parts at site for Screening
MEP Works Submittals 284d 31-May-23 01-May-24 01-Nov-23 29-Apr-25 307d 01-May-24, MEP Works Submittals
Drainage 71d 31-May-23 24-Aug-23 01-Nov-23 06-Feb-24 141d 24-Aug-23, Drainage
PS-1920 Submission of Proposal by Vendors for Drainage 15d 31-May-23 17-Jun-23 01-Nov-23 17-Nov-23 129d Submission of Proposal by Vendors for Drainage
PS-2050 Nomination and Contract with Vendor 20d 17-Jun-23 13-Jul-23 02-Dec-23 25-Dec-23 141d Nomination and Contract with Vendor
PS-2180 Submission of Material Submittal, Shop Drawings &10d
Method
13-Jul-23
Statement25-Jul-23
of Drainage 26-Dec-23 06-Jan-24 141d Submission of Material Submittal, Shop Drawings & Method Statement of Drainage
PS-2310 Approval of Material Submittal, Shop Drawings & Method
10d 25-Jul-23
Statement 08-Aug-23 08-Jan-24 19-Jan-24 118d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2440 Delivery of Equipments / Parts at site for Drainage 16d 08-Aug-23 24-Aug-23 22-Jan-24 06-Feb-24 166d Delivery of Equipments / Parts at site for Drainage
Water Supply 62d 17-Jun-23 31-Aug-23 18-Nov-23 06-Feb-24 135d 31-Aug-23, Water Supply
PS-1930 Submission of Proposal by Vendors for Water Supply6d 17-Jun-23 24-Jun-23 18-Nov-23 24-Nov-23 129d Submission of Proposal by Vendors for Water Supply
PS-2060 Nomination and Contract with Vendor 20d 24-Jun-23 20-Jul-23 02-Dec-23 25-Dec-23 135d Nomination and Contract with Vendor
PS-2190 Submission of Material Submittal, Shop Drawings &10d
Method
20-Jul-23
Statement01-Aug-23
of Water Suppl
26-Dec-23
y 06-Jan-24 135d Submission of Material Submittal, Shop Drawings & Method Statement of Water Supply
PS-2320 Approval of Material Submittal, Shop Drawings & Method
10d 01-Aug-23
Statement 15-Aug-23 08-Jan-24 19-Jan-24 113d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2450 Delivery of Equipments / Parts at site for Water Supply
16d 15-Aug-23 31-Aug-23 22-Jan-24 06-Feb-24 159d Delivery of Equipments / Parts at site for Water Supply
Lighting 62d 24-Jun-23 07-Sep-23 25-Nov-23 06-Feb-24 129d 07-Sep-23, Lighting

Actual Level of Effort Remaining Work Milestone Page 5 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
PS-1940 Submission of Proposal by Vendors for Lighting 6d 24-Jun-23 04-Jul-23 25-Nov-23 01-Dec-23 129d Submission of Proposal by Vendors for Lighting
PS-2070 Nomination and Contract with Vendor 20d 04-Jul-23 27-Jul-23 02-Dec-23 25-Dec-23 129d Nomination and Contract with Vendor
PS-2200 Submission of Material Submittal, Shop Drawings &10d
Method
27-Jul-23
Statement08-Aug-23
of Lighting 26-Dec-23 06-Jan-24 129d Submission of Material Submittal, Shop Drawings & Method Statement of Lighting
PS-2330 Approval of Material Submittal, Shop Drawings & Method
10d 08-Aug-23
Statement 22-Aug-23 08-Jan-24 19-Jan-24 108d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2460 Delivery of Equipments / Parts at site for Lighting 16d 22-Aug-23 07-Sep-23 22-Jan-24 06-Feb-24 152d Delivery of Equipments / Parts at site for Lighting
Power 56d 04-Jul-23 07-Sep-23 02-Dec-23 06-Feb-24 129d 07-Sep-23, Power
PS-1950 Submission of Proposal by Vendors for Power 6d 04-Jul-23 11-Jul-23 02-Dec-23 08-Dec-23 129d Submission of Proposal by Vendors for Power
PS-2080 Nomination and Contract with Vendor 14d 11-Jul-23 27-Jul-23 09-Dec-23 25-Dec-23 129d Nomination and Contract with Vendor
PS-2210 Submission of Material Submittal, Shop Drawings &10d
Method
27-Jul-23
Statement08-Aug-23
of Power 26-Dec-23 06-Jan-24 129d Submission of Material Submittal, Shop Drawings & Method Statement of Power
PS-2340 Approval of Material Submittal, Shop Drawings & Method
10d 08-Aug-23
Statement 22-Aug-23 08-Jan-24 19-Jan-24 108d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2470 Delivery of Equipments / Parts at site for Power 16d 22-Aug-23 07-Sep-23 22-Jan-24 06-Feb-24 152d Delivery of Equipments / Parts at site for Power
Ventilation & Smoke Management 60d 11-Jul-23 19-Sep-23 18-Dec-23 22-Mar-24 157d 19-Sep-23, Ventilation & Smoke Management
PS-1910 Submission of Proposal by Vendors for Ventilation & 6d
Smoke
11-Jul-23
Management
18-Jul-23 18-Dec-23 25-Dec-23 137d Submission of Proposal by Vendors for Ventilation & Smoke Management
PS-2040 Nomination and Contract with Vendor 19d 18-Jul-23 09-Aug-23 19-Jan-24 09-Feb-24 157d Nomination and Contract with Vendor
PS-2170 Submission of Material Submittal, Shop Drawings &10d
Method
09-Aug-23
Statement21-Aug-23
of Ventilation10-Feb-24
& Smoke Management
21-Feb-24 157d Submission of Material Submittal, Shop Drawings & Method Statement of Ventilation & Smoke Management
PS-2300 Approval of Material Submittal, Shop Drawings & Method
10d 21-Aug-23
Statement 04-Sep-23 22-Feb-24 06-Mar-24 132d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2430 Delivery of Equipments / Parts at site for Ventilation15d
& Smoke
04-Sep-23
Management
19-Sep-23 07-Mar-24 22-Mar-24 185d Delivery of Equipments / Parts at site for Ventilation & Smoke Management
Telephone System 55d 18-Jul-23 20-Sep-23 25-Dec-23 22-Mar-24 157d 20-Sep-23, Telephone System
PS-1970 Submission of Proposal by Vendors for Telephone System
6d 18-Jul-23 25-Jul-23 25-Dec-23 02-Jan-24 137d Submission of Proposal by Vendors for Telephone System
PS-2100 Nomination and Contract with Vendor 15d 25-Jul-23 11-Aug-23 25-Jan-24 10-Feb-24 156d Nomination and Contract with Vendor
PS-2230 Submission of Material Submittal, Shop Drawings &10d
Method
11-Aug-23
Statement23-Aug-23
of Tele phone12-Feb-24
System 22-Feb-24 156d Submission of Material Submittal, Shop Drawings & Method Statement of Tele phone System
PS-2360 Approval of Material Submittal, Shop Drawings & Method
10d 23-Aug-23
Statement 06-Sep-23 23-Feb-24 08-Mar-24 131d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2490 Delivery of Equipments / Parts at site for Fire Fighting
14d& Fire
06-Sep-23
Alarm 20-Sep-23 09-Mar-24 22-Mar-24 185d Delivery of Equipments / Parts at site for Fire Fighting & Fire Alarm
ELV Systems 54d 25-Jul-23 26-Sep-23 02-Jan-24 22-Mar-24 151d 26-Sep-23, ELV Systems
PS-1980 Submission of Proposal by Vendors for ELV System 6d 25-Jul-23 01-Aug-23 02-Jan-24 09-Jan-24 137d Submission of Proposal by Vendors for ELV System
PS-2110 Nomination and Contract with Vendor 15d 01-Aug-23 18-Aug-23 25-Jan-24 10-Feb-24 150d Nomination and Contract with Vendor
PS-2240 Submission of Material Submittal, Shop Drawings &10d
Method
18-Aug-23
Statement30-Aug-23
of ELV System
12-Feb-24 22-Feb-24 150d Submission of Material Submittal, Shop Drawings & Method Statement of ELV System
PS-2370 Approval of Material Submittal, Shop Drawings & Method
10d 30-Aug-23
Statement 13-Sep-23 23-Feb-24 08-Mar-24 126d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2500 Delivery of Equipments / Parts at site for ELV System
13d 13-Sep-23 26-Sep-23 10-Mar-24 22-Mar-24 178d Delivery of Equipments / Parts at site for ELV System
CCTV System (IP Base) 56d 01-Aug-23 05-Oct-23 09-Jan-24 22-Mar-24 144d 05-Oct-23, CCTV System (IP Base)
PS-1990 Submission of Proposal by Vendors for CCTV (IP Base)
6d 01-Aug-23 08-Aug-23 09-Jan-24 16-Jan-24 137d Submission of Proposal by Vendors for CCTV (IP Base)
PS-2120 Nomination and Contract with Vendor 15d 08-Aug-23 25-Aug-23 24-Jan-24 10-Feb-24 144d Nomination and Contract with Vendor
PS-2250 Submission of Material Submittal, Shop Drawings &10d
Method
25-Aug-23
Statement06-Sep-23
of CCTV (IP Base)
10-Feb-24 22-Feb-24 144d Submission of Material Submittal, Shop Drawings & Method Statement of CCTV (IP Base)
PS-2380 Approval of Material Submittal, Shop Drawings & Method
10d 06-Sep-23
Statement 20-Sep-23 22-Feb-24 08-Mar-24 121d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2510 Delivery of Equipments / Parts at site for CCTV (IP 14d
Base)20-Sep-23 05-Oct-23 08-Mar-24 22-Mar-24 170d Delivery of Equipments / Parts at site for CCTV (IP Base)
Access Control System 47d 08-Aug-23 02-Oct-23 16-Jan-24 22-Mar-24 147d 02-Oct-23, Access Control System
PS-2000 Submission of Proposal by Vendors for Access Control
6d System
08-Aug-23 15-Aug-23 16-Jan-24 23-Jan-24 137d Submission of Proposal by Vendors for Access Control System
PS-2130 Nomination and Contract with Vendor 10d 15-Aug-23 26-Aug-23 02-Feb-24 14-Feb-24 146d Nomination and Contract with Vendor
PS-2260 Submission of Material Submittal, Shop Drawings &10d
Method
26-Aug-23
Statement07-Sep-23
of Access Control
14-Feb-24
System 26-Feb-24 146d Submission of Material Submittal, Shop Drawings & Method Statement of Access Control System
PS-2390 Approval of Material Submittal, Shop Drawings & Method
10d 07-Sep-23
Statement 21-Sep-23 26-Feb-24 12-Mar-24 122d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2520 Delivery of Equipments / Parts at site for Access Control
10d System
21-Sep-23 02-Oct-23 12-Mar-24 22-Mar-24 173d Delivery of Equipments / Parts at site for Access Control System
Audio Intercom System 51d 15-Aug-23 13-Oct-23 23-Jan-24 22-Mar-24 137d 13-Oct-23, Audio Intercom System
PS-2010 Submission of Proposal by Vendors for Audio Intercom
6d System
15-Aug-23 22-Aug-23 23-Jan-24 30-Jan-24 137d Submission of Proposal by Vendors for Audio Intercom System
PS-2140 Nomination and Contract with Vendor 10d 22-Aug-23 02-Sep-23 30-Jan-24 10-Feb-24 137d Nomination and Contract with Vendor
PS-2270 Submission of Material Submittal, Shop Drawings &10d
Method
02-Sep-23
Statement14-Sep-23
of Audio Intercom
10-Feb-24
System 22-Feb-24 137d Submission of Material Submittal, Shop Drawings & Method Statement of Audio Intercom System
PS-2400 Approval of Material Submittal, Shop Drawings & Method
10d 14-Sep-23
Statement 28-Sep-23 22-Feb-24 08-Mar-24 115d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2530 Delivery of Equipments / Parts at site for Audio Intercom
14d 28-Sep-23
System 13-Oct-23 08-Mar-24 22-Mar-24 162d Delivery of Equipments / Parts at site for Audio Intercom System
Fire Alarm & Fire Fighting 54d 22-Aug-23 24-Oct-23 12-Feb-24 15-Apr-24 147d 24-Oct-23, Fire Alarm & Fire Fighting
PS-1960 Submission of Proposal by Vendors for Fire Fighting &
6dFire
22-Aug-23
Alarm 29-Aug-23 12-Feb-24 19-Feb-24 148d Submission of Proposal by Vendors for Fire Fighting & Fire Alarm
PS-2090 Nomination and Contract with Vendor 15d 29-Aug-23 15-Sep-23 19-Feb-24 08-Mar-24 148d Nomination and Contract with Vendor
PS-2220 Submission of Material Submittal, Shop Drawings &10d
Method
15-Sep-23
Statement27-Sep-23
of Fire Fighting
08-Mar-24
& Fire Alarm20-Mar-24 148d Submission of Material Submittal, Shop Drawings & Method Statement of Fire Fighting & Fire Alarm

Actual Level of Effort Remaining Work Milestone Page 6 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
PS-2350 Approval of Material Submittal, Shop Drawings & Method
10d 27-Sep-23
Statement 11-Oct-23 20-Mar-24 03-Apr-24 124d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2480 Delivery of Equipments / Parts at site for Fire Fighting
13d& Fire
11-Oct-23
Alarm 24-Oct-23 03-Apr-24 15-Apr-24 174d Delivery of Equipments / Parts at site for Fire Fighting & Fire Alarm
Gate Barrier System 113d 24-Oct-23 05-Mar-24 18-Oct-24 01-Apr-25 331d 05-Mar-24, Gate Barrier System
PS-2020 Submission of Proposal by Vendors for Gate Barrier System
6d 24-Oct-23 31-Oct-23 18-Oct-24 24-Oct-24 307d Submission of Proposal by Vendors for Gate Barrier System
PS-2150 Nomination and Contract with Vendor 40d 31-Oct-23 16-Dec-23 25-Oct-24 13-Dec-24 307d Nomination and Contract with Vendor
PS-2280 Submission of Material Submittal, Shop Drawings &10d
Method
16-Dec-23
Statement28-Dec-23
of Gate Barrier
14-Dec-24
System 25-Dec-24 307d Submission of Material Submittal, Shop Drawings & Method Statement of Gate Barrier System
PS-2410 Approval of Material Submittal, Shop Drawings & Method
10d 28-Dec-23
Statement 11-Jan-24 26-Dec-24 09-Jan-25 257d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2540 Delivery of Equipments / Parts at site for Gate Barrier
54dSystem
11-Jan-24 05-Mar-24 06-Feb-25 01-Apr-25 392d Delivery of Equipments / Parts at site for Gate Barrier System
Air Condition (AC) 94d 11-Jan-24 01-May-24 10-Jan-25 29-Apr-25 307d 01-May-24, Air Condition (AC)
PS-1900 Submission of Proposal by Vendors for AC 6d 11-Jan-24 18-Jan-24 10-Jan-25 16-Jan-25 308d Submission of Proposal by Vendors for AC
PS-2030 Nomination and Contract with Vendor 40d 18-Jan-24 05-Mar-24 17-Jan-25 04-Mar-25 308d Nomination and Contract with Vendor
PS-2160 Submission of Material Submittal, Shop Drawings &10d
Method
05-Mar-24
Statement18-Mar-24
of AC 05-Mar-25 17-Mar-25 308d Submission of Material Submittal, Shop Drawings & Method Statement of AC
PS-2290 Approval of Material Submittal, Shop Drawings & Method
10d 18-Mar-24
Statement 01-Apr-24 18-Mar-25 28-Mar-25 257d Approval of Material Submittal, Shop Drawings & Method Statement
PS-2420 Delivery of Equipments / Parts at site for AC 30d 01-Apr-24 01-May-24 31-Mar-25 29-Apr-25 364d Delivery of Equipments / Parts at site for AC
Preliminaries & Mobilization 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d 26-May-25, Preliminaries & Mob
A1050 Temporary raods 4d 24-May-23 27-May-23 07-May-25 10-May-25 604d Temporary raods
A1060 Supply of Survey Equipments at site 4d 24-May-23 27-May-23 21-May-25 24-May-25 616d Supply of Survey Equipments at site
A3270 Provision of Construction Plant and Tools 4d 29-May-23 01-Jun-23 16-May-25 20-May-25 608d Provision of Construction Plant and Tools
A3290 Temporary Hoardings 4d 29-May-23 01-Jun-23 12-May-25 15-May-25 604d Temporary Hoardings
A1070 Site Sign Boards 4d 02-Jun-23 06-Jun-23 16-May-25 20-May-25 604d Site Sign Boards
A3280 Protection of Existing Services 4d 02-Jun-23 06-Jun-23 21-May-25 24-May-25 608d Protection of Existing Services
A1100 Security & Surveillance Cameras 4d 07-Jun-23 10-Jun-23 21-May-25 24-May-25 604d Security & Surveillance Cameras
A3330 Cleaning the Works on Completion 20d 02-May-25 26-May-25 02-May-25 24-May-25 0d Cleaning the Works on Comple
Preliminaries throughout project 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d 26-May-25, Preliminaries throug
Mob-1000 Protection, Safety, First Aid and Temporary Fencing*
620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Protection, Safety, First Aid and
Mob-1010 Contractor's Office and Site Compound Establishment*
620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Contractor's Office and Site Co
Mob-1020 Workers Facility* 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Workers Facility*
A1080 Temporary electrical power and lighting* 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Temporary electrical power and
A1090 Temporary water arrangement* 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Temporary water arrangement*
A1120 Clearing away rubbish during Execution of Works*620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Clearing away rubbish during E
A3300 Engineer's Office Establishment and provision of accessories
620d 24-May-23
etc.* 26-May-25 23-May-23 24-May-25 0d Engineer's Office Establishmen
A3320 Periodic Reports, Progress Meetings and Programme
620dof 24-May-23
Works * 26-May-25 23-May-23 24-May-25 0d Periodic Reports, Progress Mee
A3340 Arrangement of necessary Insurances* 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Arrangement of necessary Insu
A6920 Material Testing * 620d 24-May-23 26-May-25 23-May-23 24-May-25 0d Material Testing *
Approvals from Authority 181d 08-Aug-23 08-Mar-24 17-Sep-24 21-Apr-25 346d 08-Mar-24, Approvals from Authority
A1340 Submission of Load Schedule and drawings to DEWA
20d 08-Aug-23 31-Aug-23 17-Sep-24 09-Oct-24 345d Submission of Load Schedule and drawings to DEWA
A1330 Approval of Load Schedule and drawings to DEWA20d 31-Aug-23 23-Sep-23 10-Oct-24 01-Nov-24 345d Approval of Load Schedule and drawings to DEWA
A1320 Application for Estimation, Estimation release by DEWA
20d 23-Sep-23 17-Oct-23 02-Nov-24 25-Nov-24 345d Application for Estimation, Estimation release by DEWA
A1310 Fees Payment for DEWA 20d 17-Oct-23 09-Nov-23 26-Nov-24 21-Dec-24 345d Fees Payment for DEWA
A1300 Transformatio n Deli very 120d 09-Nov-23 08-Mar-24 23-Dec-24 21-Apr-25 409d Transformatio n Delivery
Construction 618d 24-May-23 23-May-25 30-May-23 24-May-25 2d 23-May-25, Construction
Approvals and Erection of Tower Crane 491d 27-May-23 27-Dec-24 11-Mar-25 12-Apr-25 90d 27-Dec-24, Approvals and Erection of Tower Crane
A1010 Erection of Tower Crane 20d 27-May-23 19-Jun-23 11-Mar-25 01-Apr-25 551d Erection of Tower Crane
A1020 DCD Inspection 10d 16-Dec-24 27-Dec-24 02-Apr-25 12-Apr-25 90d DCD Inspection
Excavation & Earthwork 15d 24-May-23 09-Jun-23 30-May-23 17-Jun-23 7d 09-Jun-23, Excavation & Earthwork
Basement Floor 8d 24-May-23 01-Jun-23 30-May-23 07-Jun-23 5d 01-Jun-23, Basement Floor
Con-Subs-1000 Excavation & Disposal of Surplus Material 3d 24-May-23 26-May-23 30-May-23 01-Jun-23 5d Excavation & Disposal of Surplus Material
Con-Subs-1010 Road base and Compaction 3d 27-May-23 30-May-23 02-Jun-23 05-Jun-23 5d Road base and Compaction
Con-Subs-1020 Anti termite 2d 31-May-23 01-Jun-23 06-Jun-23 07-Jun-23 5d Anti termite
Ground Floor 12d 27-May-23 09-Jun-23 05-Jun-23 17-Jun-23 7d 09-Jun-23, Ground Floor
Con-Subs-1090 Excavation & Disposal of Surplus Material 5d 27-May-23 01-Jun-23 05-Jun-23 09-Jun-23 7d Excavation & Disposal of Surplus Material

Actual Level of Effort Remaining Work Milestone Page 7 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Con-Subs-1100 Road base and Compaction 4d 02-Jun-23 06-Jun-23 10-Jun-23 14-Jun-23 7d Road base and Compaction
Con-Subs-1110 Anti termite 3d 07-Jun-23 09-Jun-23 15-Jun-23 17-Jun-23 7d Anti termite
Concrete Works (Sub-Structure) 48d 01-Jun-23 29-Jul-23 07-Jun-23 28-Jul-23 0d 29-Jul-23, Concrete Works (Sub-Structure)
Basement Floor 33d 01-Jun-23 12-Jul-23 07-Jun-23 11-Jul-23 0d 12-Jul-23, Basement Floor
Raft 14d 01-Jun-23 17-Jun-23 07-Jun-23 16-Jun-23 0d 17-Jun-23, Raft
Con-Subs-1030 PCC blinding 2d 01-Jun-23 02-Jun-23 07-Jun-23 08-Jun-23 5d PCC blinding
Con-Subs-1080 Covering with 1000 Guage Polyether Sheer 1d 01-Jun-23 01-Jun-23 07-Jun-23 07-Jun-23 5d Covering with 1000 Guage Polyether Sheer
Con-Subs-1032 Thermal & Moisture Protection - Two Coats Bitumen 2d 03-Jun-23 05-Jun-23 09-Jun-23 10-Jun-23 5d Thermal & Moisture Protection - Two Coats Bitumen
Con-Subs-1040 Raft - Fixing of Reinforcement & Formworks 4d 12-Jun-23 16-Jun-23 12-Jun-23 15-Jun-23 0d Raft - Fixing of Reinforcement & Formworks
Con-Subs-1120 Concrete Pouring of Raft 1d 16-Jun-23 17-Jun-23 16-Jun-23 16-Jun-23 0d Concrete Pouring of Raft
Columns 5d 17-Jun-23 23-Jun-23 24-Jun-23 01-Jul-23 6d 23-Jun-23, Columns
Con-Subs-1130 Columns - Reinforcement Fixing & Formwork 4d 17-Jun-23 22-Jun-23 24-Jun-23 30-Jun-23 6d Columns - Reinforcement Fixing & Formwork
Con-Subs-1140 Columns - Concrete Pouring 2d 21-Jun-23 23-Jun-23 30-Jun-23 01-Jul-23 6d Columns - Concrete Pouring
Water tank 11d 17-Jun-23 03-Jul-23 17-Jun-23 01-Jul-23 0d 03-Jul-23, Water tank
Con-Subs-1150 Water tank Walls - Reinforcement & Formwork Fixing5d 17-Jun-23 23-Jun-23 17-Jun-23 22-Jun-23 0d Water tank Walls - Reinforcement & Formwork Fixing
Con-Subs-1160 Water tank Walls - Concrete Pouring 2d 23-Jun-23 26-Jun-23 23-Jun-23 24-Jun-23 0d Water tank Walls - Concrete Pouring
Con-Subs-1190 Two Layer 5mm thick SBS Water Proofing Membrane
2d 30-Jun-23 03-Jul-23 30-Jun-23 01-Jul-23 0d Two Layer 5mm thick SBS Water Proofing Membrane
Con-Subs-1200 Protection Board at Water tank Side Walls 2d 30-Jun-23 03-Jul-23 30-Jun-23 01-Jul-23 0d Protection Board at Water tank Side Walls
Core Walls 11d 17-Jun-23 03-Jul-23 24-Jun-23 08-Jul-23 6d 03-Jul-23, Core Walls
Con-Subs-1170 Core Walls - Rein forcement & Formwork Fixing 5d 17-Jun-23 23-Jun-23 24-Jun-23 01-Jul-23 6d Core Walls - Rein forcement & Formwork Fixing
Con-Subs-1180 Core Walls - Concrete Pouring 2d 23-Jun-23 26-Jun-23 03-Jul-23 04-Jul-23 6d Core Walls - Concrete Pouring
Con-Subs-1240 Two Coats of Bitumen 2d 30-Jun-23 03-Jul-23 07-Jul-23 08-Jul-23 6d Two Coats of Bitumen
Slab Works 6d 03-Jul-23 10-Jul-23 03-Jul-23 08-Jul-23 0d 10-Jul-23, Slab Works
Con-Subs-1210 Slab Formwork Fixing of Water tank & Pump Room 2d 03-Jul-23 05-Jul-23 03-Jul-23 04-Jul-23 0d Slab Formwork Fixing of Water tank & Pump Room
Con-Subs-1220 Slab Reinforcement Fixing of Water tank & Pump Room
3d 05-Jul-23 08-Jul-23 05-Jul-23 07-Jul-23 0d Slab Reinforcement Fixing of Water tank & Pump Room
Con-Subs-1230 Slab Concrete Pouring of Water tank & Pump Room1d 08-Jul-23 10-Jul-23 08-Jul-23 08-Jul-23 0d Slab Concrete Pouring of Water tank & Pump Room
Backfilling 2d 10-Jul-23 12-Jul-23 10-Jul-23 11-Jul-23 0d 12-Jul-23, Backfilling
A3350 Layer Wise Backfilling 2d 10-Jul-23 12-Jul-23 10-Jul-23 11-Jul-23 0d Layer Wise Backfilling
Ground Floor 40d 10-Jun-23 29-Jul-23 19-Jun-23 28-Jul-23 0d 29-Jul-23, Ground Floor
Raft 27d 10-Jun-23 14-Jul-23 19-Jun-23 13-Jul-23 0d 14-Jul-23, Raft
Con-Subs-1260 PCC blinding 5d 10-Jun-23 15-Jun-23 19-Jun-23 23-Jun-23 7d PCC blinding
Con-Subs-1250 Covering with 1000 Guage Polyether Sheer 3d 10-Jun-23 13-Jun-23 19-Jun-23 21-Jun-23 7d Covering with 1000 Guage Polyether Sheer
Con-Subs-1270 Thermal & Moisture Protection - Two Coats Bitumen 5d 16-Jun-23 21-Jun-23 24-Jun-23 01-Jul-23 7d Thermal & Moisture Protection - Two Coats Bitumen
Con-Subs-1280 Raft - Fixing of Reinforcement & Formworks 8d 03-Jul-23 12-Jul-23 03-Jul-23 11-Jul-23 0d Raft - Fixing of Reinforcement & Formworks
Con-Subs-1290 Concrete Pouring of Raft 2d 12-Jul-23 14-Jul-23 12-Jul-23 13-Jul-23 0d Concrete Pouring of Raft
Columns 9d 14-Jul-23 25-Jul-23 14-Jul-23 24-Jul-23 0d 25-Jul-23, Columns
Con-Subs-1300 Columns - Reinforcement Fixing & Formwork upto FFl
6d 14-Jul-23 21-Jul-23 14-Jul-23 20-Jul-23 0d Columns - Reinforcement Fixing & Formwork upto FFl
Con-Subs-1310 Columns - Concrete Pouring upto FFL 4d 18-Jul-23 22-Jul-23 18-Jul-23 21-Jul-23 0d Columns - Concrete Pouring upto FFL
Con-Subs-1320 2 Coats of Bitumen 2d 22-Jul-23 25-Jul-23 22-Jul-23 24-Jul-23 0d 2 Coats of Bitumen
Irrigation Tank 11d 12-Jul-23 25-Jul-23 12-Jul-23 24-Jul-23 0d 25-Jul-23, Irrigation Tank
A3360 Irrigation Tank Footing - Reinforcement & Formwork Fi
4d
x ing
12-Jul-23 17-Jul-23 12-Jul-23 15-Jul-23 0d Irrigation Tank Footing - Reinforcement & Formwork Fix ing
A3370 Irrigation Tank Footing - Concrete Pouring 1d 17-Jul-23 18-Jul-23 17-Jul-23 17-Jul-23 0d Irrigation Tank Footing - Concrete Pouring
A3380 Irrigation Tanks Walls - Reinforcement & Formwork Fixing
3d 18-Jul-23 21-Jul-23 18-Jul-23 20-Jul-23 0d Irrigation Tanks Walls - Reinforcement & Formwork Fixing
A3390 Irrigation Tank Walls - Concrete Pouring 1d 21-Jul-23 22-Jul-23 21-Jul-23 21-Jul-23 0d Irrigation Tank Walls - Concrete Pouring
A3400 2 Coats of Bitumen 2d 22-Jul-23 25-Jul-23 22-Jul-23 24-Jul-23 0d 2 Coats of Bitumen
Walls 9d 14-Jul-23 25-Jul-23 14-Jul-23 24-Jul-23 0d 25-Jul-23, Wall s
A3410 Wall s - Rein forcement & Formwork Fix ing upto FFL 5d 14-Jul-23 20-Jul-23 14-Jul-23 19-Jul-23 0d Walls - Rein forcement & Formwork Fix ing upto FFL
A3420 Wall s - Concrete Pouring upto FFL 3d 19-Jul-23 22-Jul-23 19-Jul-23 21-Jul-23 0d Wall s - Concrete Pouring upto FFL
A3430 2 Coats of Bitumen 2d 22-Jul-23 25-Jul-23 22-Jul-23 24-Jul-23 0d 2 Coats of Bitumen
Stairs & Landing 4d 19-Jul-23 24-Jul-23 20-Jul-23 24-Jul-23 1d 24-Jul-23, Stairs & Landing
A3450 Sairs & Landing - Reinforcement & Formwork Fixing3d 19-Jul-23 22-Jul-23 20-Jul-23 22-Jul-23 1d Sairs & Landing - Reinforcement & Formwork Fixing
A3460 Stairs & Landing - Concrete Pouring 1d 22-Jul-23 24-Jul-23 24-Jul-23 24-Jul-23 1d Stairs & Landing - Concrete Pouring

Actual Level of Effort Remaining Work Milestone Page 8 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Backfilling 4d 25-Jul-23 29-Jul-23 25-Jul-23 28-Jul-23 0d 29-Jul-23, Backfilling
A3440 Layer Wise Backfilling 4d 25-Jul-23 29-Jul-23 25-Jul-23 28-Jul-23 0d Layer Wise Backfilling
Concrete Works (Super-Structure) 219d 29-Jul-23 11-Apr-24 29-Jul-23 24-May-25 346d 11-Apr-24, Concrete Works (Super-Structure)
Ground To Podium 43d 29-Jul-23 18-Sep-23 29-Jul-23 15-Nov-23 51d 18-Sep-23, Ground To Podium
Columns & Walls 15d 29-Jul-23 16-Aug-23 29-Jul-23 15-Aug-23 0d 16-Aug-23, Columns & Wall s
Cons-Sup-1000 Reinforcement for Columns and Core walls 7d 29-Jul-23 07-Aug-23 29-Jul-23 05-Aug-23 0d Reinforcement for Columns and Core walls
Cons-Sup-1090 Authority Inspection 1d 07-Aug-23 08-Aug-23 07-Aug-23 07-Aug-23 0d Authority Inspection
Cons-Sup-1010 Formworks for Columns and Core walls 5d 08-Aug-23 14-Aug-23 08-Aug-23 12-Aug-23 0d Formworks for Columns and Core walls
Cons-Sup-1020 Casting of Columns and Core walls 2d 14-Aug-23 16-Aug-23 14-Aug-23 15-Aug-23 0d Casting of Columns and Core walls
Slab, Staircase & Ramp 29d 15-Aug-23 18-Sep-23 15-Aug-23 15-Nov-23 51d 18-Sep-23, Slab, Staircase & Ramp
Cons-Sup-1030 Formworks for Slab and Staircase 7d 15-Aug-23 23-Aug-23 15-Aug-23 22-Aug-23 0d Formworks for Slab and Staircase
Cons-Sup-1040 Reinforcement/PT for Slab, Staircase and Ramp 8d 23-Aug-23 01-Sep-23 23-Aug-23 31-Aug-23 0d Reinforcement/PT for Slab, Staircase and Ramp
Cons-Sup-1050 MEP 1st Fix inside the Slab, Staircase and Ramp 2d 01-Sep-23 04-Sep-23 01-Sep-23 02-Sep-23 0d MEP 1st Fix inside the Slab, Staircase and Ramp
Cons-Sup-1060 Authority Inspection 1d 04-Sep-23 05-Sep-23 04-Sep-23 04-Sep-23 0d Authority Inspection
Cons-Sup-1070 Casting of Slab, Staircase and Ramp 1d 05-Sep-23 06-Sep-23 05-Sep-23 05-Sep-23 0d Casting of Slab, Staircase and Ramp
Cons-Sup-1080 De-Shuttering for Slab, Staircase and Ramp 3d 14-Sep-23 18-Sep-23 13-Nov-23 15-Nov-23 51d De-Shuttering for Slab, Staircase and Ramp
Podium to 1st Floor 35d 06-Sep-23 17-Oct-23 06-Sep-23 13-Dec-23 50d 17-Oct-23, Podium to 1st Floor
Columns & Walls 13d 06-Sep-23 21-Sep-23 06-Sep-23 20-Sep-23 0d 21-Sep-23, Columns & Walls
Cons-Sup-1100 Reinforcement for Columns and Core walls 6d 06-Sep-23 13-Sep-23 06-Sep-23 12-Sep-23 0d Reinforcement for Columns and Core walls
Cons-Sup-1830 Authority Inspection 1d 13-Sep-23 14-Sep-23 13-Sep-23 13-Sep-23 0d Authority Inspection
Cons-Sup-1110 Formworks for Columns and Core walls 4d 14-Sep-23 19-Sep-23 14-Sep-23 18-Sep-23 0d Formworks for Columns and Core walls
Cons-Sup-1120 Casting of Columns and Core walls 2d 19-Sep-23 21-Sep-23 19-Sep-23 20-Sep-23 0d Casting of Columns and Core walls
Slab & Staircase 22d 21-Sep-23 17-Oct-23 21-Sep-23 13-Dec-23 50d 17-Oct-23, Slab & Staircase
Cons-Sup-1130 Formworks for Slab and Staircase 5d 21-Sep-23 27-Sep-23 21-Sep-23 26-Sep-23 0d Formworks for Slab and Staircase
Cons-Sup-1140 Reinforcement/PT for Slab and Staircase 5d 27-Sep-23 03-Oct-23 27-Sep-23 02-Oct-23 0d Reinforcement/PT for Slab and Staircase
Cons-Sup-1150 MEP 1st Fix inside the Slab 2d 03-Oct-23 05-Oct-23 03-Oct-23 04-Oct-23 0d MEP 1st Fix inside the Slab
Cons-Sup-1160 Authority Inspection 1d 05-Oct-23 06-Oct-23 05-Oct-23 05-Oct-23 0d Authority Inspection
Cons-Sup-1170 Casting of Slab and Staircase 1d 05-Oct-23 06-Oct-23 05-Oct-23 05-Oct-23 0d Casting of Slab and Staircase
Cons-Sup-1180 De-Shuttering 2d 14-Oct-23 17-Oct-23 12-Dec-23 13-Dec-23 50d De-Shuttering
1st to 2nd Floor 31d 06-Oct-23 11-Nov-23 06-Oct-23 29-Dec-23 42d 11-Nov-23, 1st to 2nd Floor
Columns & Walls 11d 06-Oct-23 19-Oct-23 06-Oct-23 18-Oct-23 0d 19-Oct-23, Columns & Walls
Cons-Sup-1190 Reinforcement for Columns and Core walls 5d 06-Oct-23 12-Oct-23 06-Oct-23 11-Oct-23 0d Reinforcement for Columns and Core walls
Cons-Sup-1840 Authority Inspection 1d 12-Oct-23 13-Oct-23 12-Oct-23 12-Oct-23 0d Authority Inspection
Cons-Sup-1200 Formworks for Columns and Core walls 3d 13-Oct-23 17-Oct-23 13-Oct-23 16-Oct-23 0d Formworks for Columns and Core walls
Cons-Sup-1210 Casting of Columns and Core walls 2d 17-Oct-23 19-Oct-23 17-Oct-23 18-Oct-23 0d Casting of Columns and Core walls
Pools 18d 06-Oct-23 27-Oct-23 09-Oct-23 28-Oct-23 2d 27-Oct-23, Pools
A3470 Bottom Slab - Reinforcement & Formwork Fixing 4d 06-Oct-23 11-Oct-23 09-Oct-23 12-Oct-23 2d Bottom Slab - Reinforcement & Formwork Fixing
A3510 Bottom Slab - MEP 1st Fix 2d 11-Oct-23 13-Oct-23 13-Oct-23 14-Oct-23 2d Bottom Slab - MEP 1st Fix
A3480 Bottom Slab - Concrete Pouring 1d 13-Oct-23 14-Oct-23 16-Oct-23 16-Oct-23 2d Bottom Slab - Concrete Pouring
A3490 Wall s & Beams- Rein forcement & Formwork Fixing 6d 14-Oct-23 21-Oct-23 17-Oct-23 23-Oct-23 2d Wall s & Beams- Rein forcement & Formwork Fixing
A3520 Wall s - MEP 1st Fix 2d 21-Oct-23 24-Oct-23 24-Oct-23 25-Oct-23 2d Wall s - MEP 1st Fix
A3500 Wall s & Beams - Concrete Pourin g 3d 24-Oct-23 27-Oct-23 26-Oct-23 28-Oct-23 2d Wall s & Beams - Concrete Pourin g
Slab & Staircase 20d 19-Oct-23 11-Nov-23 19-Oct-23 29-Dec-23 42d 11-Nov-23, Slab & Staircase
Cons-Sup-1220 Formworks for Slab and Staircase 5d 19-Oct-23 25-Oct-23 19-Oct-23 24-Oct-23 0d Formworks for Slab and Staircase
Cons-Sup-1230 Reinforcement/PT for Slab and Staircase 4d 25-Oct-23 30-Oct-23 25-Oct-23 28-Oct-23 0d Reinforcement/PT for Slab and Staircase
Cons-Sup-1240 MEP 1st Fix inside the slab 1d 30-Oct-23 31-Oct-23 30-Oct-23 30-Oct-23 0d MEP 1st Fix inside the slab
Cons-Sup-1250 Authority Inspection 1d 31-Oct-23 01-Nov-23 31-Oct-23 31-Oct-23 0d Authority Inspection
Cons-Sup-1260 Casting of Slab and Staircase 1d 31-Oct-23 01-Nov-23 31-Oct-23 31-Oct-23 0d Casting of Slab and Staircase
Cons-Sup-1270 De-Shuttering 2d 09-Nov-23 11-Nov-23 28-Dec-23 29-Dec-23 42d De-Shuttering
2nd to 3rd Floor 32d 01-Nov-23 08-Dec-23 01-Nov-23 16-Jan-24 33d 08-Dec-23, 2nd to 3rd Floor
Columns & Walls 11d 01-Nov-23 14-Nov-23 01-Nov-23 13-Nov-23 0d 14-Nov-23, Columns & Wall s
Cons-Sup-1280 Reinforcement for Columns and Core walls 5d 01-Nov-23 07-Nov-23 01-Nov-23 06-Nov-23 0d Reinforcement for Columns and Core walls

Actual Level of Effort Remaining Work Milestone Page 9 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Cons-Sup-1850 Authority Inspection 1d 07-Nov-23 08-Nov-23 07-Nov-23 07-Nov-23 0d Authority Inspection
Cons-Sup-1290 Formworks for Columns and Core walls 3d 08-Nov-23 11-Nov-23 08-Nov-23 10-Nov-23 0d Formworks for Columns and Core walls
Cons-Sup-1300 Casting of Columns and Core walls 2d 11-Nov-23 14-Nov-23 11-Nov-23 13-Nov-23 0d Casting of Columns and Core walls
Slab & Staircase 21d 14-Nov-23 08-Dec-23 14-Nov-23 16-Jan-24 33d 08-Dec-23, Slab & Staircase
Cons-Sup-1310 Formworks for Slab and Staircase 4d 14-Nov-23 18-Nov-23 14-Nov-23 17-Nov-23 0d Formworks for Slab and Staircase
Cons-Sup-1320 Reinforcement/PT for Slab and Staircase 4d 18-Nov-23 23-Nov-23 18-Nov-23 22-Nov-23 0d Reinforcement/PT for Slab and Staircase
Cons-Sup-1330 MEP 1st Fix inside the slab 1d 23-Nov-23 24-Nov-23 23-Nov-23 23-Nov-23 0d MEP 1st Fix inside the slab
Cons-Sup-1340 Authority Inspection 1d 24-Nov-23 27-Nov-23 24-Nov-23 24-Nov-23 0d Authority Inspection
Cons-Sup-1350 Casting of Slab and Staircase 1d 27-Nov-23 28-Nov-23 27-Nov-23 27-Nov-23 0d Casting of Slab and Staircase
Cons-Sup-1360 De-shuttering 2d 06-Dec-23 08-Dec-23 15-Jan-24 16-Jan-24 33d De-shuttering
3rd to 4th Floor 34d 28-Nov-23 08-Jan-24 28-Nov-23 01-Feb-24 22d 08-Jan-24, 3rd to 4th Floor
Columns & Walls 12d 28-Nov-23 12-Dec-23 28-Nov-23 11-Dec-23 0d 12-Dec-23, Columns & Wall s
Cons-Sup-1370 Reinforcement for Columns and Core walls 5d 28-Nov-23 04-Dec-23 28-Nov-23 02-Dec-23 0d Reinforcement for Columns and Core walls
Cons-Sup-1860 Authority Inspection 1d 04-Dec-23 05-Dec-23 04-Dec-23 04-Dec-23 0d Authority Inspection
Cons-Sup-1380 Formworks for Columns and Core walls 3d 05-Dec-23 08-Dec-23 05-Dec-23 07-Dec-23 0d Formworks for Columns and Core walls
Cons-Sup-1390 Casting of Columns and Core walls 2d 09-Dec-23 12-Dec-23 09-Dec-23 11-Dec-23 0d Casting of Columns and Core walls
Slab & Staircase 22d 12-Dec-23 08-Jan-24 12-Dec-23 01-Feb-24 22d 08-Jan-24, Slab & Staircase
Cons-Sup-1400 Formworks for Slab and Staircase 4d 12-Dec-23 16-Dec-23 12-Dec-23 15-Dec-23 0d Formworks for Slab and Staircase
Cons-Sup-1410 Reinforcement/PT for Slab and Staircase 4d 16-Dec-23 21-Dec-23 16-Dec-23 20-Dec-23 0d Reinforcement/PT for Slab and Staircase
Cons-Sup-1420 MEP 1st Fix inside the slab 1d 21-Dec-23 22-Dec-23 21-Dec-23 21-Dec-23 0d MEP 1st Fix inside the slab
Cons-Sup-1430 Authority Inspection 1d 22-Dec-23 25-Dec-23 22-Dec-23 22-Dec-23 0d Authority Inspection
Cons-Sup-1440 Casting of Slab and Staircase 1d 25-Dec-23 26-Dec-23 25-Dec-23 25-Dec-23 0d Casting of Slab and Staircase
Cons-Sup-1450 De-shuttering 3d 04-Jan-24 08-Jan-24 30-Jan-24 01-Feb-24 22d De-shuttering
4th to 5th floor 31d 26-Dec-23 01-Feb-24 26-Dec-23 17-Feb-24 15d 01-Feb-24, 4th to 5th floor
Columns & Walls 9d 26-Dec-23 06-Jan-24 26-Dec-23 05-Jan-24 0d 06-Jan-24, Columns & Walls
Cons-Sup-1460 Reinforcement for Columns and Core walls 5d 26-Dec-23 02-Jan-24 26-Dec-23 30-Dec-23 0d Reinforcement for Columns and Core walls
Cons-Sup-1870 Authority Inspection 1d 02-Jan-24 03-Jan-24 02-Jan-24 02-Jan-24 0d Authority Inspection
Cons-Sup-1470 Formworks for Columns and Core walls 2d 03-Jan-24 05-Jan-24 03-Jan-24 04-Jan-24 0d Formworks for Columns and Core walls
Cons-Sup-1480 Casting of Columns and Core walls 1d 05-Jan-24 06-Jan-24 05-Jan-24 05-Jan-24 0d Casting of Columns and Core walls
Slab & Staircase 22d 06-Jan-24 01-Feb-24 06-Jan-24 17-Feb-24 15d 01-Feb-24, Slab & Staircase
5th to 6th floor 32d 20-Jan-24 27-Feb-24 20-Jan-24 05-Mar-24 7d 27-Feb-24, 5th to 6th floor
Columns & Walls 12d 20-Jan-24 03-Feb-24 20-Jan-24 02-Feb-24 0d 03-Feb-24, Columns & Walls
Cons-Sup-1550 Reinforcement for Columns and Core walls 5d 20-Jan-24 26-Jan-24 20-Jan-24 25-Jan-24 0d Reinforcement for Columns and Core walls
Cons-Sup-1880 Authority Inspection 1d 26-Jan-24 29-Jan-24 26-Jan-24 26-Jan-24 0d Authority Inspection
Cons-Sup-1560 Formworks for Columns and Core walls 3d 29-Jan-24 01-Feb-24 29-Jan-24 31-Jan-24 0d Formworks for Columns and Core walls
Cons-Sup-1570 Casting of Columns and Core walls 2d 01-Feb-24 03-Feb-24 01-Feb-24 02-Feb-24 0d Casting of Columns and Core walls
Slab & Staircase 20d 03-Feb-24 27-Feb-24 03-Feb-24 05-Mar-24 7d 27-Feb-24, Slab & Staircase
Cons-Sup-1580 Formworks for Slab and Staircase 4d 03-Feb-24 08-Feb-24 03-Feb-24 07-Feb-24 0d Formworks for Slab and Staircase
Cons-Sup-1590 Reinforcement/PT for Slab and Staircase 4d 08-Feb-24 13-Feb-24 08-Feb-24 12-Feb-24 0d Reinforcement/PT for Slab and Staircase
Cons-Sup-1600 MEP 1st Fix inside the Slab and Staircase 1d 13-Feb-24 14-Feb-24 13-Feb-24 13-Feb-24 0d MEP 1st Fix inside the Slab and Staircase
Cons-Sup-1610 Authority Inspection 1d 14-Feb-24 15-Feb-24 14-Feb-24 14-Feb-24 0d Authority Inspection
Cons-Sup-1620 Casting of Slab and Staircase 1d 15-Feb-24 16-Feb-24 15-Feb-24 15-Feb-24 0d Casting of Slab and Staircase
Cons-Sup-1630 Deshuttering 2d 24-Feb-24 27-Feb-24 04-Mar-24 05-Mar-24 7d Deshuttering
6th to roof floor 30d 16-Feb-24 23-Mar-24 16-Feb-24 22-Mar-24 0d 23-Mar-24, 6th to roof floor
Columns & Walls 10d 16-Feb-24 28-Feb-24 16-Feb-24 27-Feb-24 0d 28-Feb-24, Columns & Walls
Cons-Sup-1640 Reinforcement for Columns and Core walls 4d 16-Feb-24 21-Feb-24 16-Feb-24 20-Feb-24 0d Reinforcement for Columns and Core walls
Cons-Sup-1890 Authority Inspection 1d 21-Feb-24 22-Feb-24 21-Feb-24 21-Feb-24 0d Authority Inspection
Cons-Sup-1650 Formworks for Columns and Core walls 3d 22-Feb-24 26-Feb-24 22-Feb-24 24-Feb-24 0d Formworks for Columns and Core walls
Cons-Sup-1660 Casting of Columns and Core walls 2d 26-Feb-24 28-Feb-24 26-Feb-24 27-Feb-24 0d Casting of Columns and Core walls
Slab & Staircase 20d 28-Feb-24 23-Mar-24 28-Feb-24 22-Mar-24 0d 23-Mar-24, Slab & Staircase
Cons-Sup-1670 Formworks for Slab and Staircase 4d 28-Feb-24 04-Mar-24 28-Feb-24 02-Mar-24 0d Formworks for Slab and Staircase
Cons-Sup-1680 Reinforcement/PT for Slab and Staircase 4d 04-Mar-24 09-Mar-24 04-Mar-24 08-Mar-24 0d Reinforcement/PT for Slab and Staircase

Actual Level of Effort Remaining Work Milestone Page 10 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Cons-Sup-1690 MEP 1st Fix inside the Slab & Staircase 1d 09-Mar-24 11-Mar-24 09-Mar-24 09-Mar-24 0d MEP 1st Fix inside the Slab & Staircase
Cons-Sup-1700 Authority Inspection 1d 11-Mar-24 12-Mar-24 11-Mar-24 11-Mar-24 0d Authority Inspection
Cons-Sup-1710 Casting of Slab and Staircase 1d 12-Mar-24 13-Mar-24 12-Mar-24 12-Mar-24 0d Casting of Slab and Staircase
Cons-Sup-1720 De-shuttering 2d 21-Mar-24 23-Mar-24 21-Mar-24 22-Mar-24 0d De-shuttering
Roof to Upper Roof 176d 18-Sep-23 11-Apr-24 19-Aug-24 24-May-25 346d 11-Apr-24, Roof to Upper Roof
Columns & Walls 8d 13-Mar-24 21-Mar-24 19-Aug-24 26-Aug-24 135d 21-Mar-24, Columns & Walls
Cons-Sup-1730 Reinforcement for Core wall 3d 13-Mar-24 16-Mar-24 19-Aug-24 21-Aug-24 136d Reinforcement for Core wall
Cons-Sup-1900 Authority Inspection 1d 18-Mar-24 18-Mar-24 22-Aug-24 22-Aug-24 113d Authority Inspection
Cons-Sup-1740 Formworks for Core wall 2d 19-Mar-24 20-Mar-24 23-Aug-24 24-Aug-24 135d Formworks for Core wall
Cons-Sup-1750 Casting of Core wall 1d 21-Mar-24 21-Mar-24 26-Aug-24 26-Aug-24 135d Casting of Core wall
Slab 16d 22-Mar-24 09-Apr-24 27-Aug-24 24-May-25 348d 09-Apr-24, Slab
Cons-Sup-1760 Formworks for slab 3d 22-Mar-24 25-Mar-24 27-Aug-24 29-Aug-24 135d Formworks for slab
Cons-Sup-1770 Reinforcement/PT for slab 2d 26-Mar-24 27-Mar-24 30-Aug-24 31-Aug-24 135d Reinforcement/PT for slab
Cons-Sup-1780 MEP 1st Fix inside the slab 1d 28-Mar-24 28-Mar-24 02-Sep-24 02-Sep-24 135d MEP 1st Fix inside the slab
Cons-Sup-1790 Authority Inspection 1d 29-Mar-24 29-Mar-24 03-Sep-24 03-Sep-24 112d Authority Inspection
Cons-Sup-1800 Casting of Slab 1d 30-Mar-24 30-Mar-24 04-Sep-24 04-Sep-24 135d Casting of Slab
Cons-Sup-1810 De-Shuttering 1d 09-Apr-24 09-Apr-24 24-May-25 24-May-25 348d De-Shuttering
Lift Machine Room 10d 01-Apr-24 11-Apr-24 05-Sep-24 16-Sep-24 135d 11-Apr-24, Lift Machine Room
Cons-Sup-1910 Construction of lift machine room 10d 01-Apr-24 11-Apr-24 05-Sep-24 16-Sep-24 135d Construction of lift machine room
Equipment Bases 11d 18-Sep-23 30-Sep-23 20-Mar-25 24-May-25 511d 30-Sep-23, Equipment Bases
A3530 Equipment Bases - Reinforcement & Formwork Fixing
5d 18-Sep-23 23-Sep-23 20-Mar-25 24-Mar-25 464d Equipment Bases - Reinforcement & Formwork Fixing
A3540 Equipment Bases - MEP 1st Fix 2d 23-Sep-23 26-Sep-23 25-Mar-25 26-Mar-25 464d Equipment Bases - MEP 1st Fix
A3550 Equipment Bases - Concrete Pouring 4d 26-Sep-23 30-Sep-23 21-May-25 24-May-25 511d Equipment Bases - Concrete Pouring
Parapett Wall 4d 13-Mar-24 18-Mar-24 21-May-25 24-May-25 368d 18-Mar-24, Parapett Wall
Cons-Sup-1820 Parapet Wall - Rein forcement & Formwork Fix ing 3d 13-Mar-24 16-Mar-24 21-May-25 23-May-25 368d Parapet Wall - Rein forcement & Formwork Fix ing
Cons-Sup-1920 Parapet Wall - Concrete Porin g 1d 16-Mar-24 18-Mar-24 24-May-25 24-May-25 368d Parapet Wall - Concrete Porin g
Block Works & MEP 1st Fix 181d 18-Sep-23 18-Apr-24 16-Nov-23 04-Jul-24 67d 18-Apr-24, Block Works & MEP 1st Fix
Ground Floor 34d 18-Sep-23 27-Oct-23 16-Nov-23 17-Feb-24 97d 27-Oct-23, Ground Floor
A4130 At Grade Slab 10d 18-Sep-23 29-Sep-23 16-Nov-23 27-Nov-23 51d At Grade Slab
A3580 Solid & Hollow Block Walls 14d 29-Sep-23 16-Oct-23 28-Nov-23 13-Dec-23 51d Solid & Hollow Block Walls
A4140 Sub-Frame for Door Openings 8d 29-Sep-23 09-Oct-23 29-Jan-24 06-Feb-24 103d Sub-Frame for Door Openings
A3560 Thermal Insulated External Block Walls 5d 10-Oct-23 16-Oct-23 08-Dec-23 13-Dec-23 51d Thermal Insulated External Block Walls
A3570 Internal Cavity Wall s 3d 12-Oct-23 16-Oct-23 11-Dec-23 13-Dec-23 51d Internal Cavity Wall s
A3590 MEP Wall Containment 1st Fix 10d 16-Oct-23 27-Oct-23 07-Feb-24 17-Feb-24 97d MEP Wall Containment 1st Fix
Podium Floor 24d 17-Oct-23 14-Nov-23 14-Dec-23 05-Mar-24 96d 14-Nov-23, Podium Floor
A3620 Solid & Hollow Block Walls 14d 17-Oct-23 02-Nov-23 14-Dec-23 29-Dec-23 50d Solid & Hollow Block Walls
A4150 Sub-Frame for Door Openings 8d 17-Oct-23 26-Oct-23 14-Feb-24 22-Feb-24 102d Sub-Frame for Door Openings
A3600 Thermal Insulated External Block Walls 5d 27-Oct-23 02-Nov-23 25-Dec-23 29-Dec-23 50d Thermal Insulated External Block Walls
A3610 Internal Cavity Wall s 3d 30-Oct-23 02-Nov-23 27-Dec-23 29-Dec-23 50d Internal Cavity Wall s
A3630 MEP Wall Containment 1st Fix 10d 02-Nov-23 14-Nov-23 23-Feb-24 05-Mar-24 96d MEP Wall Containment 1st Fix
1st Floor 24d 11-Nov-23 09-Dec-23 30-Dec-23 29-Feb-24 70d 09-Dec-23, 1st Floor
A3660 Solid & Hollow Block Walls 14d 11-Nov-23 28-Nov-23 30-Dec-23 16-Jan-24 42d Solid & Hollow Block Walls
A4160 Sub-Frame for Door Openings 8d 11-Nov-23 21-Nov-23 09-Feb-24 17-Feb-24 76d Sub-Frame for Door Openings
A3640 Thermal Insulated External Block Walls 5d 22-Nov-23 28-Nov-23 11-Jan-24 16-Jan-24 42d Thermal Insulated External Block Walls
A3650 Internal Cavity Wall s 3d 24-Nov-23 28-Nov-23 13-Jan-24 16-Jan-24 42d Internal Cavity Wall s
A3670 MEP Wall Containment 1st Fix 10d 28-Nov-23 09-Dec-23 19-Feb-24 29-Feb-24 70d MEP Wall Containment 1st Fix
2nd Floor 24d 08-Dec-23 06-Jan-24 17-Jan-24 06-May-24 103d 06-Jan-24, 2nd Floor
A3700 Solid & Hollow Block Walls 14d 08-Dec-23 25-Dec-23 17-Jan-24 01-Feb-24 33d Solid & Hollow Block Walls
A4170 Sub-Frame for Door Openings 8d 08-Dec-23 18-Dec-23 16-Apr-24 24-Apr-24 109d Sub-Frame for Door Openings
A3680 Thermal Insulated External Block Walls 5d 19-Dec-23 25-Dec-23 27-Jan-24 01-Feb-24 33d Thermal Insulated External Block Walls
A3690 Internal Cavity Wall s 3d 21-Dec-23 25-Dec-23 30-Jan-24 01-Feb-24 33d Internal Cavity Wall s
A3710 MEP Wall Containment 1st Fix 10d 25-Dec-23 06-Jan-24 25-Apr-24 06-May-24 103d MEP Wall Containment 1st Fix

Actual Level of Effort Remaining Work Milestone Page 11 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
3rd Floor 24d 08-Jan-24 05-Feb-24 02-Feb-24 25-May-24 95d 05-Feb-24, 3rd Floor
A3740 Solid & Hollow Block Walls 14d 08-Jan-24 24-Jan-24 02-Feb-24 17-Feb-24 22d Solid & Hollow Block Walls
A4180 Sub-Frame for Door Openings 8d 08-Jan-24 17-Jan-24 06-May-24 14-May-24 101d Sub-Frame for Door Openings
A3720 Thermal Insulated External Block Walls 5d 18-Jan-24 24-Jan-24 13-Feb-24 17-Feb-24 22d Thermal Insulated External Block Walls
A3730 Internal Cavity Wall s 3d 20-Jan-24 24-Jan-24 15-Feb-24 17-Feb-24 22d Internal Cavity Wall s
A3750 MEP Wall Containment 1st Fix 10d 24-Jan-24 05-Feb-24 15-May-24 25-May-24 95d MEP Wall Containment 1st Fix
4th Floor 24d 01-Feb-24 29-Feb-24 19-Feb-24 14-Jun-24 91d 29-Feb-24, 4th Floor
A3780 Solid & Hollow Block Walls 14d 01-Feb-24 17-Feb-24 19-Feb-24 05-Mar-24 15d Solid & Hollow Block Walls
A4190 Sub-Frame for Door Openings 8d 01-Feb-24 10-Feb-24 25-May-24 03-Jun-24 97d Sub-Frame for Door Openings
A3760 Thermal Insulated External Block Walls 5d 12-Feb-24 17-Feb-24 29-Feb-24 05-Mar-24 15d Thermal Insulated External Block Walls
A3770 Internal Cavity Wall s 3d 14-Feb-24 17-Feb-24 02-Mar-24 05-Mar-24 15d Internal Cavity Wall s
A3790 MEP Wall Containment 1st Fix 10d 17-Feb-24 29-Feb-24 04-Jun-24 14-Jun-24 91d MEP Wall Containment 1st Fix
5th Floor 24d 27-Feb-24 27-Mar-24 06-Mar-24 04-Jul-24 86d 27-Mar-24, 5th Floor
A3820 Solid & Hollow Block Walls 14d 27-Feb-24 15-Mar-24 06-Mar-24 22-Mar-24 7d Solid & Hollow Block Walls
A4200 Sub-Frame for Door Openings 8d 27-Feb-24 08-Mar-24 14-Jun-24 22-Jun-24 92d Sub-Frame for Door Openings
A3800 Thermal Insulated External Block Walls 5d 09-Mar-24 15-Mar-24 18-Mar-24 22-Mar-24 7d Thermal Insulated External Block Walls
A3810 Internal Cavity Wall s 3d 12-Mar-24 15-Mar-24 20-Mar-24 22-Mar-24 7d Internal Cavity Wall s
A3830 MEP Wall Containment 1st Fix 10d 15-Mar-24 27-Mar-24 24-Jun-24 04-Jul-24 86d MEP Wall Containment 1st Fix
6th Floor 22d 23-Mar-24 18-Apr-24 23-Mar-24 17-Apr-24 0d 18-Apr-24, 6th Floor
A3860 Solid & Hollow Block Walls 12d 23-Mar-24 06-Apr-24 23-Mar-24 05-Apr-24 0d Solid & Hollow Block Walls
A4210 Sub-Frame for Door Openings 8d 23-Mar-24 02-Apr-24 28-Mar-24 05-Apr-24 4d Sub-Frame for Door Openings
A3840 Thermal Insulated External Block Walls 5d 01-Apr-24 06-Apr-24 01-Apr-24 05-Apr-24 0d Thermal Insulated External Block Walls
A3850 Internal Cavity Wall s 3d 03-Apr-24 06-Apr-24 03-Apr-24 05-Apr-24 0d Internal Cavity Wall s
A3870 MEP Wall Containment 1st Fix 10d 06-Apr-24 18-Apr-24 06-Apr-24 17-Apr-24 0d MEP Wall Containment 1st Fix
Plaster Works 275d 27-Oct-23 14-Sep-24 19-Feb-24 24-May-25 213d 14-Sep-24, Plaster Works
Basement Floor 5d 27-Oct-23 02-Nov-23 20-May-25 24-May-25 483d 02-Nov-23, Basement Floor
A4220 Plaster Works 5d 27-Oct-23 02-Nov-23 20-May-25 24-May-25 483d Plaster Works
Ground Floor 28d 27-Oct-23 29-Nov-23 19-Feb-24 22-Mar-24 97d 29-Nov-23, Ground Floor
A3880 Wall Pla ster 12d 27-Oct-23 10-Nov-23 19-Feb-24 02-Mar-24 97d Wall Pla ster
A3900 Ceiling Plaster 7d 10-Nov-23 18-Nov-23 04-Mar-24 12-Mar-24 97d Ceiling Plaster
A3890 External Wall Spray Plaster 5d 18-Nov-23 24-Nov-23 13-Mar-24 18-Mar-24 97d External Wall Spray Plaster
A4360 1:3 Cement Sand Screed for Water Proofing 4d 24-Nov-23 29-Nov-23 19-Mar-24 22-Mar-24 97d 1:3 Cement Sand Screed for Water Proofing
Podium Floor 26d 14-Nov-23 14-Dec-23 06-Mar-24 05-Apr-24 96d 14-Dec-23, Podium Floor
A3940 Wall Pla ster 12d 14-Nov-23 28-Nov-23 06-Mar-24 20-Mar-24 96d Wall Pla ster
A3930 Ceiling Plaster 7d 28-Nov-23 06-Dec-23 21-Mar-24 28-Mar-24 96d Ceiling Plaster
A3920 External Wall Spray Plaster 5d 06-Dec-23 12-Dec-23 29-Mar-24 03-Apr-24 96d External Wall Spray Plaster
A6420 1:3 Cement Sand Screed for Water Proofing 2d 12-Dec-23 14-Dec-23 04-Apr-24 05-Apr-24 96d 1:3 Cement Sand Screed for Water Proofing
1st Floor 46d 09-Dec-23 02-Feb-24 01-Mar-24 24-Apr-24 70d 02-Feb-24, 1st Floor
A3970 Wall Pla ster 15d 09-Dec-23 27-Dec-23 01-Mar-24 19-Mar-24 70d Wall Pla ster
A3960 Ceiling Plaster 10d 27-Dec-23 09-Jan-24 20-Mar-24 30-Mar-24 70d Ceiling Plaster
A3950 External Wall Spray Plaster 7d 09-Jan-24 17-Jan-24 01-Apr-24 08-Apr-24 70d External Wall Spray Plaster
A3910 Sauna & Steam Spray Plaster 4d 17-Jan-24 22-Jan-24 09-Apr-24 12-Apr-24 70d Sauna & Steam Spray Plaster
A6430 1:3 Cement Sand Screed for Water Proofing 10d 22-Jan-24 02-Feb-24 13-Apr-24 24-Apr-24 70d 1:3 Cement Sand Screed for Water Proofing
2nd Floor 32d 06-Jan-24 13-Feb-24 07-May-24 12-Jun-24 103d 13-Feb-24, 2nd Floor
A4000 Wall Pla ster 12d 06-Jan-24 20-Jan-24 07-May-24 20-May-24 103d Wall Plaster
A3990 Ceiling Plaster 7d 20-Jan-24 29-Jan-24 21-May-24 28-May-24 103d Ceiling Plaster
A3980 External Wall Spray Plaster 5d 29-Jan-24 03-Feb-24 29-May-24 03-Jun-24 103d External Wall Spray Plaster
A6440 1:3 Cement Sand Screed for Water Proofing 8d 03-Feb-24 13-Feb-24 04-Jun-24 12-Jun-24 103d 1:3 Cement Sand Screed for Water Proofing
3rd Floor 32d 05-Feb-24 14-Mar-24 27-May-24 02-Jul-24 95d 14-Mar-24, 3rd Floor
A4030 Wall Pla ster 12d 05-Feb-24 19-Feb-24 27-May-24 08-Jun-24 95d Wall Pla ster
A4020 Ceiling Plaster 7d 19-Feb-24 27-Feb-24 10-Jun-24 17-Jun-24 95d Ceiling Plaster
A4010 External Wall Spray Plaster 5d 27-Feb-24 04-Mar-24 18-Jun-24 22-Jun-24 95d External Wall Spray Plaster

Actual Level of Effort Remaining Work Milestone Page 12 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A6450 1:3 Cement Sand Screed for Water Proofing 8d 04-Mar-24 14-Mar-24 24-Jun-24 02-Jul-24 95d 1:3 Cement Sand Screed for Water Proofing
4th Floor 32d 29-Feb-24 08-Apr-24 15-Jun-24 22-Jul-24 91d 08-Apr-24, 4th Floor
A4060 Wall Pla ster 12d 29-Feb-24 15-Mar-24 15-Jun-24 28-Jun-24 91d Wall Pla ster
A4050 Ceiling Plaster 7d 15-Mar-24 23-Mar-24 29-Jun-24 06-Jul-24 91d Ceiling Plaster
A4040 External Wall Spray Plaster 5d 23-Mar-24 29-Mar-24 08-Jul-24 12-Jul-24 91d External Wall Spray Plaster
A6460 1:3 Cement Sand Screed for Water Proofing 8d 29-Mar-24 08-Apr-24 13-Jul-24 22-Jul-24 91d 1:3 Cement Sand Screed for Water Proofing
5th Floor 32d 27-Mar-24 03-May-24 05-Jul-24 10-Aug-24 86d 03-May-24, 5th Floor
A4090 Wall Pla ster 12d 27-Mar-24 10-Apr-24 05-Jul-24 18-Jul-24 86d Wall Pla ster
A4080 Ceiling Plaster 7d 10-Apr-24 18-Apr-24 19-Jul-24 26-Jul-24 86d Ceiling Plaster
A4070 External Wall Spray Plaster 5d 18-Apr-24 24-Apr-24 27-Jul-24 01-Aug-24 86d External Wall Spray Plaster
A6470 1:3 Cement Sand Screed for Water Proofing 8d 24-Apr-24 03-May-24 02-Aug-24 10-Aug-24 86d 1:3 Cement Sand Screed for Water Proofing
6th Floor 32d 18-Apr-24 25-May-24 18-Apr-24 02-Oct-24 112d 25-May-24, 6th Floor
A4120 Wall Pla ster 12d 18-Apr-24 02-May-24 18-Apr-24 01-May-24 0d Wall Pla ster
A4110 Ceiling Plaster 7d 02-May-24 10-May-24 02-May-24 09-May-24 0d Ceiling Plaster
A4100 External Wall Spray Plaster 5d 10-May-24 16-May-24 10-May-24 15-May-24 0d External Wall Spray Plaster
A6480 1:3 Cement Sand Screed for Water Proofing 8d 16-May-24 25-May-24 24-Sep-24 02-Oct-24 112d 1:3 Cement Sand Screed for Water Proofing
Roof Floor 116d 02-May-24 14-Sep-24 06-Jan-25 24-May-25 213d 14-Sep-24, Roof Floor
Civil Works 39d 02-May-24 17-Jun-24 06-Jan-25 19-Feb-25 209d 17-Jun-24, Civil Works
M&F-RF-1000 Block Work 12d 02-May-24 16-May-24 06-Jan-25 18-Jan-25 209d Block Work
M&F-RF-1020 Plaster Work 15d 16-May-24 03-Jun-24 20-Jan-25 05-Feb-25 209d Plaster Work
M&F-RF-1050 Equipment and Tank Foundation 12d 03-Jun-24 17-Jun-24 06-Feb-25 19-Feb-25 209d Equipment and Tank Foundation
Roof Waterproofing 77d 17-Jun-24 14-Sep-24 20-Feb-25 24-May-25 213d 14-Sep-24, Roof Waterproofing
M&F-RF-1060 Cleaning and surface preparation for water rpoofing20d 17-Jun-24 10-Jul-24 20-Feb-25 15-Mar-25 209d Cleaning and surface preparation for water rpoofing
M&F-RF-1070 Roofing system +test 20d 10-Jul-24 02-Aug-24 17-Mar-25 07-Apr-25 209d Roofing system +test
M&F-RF-1080 Screed Concrete 15d 02-Aug-24 20-Aug-24 08-Apr-25 24-Apr-25 209d Screed Concrete
M&F-RF-1100 MEP 2nd fix 12d 20-Aug-24 03-Sep-24 30-Apr-25 13-May-25 213d MEP 2nd fix
M&F-RF-1090 Final Finish 10d 03-Sep-24 14-Sep-24 14-May-25 24-May-25 213d Final Finish
MEP 2nd Fix 177d 29-Nov-23 25-Jun-24 23-Mar-24 01-Nov-24 112d 25-Jun-24, MEP 2nd Fix
Ground Floor 32d 29-Nov-23 06-Jan-24 23-Mar-24 29-Apr-24 97d 06-Jan-24, Ground Floor
A6490 Installation of Cable Trays 10d 29-Nov-23 11-Dec-23 23-Mar-24 03-Apr-24 97d Installation of Cable Trays
A6500 Pulling of Cables of all utilities 10d 11-Dec-23 22-Dec-23 04-Apr-24 15-Apr-24 97d Pulling of Cables of all utilities
A6510 Installation of Pipes / Conduits of Fire Fighting etc. 12d 22-Dec-23 06-Jan-24 16-Apr-24 29-Apr-24 97d Installation of Pipes / Conduits of Fire Fighting etc.
Podium Floor 32d 14-Dec-23 22-Jan-24 06-Apr-24 13-May-24 96d 22-Jan-24, Podium Floor
A6520 Installation of Cable Trays 10d 14-Dec-23 26-Dec-23 06-Apr-24 17-Apr-24 96d Installation of Cable Trays
A6530 Pulling of Cables of all utilities 10d 26-Dec-23 08-Jan-24 18-Apr-24 29-Apr-24 96d Pulling of Cables of all utilities
A6540 Installation of Pipes / Conduits of Fire Fighting etc. 12d 08-Jan-24 22-Jan-24 30-Apr-24 13-May-24 96d Installation of Pipes / Conduits of Fire Fighting etc.
1st Floor 26d 02-Feb-24 04-Mar-24 25-Apr-24 24-May-24 70d 04-Mar-24, 1st Floor
A6550 Installation of Cable Trays 8d 02-Feb-24 12-Feb-24 25-Apr-24 03-May-24 70d Installation of Cable Trays
A6560 Pulling of Cables of all utilities 8d 12-Feb-24 21-Feb-24 04-May-24 13-May-24 70d Pulling of Cables of all utilities
A6570 Installation of Pipes / Conduits of Fire Fighting etc. 10d 21-Feb-24 04-Mar-24 14-May-24 24-May-24 70d Installation of Pipes / Conduits of Fire Fighting etc.
2nd Floor 27d 13-Feb-24 16-Mar-24 13-Jun-24 12-Jul-24 102d 16-Mar-24, 2nd Floor
A6580 Installation of Cable Trays 8d 13-Feb-24 22-Feb-24 13-Jun-24 21-Jun-24 103d Installation of Cable Trays
A6590 Pulling of Cables of all utilities 8d 22-Feb-24 02-Mar-24 22-Jun-24 01-Jul-24 103d Pulling of Cables of all utilities
A6600 Installation of Pipes / Conduits of Fire Fighting etc. 10d 04-Mar-24 16-Mar-24 02-Jul-24 12-Jul-24 102d Installation of Pipes / Conduits of Fire Fighting etc.
3rd Floor 26d 14-Mar-24 13-Apr-24 03-Jul-24 01-Aug-24 95d 13-Apr-24, 3rd Floor
A6610 Installation of Cable Trays 8d 14-Mar-24 23-Mar-24 03-Jul-24 11-Jul-24 95d Installation of Cable Trays
A6620 Pulling of Cables of all utilities 8d 23-Mar-24 02-Apr-24 12-Jul-24 20-Jul-24 95d Pulling of Cables of all utilities
A6630 Installation of Pipes / Conduits of Fire Fighting etc. 10d 02-Apr-24 13-Apr-24 22-Jul-24 01-Aug-24 95d Installation of Pipes / Conduits of Fire Fighting etc.
4th Floor 26d 08-Apr-24 08-May-24 23-Jul-24 21-Aug-24 91d 08-May-24, 4th Floor
A6640 Installation of Cable Trays 8d 08-Apr-24 17-Apr-24 23-Jul-24 31-Jul-24 91d Installation of Cable Trays
A6650 Pulling of Cables of all utilities 8d 17-Apr-24 26-Apr-24 01-Aug-24 09-Aug-24 91d Pulling of Cables of all utilities
A6660 Installation of Pipes / Conduits of Fire Fighting etc. 10d 26-Apr-24 08-May-24 10-Aug-24 21-Aug-24 91d Installation of Pipes / Conduits of Fire Fighting etc.

Actual Level of Effort Remaining Work Milestone Page 13 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
5th Floor 26d 03-May-24 03-Jun-24 12-Aug-24 10-Sep-24 86d 03-Jun-24, 5th Floor
A6670 Installation of Cable Trays 8d 03-May-24 13-May-24 12-Aug-24 20-Aug-24 86d Installation of Cable Trays
A6680 Pulling of Cables of all utilities 8d 13-May-24 22-May-24 21-Aug-24 29-Aug-24 86d Pulling of Cables of all utilities
A6690 Installation of Pipes / Conduits of Fire Fighting etc. 10d 22-May-24 03-Jun-24 30-Aug-24 10-Sep-24 86d Installation of Pipes / Conduits of Fire Fighting etc.
6th Floor 26d 25-May-24 25-Jun-24 03-Oct-24 01-Nov-24 112d 25-Jun-24, 6th Floor
A6700 Installation of Cable Trays 8d 25-May-24 04-Jun-24 03-Oct-24 11-Oct-24 112d Installation of Cable Trays
A6710 Pulling of Cables of all utilities 8d 04-Jun-24 13-Jun-24 12-Oct-24 21-Oct-24 112d Pulling of Cables of all utilities
A6720 Installation of Pipes / Conduits of Fire Fighting etc. 10d 13-Jun-24 25-Jun-24 22-Oct-24 01-Nov-24 112d Installation of Pipes / Conduits of Fire Fighting etc.
Ceiling Finishes Works 124d 15-Apr-24 05-Sep-24 08-May-24 21-Nov-24 66d 05-Sep-24, Ceiling Finishes Works
Ground Floor 14d 15-Apr-24 30-Apr-24 08-May-24 23-May-24 20d 30-Apr-24, Ground Floor
Entrance & Entrance Hall 3d 15-Apr-24 17-Apr-24 08-May-24 10-May-24 20d 17-Apr-24, Entrance & Entrance Hall
A4270 Suspension of Ceiling using Gypsum Board 3d 15-Apr-24 17-Apr-24 08-May-24 10-May-24 20d Suspension of Ceiling using Gypsum Board
Shops 9d 18-Apr-24 27-Apr-24 11-May-24 21-May-24 20d 27-Apr-24, Shops
A4350 Suspension of Ceiling using Gypsum Board in Shops6d 18-Apr-24 24-Apr-24 11-May-24 17-May-24 20d Suspension of Ceiling using Gypsum Board in Shops
A4340 Suspension of Ceiling using Water Resistant Board in
3dWR
25-Apr-24 27-Apr-24 18-May-24 21-May-24 20d Suspension of Ceiling using Water Resistant Board in WR
Security Room and Public Washrooms 2d 29-Apr-24 30-Apr-24 22-May-24 23-May-24 20d 30-Apr-24, Security Room and Public Washrooms
A4370 Installation of 600x600 ceiling tile. 2d 29-Apr-24 30-Apr-24 22-May-24 23-May-24 20d Installation of 600x600 ceiling tile.
1st Floor 24d 02-May-24 29-May-24 25-May-24 12-Jul-24 38d 29-May-24, 1st Floor
Apartment, Corridor & Wet Area 17d 02-May-24 21-May-24 25-May-24 13-Jun-24 20d 21-May-24, Apartment, Corridor & Wet Area
A4380 Suspension of Ceiling using Gypsum Board 12d 02-May-24 15-May-24 25-May-24 07-Jun-24 20d Suspension of Ceiling using Gypsum Board
A4390 Suspension of Ceiling using Water Resistant Board 5d 16-May-24 21-May-24 08-Jun-24 13-Jun-24 20d Suspension of Ceiling using Water Resistant Board
GYM, Steam & Sauna 7d 22-May-24 29-May-24 05-Jul-24 12-Jul-24 38d 29-May-24, GYM, Steam & Sauna
A4400 Suspension of Ceiling using Gypsum Board 4d 22-May-24 25-May-24 05-Jul-24 09-Jul-24 38d Suspension of Ceiling using Gypsum Board
A4410 Installation of 600x600 ceiling tile. 3d 27-May-24 29-May-24 10-Jul-24 12-Jul-24 38d Installation of 600x600 ceiling tile.
2nd Floor 17d 30-May-24 18-Jun-24 13-Jul-24 01-Aug-24 38d 18-Jun-24, 2nd Floor
Apartment, Corridor & Wet Area 17d 30-May-24 18-Jun-24 13-Jul-24 01-Aug-24 38d 18-Jun-24, Apartment, Corridor & Wet Area
A4420 Suspension of Ceiling using Gypsum Board 12d 30-May-24 12-Jun-24 13-Jul-24 26-Jul-24 38d Suspension of Ceiling using Gypsum Board
A4430 Suspension of Ceiling using Water Resistant Board 5d 13-Jun-24 18-Jun-24 27-Jul-24 01-Aug-24 38d Suspension of Ceiling using Water Resistant Board
3rd Floor 17d 19-Jun-24 08-Jul-24 02-Aug-24 21-Aug-24 38d 08-Jul-24, 3rd Floor
Apartment, Corridor & Wet Area 17d 19-Jun-24 08-Jul-24 02-Aug-24 21-Aug-24 38d 08-Jul-24, Apartment, Corridor & Wet Area
A4440 Suspension of Ceiling using Gypsum Board 12d 19-Jun-24 02-Jul-24 02-Aug-24 15-Aug-24 38d Suspension of Ceiling using Gypsum Board
A4450 Suspension of Ceiling using Water Resistant Board 5d 03-Jul-24 08-Jul-24 16-Aug-24 21-Aug-24 38d Suspension of Ceiling using Water Resistant Board
4th Floor 17d 09-Jul-24 27-Jul-24 22-Aug-24 10-Sep-24 38d 27-Jul-24, 4th Floor
Apartment, Corridor & Wet Area 17d 09-Jul-24 27-Jul-24 22-Aug-24 10-Sep-24 38d 27-Jul-24, Apartment, Corridor & Wet Area
A4460 Suspension of Ceiling using Gypsum Board 12d 09-Jul-24 22-Jul-24 22-Aug-24 04-Sep-24 38d Suspension of Ceiling using Gypsum Board
A4470 Suspension of Ceiling using Water Resistant Board 5d 23-Jul-24 27-Jul-24 05-Sep-24 10-Sep-24 38d Suspension of Ceiling using Water Resistant Board
5th Floor 17d 29-Jul-24 16-Aug-24 11-Sep-24 30-Sep-24 38d 16-Aug-24, 5th Floor
Apartment, Corridor & Wet Area 17d 29-Jul-24 16-Aug-24 11-Sep-24 30-Sep-24 38d 16-Aug-24, Apartment, Corridor & Wet Area
A4480 Suspension of Ceiling using Gypsum Board 12d 29-Jul-24 10-Aug-24 11-Sep-24 24-Sep-24 38d Suspension of Ceiling using Gypsum Board
A4490 Suspension of Ceiling using Water Resistant Board 5d 12-Aug-24 16-Aug-24 25-Sep-24 30-Sep-24 38d Suspension of Ceiling using Water Resistant Board
6th Floor 17d 17-Aug-24 05-Sep-24 02-Nov-24 21-Nov-24 66d 05-Sep-24, 6th Floor
Apartment, Corridor & Wet Area 17d 17-Aug-24 05-Sep-24 02-Nov-24 21-Nov-24 66d 05-Sep-24, Apartment, Corridor & Wet Area
A4500 Suspension of Ceiling using Gypsum Board 12d 17-Aug-24 30-Aug-24 02-Nov-24 15-Nov-24 66d Suspension of Ceiling using Gypsum Board
A4510 Suspension of Ceiling using Water Resistant Board 5d 31-Aug-24 05-Sep-24 16-Nov-24 21-Nov-24 66d Suspension of Ceiling using Water Resistant Board
Wall Finishes Works 132d 25-Apr-24 26-Sep-24 16-May-24 24-May-25 202d 26-Sep-24, Wall Finishes Works
Ground Floor 16d 25-Apr-24 14-May-24 16-May-24 25-Apr-25 293d 14-May-24, Ground Floor
Entrance & Entrance Hall 4d 25-Apr-24 30-Apr-24 16-May-24 20-May-24 17d 30-Apr-24, Entrance & Entrance Hall
A4290 Fixing of Natural Marble Glossy finish on Walls 4d 25-Apr-24 30-Apr-24 16-May-24 20-May-24 17d Fixing of Natural Marble Glossy finish on Walls
Shops 6d 30-Apr-24 07-May-24 22-May-24 28-May-24 18d 07-May-24, Shops
A4520 Fixing of Porcelein Glossy Tiles in Wash Rooms 6d 30-Apr-24 07-May-24 22-May-24 28-May-24 18d Fixing of Porcelein Glossy Tiles in Wash Rooms
Garbage Room, Combined MTR GSM Room & Water Meter Room 3d 07-May-24 10-May-24 07-Jun-24 10-Jun-24 26d 10-May-24, Garbage Room, Combined MTR GSM Room & Water Meter Room
A4530 Fixing of Heavy Duty Ceramic Glossy Tile 3d 07-May-24 10-May-24 07-Jun-24 10-Jun-24 26d Fixing of Heavy Duty Ceramic Glossy Tile
Grouting of Tiles 3d 10-May-24 14-May-24 23-Apr-25 25-Apr-25 293d 14-May-24, Grouting of Tiles

Actual Level of Effort Remaining Work Milestone Page 14 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A4730 Grouting of Tiles at Ground Floor Walls 3d 10-May-24 14-May-24 23-Apr-25 25-Apr-25 293d Grouting of Tiles at Ground Floor Walls
1st Floor 24d 22-May-24 18-Jun-24 14-Jun-24 01-May-25 268d 18-Jun-24, 1st Floor
Apartment, Corridor & Wet Area 14d 22-May-24 06-Jun-24 14-Jun-24 29-Jun-24 20d 06-Jun-24, Apartment, Corridor & Wet Area
A4540 Fixing of Glossy Porcelein Tile 10d 22-May-24 01-Jun-24 14-Jun-24 25-Jun-24 20d Fixing of Glossy Porcelein Tile
A4550 Preparation of Niches in Bathrooms 4d 03-Jun-24 06-Jun-24 26-Jun-24 29-Jun-24 20d Preparation of Niches in Bathrooms
Service Area & Electrical Room 3d 03-Jun-24 05-Jun-24 23-Jul-24 25-Jul-24 43d 05-Jun-24, Service Area & Electrical Room
A4570 Fixing of Heavy Duty Ceramic Glossy Tile 3d 03-Jun-24 05-Jun-24 23-Jul-24 25-Jul-24 43d Fixing of Heavy Duty Ceramic Glossy Tile
GYM, Steam & Sauna 6d 06-Jun-24 12-Jun-24 26-Jul-24 01-Aug-24 43d 12-Jun-24, GYM, Steam & Sauna
A4560 Fixing of Glossy Porcelein Tile 6d 06-Jun-24 12-Jun-24 26-Jul-24 01-Aug-24 43d Fixing of Glossy Porcelein Tile
Grouting of Tiles 5d 13-Jun-24 18-Jun-24 26-Apr-25 01-May-25 268d 18-Jun-24, Grouting of Tiles
A4740 Grouting of Tiles at First Floor Walls 5d 13-Jun-24 18-Jun-24 26-Apr-25 01-May-25 268d Grouting of Tiles at First Floor Walls
2nd Floor 18d 19-Jun-24 09-Jul-24 02-Aug-24 06-May-25 254d 09-Jul-24, 2nd Floor
Apartment, Corridor & Wet Area 14d 19-Jun-24 04-Jul-24 02-Aug-24 17-Aug-24 38d 04-Jul-24, Apartment, Corridor & Wet Area
A4580 Fixing of Glossy Porcelein Tile 10d 19-Jun-24 29-Jun-24 02-Aug-24 13-Aug-24 38d Fixing of Glossy Porcelein Tile
A4590 Preparation of Niches in Bathrooms 4d 01-Jul-24 04-Jul-24 14-Aug-24 17-Aug-24 38d Preparation of Niches in Bathrooms
Service Area & Electrical Room 3d 01-Jul-24 03-Jul-24 19-Aug-24 21-Aug-24 42d 03-Jul-24, Service Area & Electrical Room
A4680 Fixing of Heavy Duty Ceramic Glossy Tile 3d 01-Jul-24 03-Jul-24 19-Aug-24 21-Aug-24 42d Fixing of Heavy Duty Ceramic Glossy Tile
Grouting of Tiles 4d 05-Jul-24 09-Jul-24 02-May-25 06-May-25 254d 09-Jul-24, Grouting of Tiles
A4750 Grouting of Tiles at Second Floor Walls 4d 05-Jul-24 09-Jul-24 02-May-25 06-May-25 254d Grouting of Tiles at Second Floor Walls
3rd Floor 18d 09-Jul-24 29-Jul-24 22-Aug-24 10-May-25 241d 29-Jul-24, 3rd Floor
Apartment, Corridor & Wet Area 14d 09-Jul-24 24-Jul-24 22-Aug-24 06-Sep-24 38d 24-Jul-24, Apartment, Corridor & Wet Area
A4600 Fixing of Glossy Porcelein Tile 10d 09-Jul-24 19-Jul-24 22-Aug-24 02-Sep-24 38d Fixing of Glossy Porcelein Tile
A4610 Preparation of Niches in Bathrooms 4d 20-Jul-24 24-Jul-24 03-Sep-24 06-Sep-24 38d Preparation of Niches in Bathrooms
Service Area & Electrical Room 3d 20-Jul-24 23-Jul-24 07-Sep-24 10-Sep-24 42d 23-Jul-24, Service Area & Electrical Room
A4690 Fixing of Heavy Duty Ceramic Glossy Tile 3d 20-Jul-24 23-Jul-24 07-Sep-24 10-Sep-24 42d Fixing of Heavy Duty Ceramic Glossy Tile
Grouting of Tiles 4d 25-Jul-24 29-Jul-24 07-May-25 10-May-25 241d 29-Jul-24, Grouting of Tiles
A4760 Grouting of Tiles at Third Floor Walls 4d 25-Jul-24 29-Jul-24 07-May-25 10-May-25 241d Grouting of Tiles at Third Floor Walls
4th Floor 18d 29-Jul-24 17-Aug-24 11-Sep-24 15-May-25 228d 17-Aug-24, 4th Floor
Apartment, Corridor & Wet Area 14d 29-Jul-24 13-Aug-24 11-Sep-24 26-Sep-24 38d 13-Aug-24, Apartment, Corridor & Wet Area
A4620 Fixing of Glossy Porcelein Tile 10d 29-Jul-24 08-Aug-24 11-Sep-24 21-Sep-24 38d Fixing of Glossy Porcelein Tile
A4630 Preparation of Niches in Bathrooms 4d 09-Aug-24 13-Aug-24 23-Sep-24 26-Sep-24 38d Preparation of Niches in Bathrooms
Service Area & Electrical Room 3d 09-Aug-24 12-Aug-24 27-Sep-24 30-Sep-24 42d 12-Aug-24, Service Area & Electrical Room
A4700 Fixing of Heavy Duty Ceramic Glossy Tile 3d 09-Aug-24 12-Aug-24 27-Sep-24 30-Sep-24 42d Fixing of Heavy Duty Ceramic Glossy Tile
Grouting of Tiles 4d 14-Aug-24 17-Aug-24 12-May-25 15-May-25 228d 17-Aug-24, Grouting of Tiles
A4770 Grouting of Tiles at Fourth Floor Walls 4d 14-Aug-24 17-Aug-24 12-May-25 15-May-25 228d Grouting of Tiles at Fourth Floor Walls
5th Floor 18d 17-Aug-24 06-Sep-24 01-Oct-24 20-May-25 215d 06-Sep-24, 5th Floor
Apartment, Corridor & Wet Area 14d 17-Aug-24 02-Sep-24 01-Oct-24 16-Oct-24 38d 02-Sep-24, Apartment, Corridor & Wet Area
A4640 Fixing of Glossy Porcelein Tile 10d 17-Aug-24 28-Aug-24 01-Oct-24 11-Oct-24 38d Fixing of Glossy Porcelein Tile
A4650 Preparation of Niches in Bathrooms 4d 29-Aug-24 02-Sep-24 12-Oct-24 16-Oct-24 38d Preparation of Niches in Bathrooms
Service Area & Electrical Room 3d 29-Aug-24 31-Aug-24 05-Nov-24 07-Nov-24 58d 31-Aug-24, Service Area & Electrical Room
A4710 Fixing of Heavy Duty Ceramic Glossy Tile 3d 29-Aug-24 31-Aug-24 05-Nov-24 07-Nov-24 58d Fixing of Heavy Duty Ceramic Glossy Tile
Grouting of Tiles 4d 03-Sep-24 06-Sep-24 16-May-25 20-May-25 215d 06-Sep-24, Grouting of Tiles
A4780 Grouting of Tiles at Fifth Floor Walls 4d 03-Sep-24 06-Sep-24 16-May-25 20-May-25 215d Grouting of Tiles at Fifth Floor Walls
6th Floor 18d 06-Sep-24 26-Sep-24 22-Nov-24 24-May-25 202d 26-Sep-24, 6th Floor
Apartment, Corridor & Wet Area 14d 06-Sep-24 21-Sep-24 22-Nov-24 11-Dec-24 66d 21-Sep-24, Apartment, Corridor & Wet Area
A4660 Fixing of Glossy Porcelein Tile 10d 06-Sep-24 17-Sep-24 22-Nov-24 06-Dec-24 66d Fixing of Glossy Porcelein Tile
A4670 Preparation of Niches in Bathrooms 4d 18-Sep-24 21-Sep-24 07-Dec-24 11-Dec-24 66d Preparation of Niches in Bathrooms
Service Area & Electrical Room 3d 18-Sep-24 20-Sep-24 07-Jan-25 09-Jan-25 91d 20-Sep-24, Service Area & Electrical Room
A4720 Fixing of Heavy Duty Ceramic Glossy Tile 3d 18-Sep-24 20-Sep-24 07-Jan-25 09-Jan-25 91d Fixing of Heavy Duty Ceramic Glossy Tile
Grouting of Tiles 4d 23-Sep-24 26-Sep-24 21-May-25 24-May-25 202d 26-Sep-24, Grouting of Tiles
A4790 Grouting of Tiles at Sixth Floor Walls 4d 23-Sep-24 26-Sep-24 21-May-25 24-May-25 202d Grouting of Tiles at Sixth Floor Walls
Floor Finishes Works 272d 16-May-24 03-Apr-25 16-May-24 24-May-25 45d 03-Apr-25, Floor Finishes Works
Basement Floor 5d 16-May-24 22-May-24 16-May-24 21-Jun-24 27d 22-May-24, Basement Floor

Actual Level of Effort Remaining Work Milestone Page 15 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Pump Room 4d 16-May-24 21-May-24 16-May-24 20-May-24 0d 21-May-24, Pump Room
A4230 Sand / Cement Screed 3d 16-May-24 20-May-24 16-May-24 18-May-24 0d Sand / Cement Screed
A4240 Fixing of Matt tiles Skirting with grouting 1d 20-May-24 21-May-24 20-May-24 20-May-24 0d Fixing of Matt tiles Skirting with grouting
Grouting 1d 21-May-24 22-May-24 21-Jun-24 21-Jun-24 27d 22-May-24, Grouting
A5530 Grouting at Basement Floor 1d 21-May-24 22-May-24 21-Jun-24 21-Jun-24 27d Grouting at Basement Floor
Ground Floor 258d 21-May-24 23-Mar-25 21-May-24 27-Mar-25 5d 23-Mar-25, Ground Floor
Entrance & Entrance Hall 7d 21-May-24 29-May-24 21-May-24 28-May-24 0d 29-May-24, Entrance & Entrance Hall
A4310 Fixing of Natural Marble Glossy finish on Floor 4d 21-May-24 25-May-24 21-May-24 24-May-24 0d Fixing of Natural Marble Glossy finish on Floor
A4320 Fixing of Natural Marble Heavy Duty Matte finish on 2d
Floor
25-May-24 28-May-24 25-May-24 27-May-24 0d Fixing of Natural Marble Heavy Duty Matte finish on Floor
A4330 Fixing of Rough Natural Granitre Skirting 1d 28-May-24 29-May-24 28-May-24 28-May-24 0d Fixing of Rough Natural Granitre Skirting
Shops 7d 29-May-24 06-Jun-24 29-May-24 05-Jun-24 0d 06-Jun-24, Shops
A4800 Fixing of Full Body Porcelein Glazed Tile 6d 29-May-24 05-Jun-24 29-May-24 04-Jun-24 0d Fixing of Full Body Porcelein Glazed Tile
A4810 Fixing of Porcelein Glazed Chamfer Skirting 1d 05-Jun-24 06-Jun-24 05-Jun-24 05-Jun-24 0d Fixing of Porcelein Glazed Chamfer Skirting
Parking Area 7d 15-Mar-25 23-Mar-25 21-Mar-25 27-Mar-25 5d 23-Mar-25, Parking Area
A4820 Application of Anti-Slip Heavy Duty Epoxy Coating 7d 15-Mar-25 23-Mar-25 21-Mar-25 27-Mar-25 5d Application of Anti-Slip Heavy Duty Epoxy C
Security Room and Public Washrooms 4d 06-Jun-24 11-Jun-24 06-Jun-24 10-Jun-24 0d 11-Jun-24, Security Room and Public Washrooms
A4830 Fixing of Ceramic Matt Tiles 3d 06-Jun-24 10-Jun-24 06-Jun-24 08-Jun-24 0d Fixing of Ceramic Matt Tiles
A4860 Fixing of Ceramic Matt Tiles Skirting at Security Room
1d 10-Jun-24 11-Jun-24 10-Jun-24 10-Jun-24 0d Fixing of Ceramic Matt Tiles Skirting at Security Room
Garbage Room, Combined MTR GSM Room & Water Meter Room 4d 11-Jun-24 15-Jun-24 11-Jun-24 14-Jun-24 0d 15-Jun-24, Garbage Room, Combined MTR GSM Room & Water Meter Room
A4840 Fixing of Heavy Duty Matt Tiles 4d 11-Jun-24 15-Jun-24 11-Jun-24 14-Jun-24 0d Fixing of Heavy Duty Matt Tiles
Substation & LV Room 7d 15-Jun-24 24-Jun-24 15-Jun-24 22-Jun-24 0d 24-Jun-24, Substation & LV Room
A4890 Application of Sand/Cement Screed 2d 15-Jun-24 18-Jun-24 15-Jun-24 17-Jun-24 0d Application of Sand/Cement Screed
A4850 Fixing of Ceramic at Matt Tiles 4d 18-Jun-24 22-Jun-24 18-Jun-24 21-Jun-24 0d Fixing of Ceramic at Matt Tiles
A4870 Fixing of Ceramic Matt Tiles Skirting 1d 22-Jun-24 24-Jun-24 22-Jun-24 22-Jun-24 0d Fixing of Ceramic Matt Tiles Skirting
Grouting 4d 24-Jun-24 28-Jun-24 24-Jun-24 27-Jun-24 0d 28-Jun-24, Grouting
A5540 Grouting at Ground Floor 4d 24-Jun-24 28-Jun-24 24-Jun-24 27-Jun-24 0d Grouting at Ground Floor
Podium Floor 239d 24-Jun-24 03-Apr-25 26-Jun-24 10-Apr-25 7d 03-Apr-25, Podium Floor
Parking Area 7d 26-Mar-25 03-Apr-25 03-Apr-25 10-Apr-25 7d 03-Apr-25, Parking Area
A4880 Application of Anti-Slip Heavy Duty Epoxy Coating 7d 26-Mar-25 03-Apr-25 03-Apr-25 10-Apr-25 7d Application of Anti-Slip Heavy Duty Epoxy
Generator & Swimming Pool Pump Room 4d 24-Jun-24 28-Jun-24 26-Jun-24 29-Jun-24 2d 28-Jun-24, Generator & Swimming Pool Pump Room
A4900 Application of Sand/Cement Screed 3d 24-Jun-24 27-Jun-24 26-Jun-24 28-Jun-24 2d Application of Sand/Cement Screed
A4910 Fixing of Ceramic Matt Tiles Skirting 1d 27-Jun-24 28-Jun-24 29-Jun-24 29-Jun-24 2d Fixing of Ceramic Matt Tiles Skirting
Grouting 1d 28-Jun-24 29-Jun-24 15-Aug-24 15-Aug-24 41d 29-Jun-24, Grouting
A5550 Grouting at Podium Floor 1d 28-Jun-24 29-Jun-24 15-Aug-24 15-Aug-24 41d Grouting at Podium Floor
1st Floor 170d 28-Jun-24 17-Jan-25 01-Jul-24 24-May-25 110d 17-Jan-25, 1st Floor
Apartment, Corridor & Wet Area 24d 28-Jun-24 26-Jul-24 01-Jul-24 27-Jul-24 2d 26-Jul-24, Apartment, Corridor & Wet Area
A4930 Fixing of Ceramic Matt Tiles 5d 28-Jun-24 04-Jul-24 01-Jul-24 05-Jul-24 2d Fixing of Ceramic Matt Tiles
A4920 Fixing of Porcelein Full Body glazed Tiles 12d 04-Jul-24 18-Jul-24 06-Jul-24 19-Jul-24 2d Fixing of Porcelein Full Body glazed Tiles
A4950 Fixing of Apartment Threshholds 2d 18-Jul-24 20-Jul-24 20-Jul-24 22-Jul-24 2d Fixing of Apartment Threshholds
A4960 Fixing of Bath Rooms Threshholds 2d 20-Jul-24 23-Jul-24 23-Jul-24 24-Jul-24 2d Fixing of Bath Rooms Threshholds
A4940 Fixing of Porcelein Glazed Chamfered Skirting 3d 23-Jul-24 26-Jul-24 25-Jul-24 27-Jul-24 2d Fixing of Porcelein Glazed Chamfered Skirting
Swimming Pool, Balcony & Open Terrace Works 146d 26-Jul-24 17-Jan-25 29-Jul-24 12-May-25 99d 17-Jan-25, Swimming Pool, Balcony & Open Terrace W
A4970 Fixing of Rough Granite Tiles 5d 26-Jul-24 01-Aug-24 29-Jul-24 02-Aug-24 2d Fixing of Rough Granite Tiles
A4990 Fixing of Ceramic Full Body Matt Tiles at OTS Area 1d 01-Aug-24 02-Aug-24 03-Aug-24 03-Aug-24 2d Fixing of Ceramic Full Body Matt Tiles at OTS Area
A5010 Skirting - Fixing of Rough Natural Granite Skirting 2d 02-Aug-24 05-Aug-24 05-Aug-24 06-Aug-24 2d Skirting - Fixing of Rough Natural Granite Skirting
A5000 Skirting - Fixing of Poercelein Matt Skirting 1d 05-Aug-24 06-Aug-24 07-Aug-24 07-Aug-24 2d Skirting - Fixing of Poercelein Matt Skirting
A4980 Fixing of Water Proof Artificial Wood with Embossed Grooves
6d 10-Jan-25
at Swimming
17-Jan-25
Pool Deck06-May-25 12-May-25 99d Fixing of Water Proof Artificial Wood with Embossed Gr
Service Area & Electrical Room 5d 06-Aug-24 12-Aug-24 08-Aug-24 13-Aug-24 2d 12-Aug-24, Service Area & Electrical Room
A5020 Fixing of Cermaic Full Body Matt Tiles 4d 06-Aug-24 10-Aug-24 08-Aug-24 12-Aug-24 2d Fixing of Cermaic Full Body Matt Tiles
A5030 Skirting - Cermaic Matt Tiles 1d 10-Aug-24 12-Aug-24 13-Aug-24 13-Aug-24 2d Skirting - Cermaic Matt Tiles
GYM, Steam & Sauna 79d 12-Aug-24 12-Nov-24 14-Aug-24 24-May-25 163d 12-Nov-24, GYM, Steam & Sauna
A5040 Application of Sand / Cement Screed at Gym, Steam1d& Sauna
12-Aug-24 13-Aug-24 14-Aug-24 14-Aug-24 2d Application of Sand / Cement Screed at Gym, Steam & Sauna

Actual Level of Effort Remaining Work Milestone Page 16 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A5060 Fixing of Ceramic Full Body Anti-Slip Tiles 3d 13-Aug-24 16-Aug-24 15-Aug-24 17-Aug-24 2d Fixing of Ceramic Full Body Anti-Slip Tiles
A5050 Fixing of Anti Slip Gym Flooring Mat 3d 06-Nov-24 09-Nov-24 20-May-25 22-May-25 163d Fixing of Anti Slip Gym Flooring Mat
A5070 Skirting - Polished Wooden Skirting in Gym 2d 09-Nov-24 12-Nov-24 23-May-25 24-May-25 163d Skirting - Polished Wooden Skirting in Gym
Grouting 10d 16-Aug-24 28-Aug-24 30-Aug-24 10-Sep-24 12d 28-Aug-24, Grouting
A5560 Grouting at 1st Floor 10d 16-Aug-24 28-Aug-24 30-Aug-24 10-Sep-24 12d Grouting at 1st Floor
2nd Floor 31d 16-Aug-24 21-Sep-24 19-Aug-24 10-Oct-24 17d 21-Sep-24, 2nd Floor
Apartment, Corridor & Wet Area 24d 16-Aug-24 13-Sep-24 19-Aug-24 02-Oct-24 17d 13-Sep-24, Apartment, Corridor & Wet Area
A5080 Fixing of Ceramic Matt Tiles 5d 16-Aug-24 22-Aug-24 19-Aug-24 23-Aug-24 2d Fixing of Ceramic Matt Tiles
A5090 Fixing of Porcelein Full Body glazed Tiles 12d 22-Aug-24 05-Sep-24 24-Aug-24 06-Sep-24 2d Fixing of Porcelein Full Body glazed Tiles
A5100 Fixing of Apartment Threshholds 2d 05-Sep-24 07-Sep-24 25-Sep-24 26-Sep-24 17d Fixing of Apartment Threshholds
A5110 Fixing of Bath Rooms Threshholds 2d 07-Sep-24 10-Sep-24 27-Sep-24 28-Sep-24 17d Fixing of Bath Rooms Threshholds
A5120 Fixing of Porcelein Glazed Chamfered Skirting 3d 10-Sep-24 13-Sep-24 30-Sep-24 02-Oct-24 17d Fixing of Porcelein Glazed Chamfered Skirting
Balcony 7d 22-Aug-24 30-Aug-24 24-Aug-24 31-Aug-24 2d 30-Aug-24, Balcony
A5150 Fixing of Rough Granite Tiles 5d 22-Aug-24 28-Aug-24 24-Aug-24 29-Aug-24 2d Fixing of Rough Granite Tiles
A5160 Skirting - Fixing of Rough Natural Granite Skirting 2d 28-Aug-24 30-Aug-24 30-Aug-24 31-Aug-24 2d Skirting - Fixing of Rough Natural Granite Skirting
Service Area & Electrical Room 5d 30-Aug-24 05-Sep-24 02-Sep-24 06-Sep-24 2d 05-Sep-24, Service Area & Electrical Room
A5130 Fixing of Cermaic Full Body Matt Tiles 4d 30-Aug-24 04-Sep-24 02-Sep-24 05-Sep-24 2d Fixing of Cermaic Full Body Matt Tiles
A5140 Skirting - Cermaic Matt Tiles 1d 04-Sep-24 05-Sep-24 06-Sep-24 06-Sep-24 2d Skirting - Cermaic Matt Tiles
Grouting 7d 13-Sep-24 21-Sep-24 03-Oct-24 10-Oct-24 17d 21-Sep-24, Grouting
A5570 Grouting at 2nd Floor 7d 13-Sep-24 21-Sep-24 03-Oct-24 10-Oct-24 17d Grouting at 2nd Floor
3rd Floor 31d 05-Sep-24 11-Oct-24 07-Sep-24 07-Nov-24 24d 11-Oct-24, 3rd Floor
Apartment, Corridor & Wet Area 24d 05-Sep-24 03-Oct-24 07-Sep-24 30-Oct-24 24d 03-Oct-24, Apartment, Corridor & Wet Area
A5180 Fixing of Ceramic Matt Tiles 5d 05-Sep-24 11-Sep-24 07-Sep-24 12-Sep-24 2d Fixing of Ceramic Matt Tiles
A5170 Fixing of Porcelein Full Body glazed Tiles 12d 11-Sep-24 25-Sep-24 13-Sep-24 26-Sep-24 2d Fixing of Porcelein Full Body glazed Tiles
A5200 Fixing of Apartment Threshholds 2d 25-Sep-24 27-Sep-24 23-Oct-24 24-Oct-24 24d Fixing of Apartment Threshholds
A5210 Fixing of Bath Rooms Threshholds 2d 27-Sep-24 30-Sep-24 25-Oct-24 26-Oct-24 24d Fixing of Bath Rooms Threshholds
A5190 Fixing of Porcelein Glazed Chamfered Skirting 3d 30-Sep-24 03-Oct-24 28-Oct-24 30-Oct-24 24d Fixing of Porcelein Glazed Chamfered Skirting
Balcony 7d 11-Sep-24 19-Sep-24 13-Sep-24 20-Sep-24 2d 19-Sep-24, Balcony
A5240 Fixing of Rough Granite Tiles 5d 11-Sep-24 17-Sep-24 13-Sep-24 18-Sep-24 2d Fixing of Rough Granite Tiles
A5250 Skirting - Fixing of Rough Natural Granite Skirting 2d 17-Sep-24 19-Sep-24 19-Sep-24 20-Sep-24 2d Skirting - Fixing of Rough Natural Granite Skirting
Service Area & Electrical Room 5d 19-Sep-24 25-Sep-24 21-Sep-24 26-Sep-24 2d 25-Sep-24, Service Area & Electrical Room
A5220 Fixing of Cermaic Full Body Matt Tiles 4d 19-Sep-24 24-Sep-24 21-Sep-24 25-Sep-24 2d Fixing of Cermaic Full Body Matt Tiles
A5230 Skirting - Cermaic Matt Tiles 1d 24-Sep-24 25-Sep-24 26-Sep-24 26-Sep-24 2d Skirting - Cermaic Matt Tiles
Grouting 7d 03-Oct-24 11-Oct-24 31-Oct-24 07-Nov-24 24d 11-Oct-24, Grouting
A5580 Grouting at 3rd Floor 7d 03-Oct-24 11-Oct-24 31-Oct-24 07-Nov-24 24d Grouting at 3rd Floor
4th Floor 31d 25-Sep-24 31-Oct-24 27-Sep-24 09-Dec-24 31d 31-Oct-24, 4th Floor
Apartment, Corridor & Wet Area 24d 25-Sep-24 23-Oct-24 27-Sep-24 27-Nov-24 31d 23-Oct-24, Apartment, Corridor & Wet Area
A5270 Fixing of Ceramic Matt Tiles 5d 25-Sep-24 01-Oct-24 27-Sep-24 02-Oct-24 2d Fixing of Ceramic Matt Tiles
A5260 Fixing of Porcelein Full Body glazed Tiles 12d 01-Oct-24 15-Oct-24 03-Oct-24 16-Oct-24 2d Fixing of Porcelein Full Body glazed Tiles
A5290 Fixing of Apartment Threshholds 2d 15-Oct-24 17-Oct-24 20-Nov-24 21-Nov-24 31d Fixing of Apartment Threshholds
A5300 Fixing of Bath Rooms Threshholds 2d 17-Oct-24 19-Oct-24 22-Nov-24 23-Nov-24 31d Fixing of Bath Rooms Threshholds
A5280 Fixing of Porcelein Glazed Chamfered Skirting 3d 19-Oct-24 23-Oct-24 25-Nov-24 27-Nov-24 31d Fixing of Porcelein Glazed Chamfered Skirting
Balcony 7d 01-Oct-24 09-Oct-24 03-Oct-24 10-Oct-24 2d 09-Oct-24, Balcony
A5330 Fixing of Rough Granite Tiles 5d 01-Oct-24 07-Oct-24 03-Oct-24 08-Oct-24 2d Fixing of Rough Granite Tiles
A5340 Skirting - Fixing of Rough Natural Granite Skirting 2d 07-Oct-24 09-Oct-24 09-Oct-24 10-Oct-24 2d Skirting - Fixing of Rough Natural Granite Skirting
Service Area & Electrical Room 5d 09-Oct-24 15-Oct-24 11-Oct-24 16-Oct-24 2d 15-Oct-24, Service Area & Electrical Room
A5310 Fixing of Cermaic Full Body Matt Tiles 4d 09-Oct-24 14-Oct-24 11-Oct-24 15-Oct-24 2d Fixing of Cermaic Full Body Matt Tiles
A5320 Skirting - Cermaic Matt Tiles 1d 14-Oct-24 15-Oct-24 16-Oct-24 16-Oct-24 2d Skirting - Cermaic Matt Tiles
Grouting 7d 23-Oct-24 31-Oct-24 28-Nov-24 09-Dec-24 31d 31-Oct-24, Grouting
A5590 Grouting at 4th Floor 7d 23-Oct-24 31-Oct-24 28-Nov-24 09-Dec-24 31d Grouting at 4th Floor
5th Floor 31d 15-Oct-24 20-Nov-24 17-Oct-24 21-Nov-24 2d 20-Nov-24, 5th Floor
Apartment, Corridor & Wet Area 24d 15-Oct-24 12-Nov-24 17-Oct-24 13-Nov-24 2d 12-Nov-24, Apartment, Corridor & Wet Area

Actual Level of Effort Remaining Work Milestone Page 17 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A5360 Fixing of Ceramic Matt Tiles 5d 15-Oct-24 21-Oct-24 17-Oct-24 22-Oct-24 2d Fixing of Ceramic Matt Tiles
A5350 Fixing of Porcelein Full Body glazed Tiles 12d 21-Oct-24 04-Nov-24 23-Oct-24 05-Nov-24 2d Fixing of Porcelein Full Body glazed Tiles
A5380 Fixing of Apartment Threshholds 2d 04-Nov-24 06-Nov-24 06-Nov-24 07-Nov-24 2d Fixing of Apartment Threshholds
A5390 Fixing of Bath Rooms Threshholds 2d 06-Nov-24 08-Nov-24 08-Nov-24 09-Nov-24 2d Fixing of Bath Rooms Threshholds
A5370 Fixing of Porcelein Glazed Chamfered Skirting 3d 08-Nov-24 12-Nov-24 11-Nov-24 13-Nov-24 2d Fixing of Porcelein Glazed Chamfered Skirting
Balcony 7d 21-Oct-24 29-Oct-24 31-Oct-24 07-Nov-24 9d 29-Oct-24, Balcony
A5420 Fixing of Rough Granite Tiles 5d 21-Oct-24 26-Oct-24 31-Oct-24 05-Nov-24 9d Fixing of Rough Granite Tiles
A5430 Skirting - Fixing of Rough Natural Granite Skirting 2d 26-Oct-24 29-Oct-24 06-Nov-24 07-Nov-24 9d Skirting - Fixing of Rough Natural Granite Skirting
Service Area & Electrical Room 5d 29-Oct-24 04-Nov-24 08-Nov-24 13-Nov-24 9d 04-Nov-24, Service Area & Electrical Room
A5400 Fixing of Cermaic Full Body Matt Tiles 4d 29-Oct-24 02-Nov-24 08-Nov-24 12-Nov-24 9d Fixing of Cermaic Full Body Matt Tiles
A5410 Skirting - Cermaic Matt Tiles 1d 02-Nov-24 04-Nov-24 13-Nov-24 13-Nov-24 9d Skirting - Cermaic Matt Tiles
Grouting 7d 12-Nov-24 20-Nov-24 14-Nov-24 21-Nov-24 2d 20-Nov-24, Grouting
A5600 Grouting at 5th Floor 7d 12-Nov-24 20-Nov-24 14-Nov-24 21-Nov-24 2d Grouting at 5th Floor
6th Floor 36d 04-Nov-24 19-Dec-24 12-Dec-24 23-Jan-25 30d 19-Dec-24, 6th Floor
Apartment, Corridor & Wet Area 24d 04-Nov-24 05-Dec-24 12-Dec-24 15-Jan-25 35d 05-Dec-24, Apartment, Corridor & Wet Area
A5450 Fixing of Ceramic Matt Tiles 5d 04-Nov-24 09-Nov-24 12-Dec-24 17-Dec-24 30d Fixing of Ceramic Matt Tiles
A5440 Fixing of Porcelein Full Body glazed Tiles 12d 09-Nov-24 23-Nov-24 18-Dec-24 31-Dec-24 30d Fixing of Porcelein Full Body glazed Tiles
A5470 Fixing of Apartment Threshholds 2d 23-Nov-24 26-Nov-24 08-Jan-25 09-Jan-25 35d Fixing of Apartment Threshholds
A5480 Fixing of Bath Rooms Threshholds 2d 26-Nov-24 28-Nov-24 10-Jan-25 11-Jan-25 35d Fixing of Bath Rooms Threshholds
A5460 Fixing of Porcelein Glazed Chamfered Skirting 3d 28-Nov-24 05-Dec-24 13-Jan-25 15-Jan-25 35d Fixing of Porcelein Glazed Chamfered Skirting
Balcony 7d 23-Nov-24 05-Dec-24 02-Jan-25 09-Jan-25 30d 05-Dec-24, Balcony
A5510 Fixing of Rough Granite Tiles 5d 23-Nov-24 29-Nov-24 02-Jan-25 07-Jan-25 30d Fixing of Rough Granite Tiles
A5520 Skirting - Fixing of Rough Natural Granite Skirting 2d 29-Nov-24 05-Dec-24 08-Jan-25 09-Jan-25 30d Skirting - Fixing of Rough Natural Granite Skirting
Service Area & Electrical Room 5d 05-Dec-24 11-Dec-24 10-Jan-25 15-Jan-25 30d 11-Dec-24, Service Area & Electric al Room
A5490 Fixing of Cermaic Full Body Matt Tiles 4d 05-Dec-24 10-Dec-24 10-Jan-25 14-Jan-25 30d Fixing of Cermaic Full Body Matt Tiles
A5500 Skirting - Cermaic Matt Tiles 1d 10-Dec-24 11-Dec-24 15-Jan-25 15-Jan-25 30d Skirting - Cermaic Matt Tiles
Grouting 7d 11-Dec-24 19-Dec-24 16-Jan-25 23-Jan-25 30d 19-Dec-24, Grouting
A5610 Grouting at 6th Floor 7d 11-Dec-24 19-Dec-24 16-Jan-25 23-Jan-25 30d Grouting at 6th Floor
Paint Works Works 305d 22-May-24 17-May-25 22-Jun-24 24-May-25 7d 17-May-25, Paint Works Works
Basement Floor 5d 22-May-24 28-May-24 22-Jun-24 27-Jun-24 27d 28-May-24, Basement Floor
Pump Room 5d 22-May-24 28-May-24 22-Jun-24 27-Jun-24 27d 28-May-24, Pump Room
A4250 Epoxy Paint on Fair Face Ceiling 2d 22-May-24 24-May-24 22-Jun-24 24-Jun-24 27d Epoxy Paint on Fair Face Ceiling
A4260 Epoxy Sysem Paint on Walls 3d 24-May-24 28-May-24 25-Jun-24 27-Jun-24 27d Epoxy Sysem Paint on Walls
Ground Floor 42d 28-Jun-24 16-Aug-24 28-Jun-24 15-Aug-24 0d 16-Aug-24, Ground Floor
Entrance & Entrance Hall 5d 28-Jun-24 04-Jul-24 28-Jun-24 03-Jul-24 0d 04-Jul-24, Entrance & Entrance Hall
A4280 Paint of Ceiling with Fenomastic Emulsion 2d 28-Jun-24 01-Jul-24 28-Jun-24 29-Jun-24 0d Paint of Ceiling with Fenomastic Emulsion
A4300 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n 3d
Paint01-Jul-24 04-Jul-24 01-Jul-24 03-Jul-24 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsio n Paint
Shops 9d 04-Jul-24 15-Jul-24 04-Jul-24 13-Jul-24 0d 15-Jul-24, Shops
A5620 Paint of Ceiling with Fenomastic Emulsion 3d 04-Jul-24 08-Jul-24 04-Jul-24 06-Jul-24 0d Paint of Ceiling with Fenomastic Emulsion
A5630 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n 6d
Paint08-Jul-24 15-Jul-24 08-Jul-24 13-Jul-24 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsio n Paint
Parking Area 16d 15-Jul-24 02-Aug-24 15-Jul-24 01-Aug-24 0d 02-Aug-24, Parking Area
A5640 Paint of Ceiling 8d 15-Jul-24 24-Jul-24 15-Jul-24 23-Jul-24 0d Paint of Ceiling
A5650 Anti Carbonate Paint with spray Plaster 8d 24-Jul-24 02-Aug-24 24-Jul-24 01-Aug-24 0d Anti Carbonate Paint with spray Plaster
Garbage Room, Combined MTR GSM Room & Water Meter Room 6d 02-Aug-24 09-Aug-24 02-Aug-24 08-Aug-24 0d 09-Aug-24, Garbage Room, Combined MTR GSM Room & Water Meter Room
A5660 Epoxy Paint on Fair Face Ceiling 2d 02-Aug-24 05-Aug-24 02-Aug-24 03-Aug-24 0d Epoxy Paint on Fair Face Ceiling
A5670 Epoxy Sysem Paint on Walls 4d 05-Aug-24 09-Aug-24 05-Aug-24 08-Aug-24 0d Epoxy Sysem Paint on Walls
Substation & LV Room 6d 09-Aug-24 16-Aug-24 09-Aug-24 15-Aug-24 0d 16-Aug-24, Substation & LV Room
A5680 Epoxy Paint on Fair Face Ceiling 2d 09-Aug-24 12-Aug-24 09-Aug-24 10-Aug-24 0d Epoxy Paint on Fair Face Ceiling
A5690 Epoxy Sysem Paint on Walls 4d 12-Aug-24 16-Aug-24 12-Aug-24 15-Aug-24 0d Epoxy Sysem Paint on Walls
Podium Floor 22d 16-Aug-24 11-Sep-24 16-Aug-24 10-Sep-24 0d 11-Sep-24, Podium Floor
Parking Area 16d 16-Aug-24 04-Sep-24 16-Aug-24 03-Sep-24 0d 04-Sep-24, Parking Area
A5700 Paint of Ceiling 8d 16-Aug-24 26-Aug-24 16-Aug-24 24-Aug-24 0d Paint of Ceiling

Actual Level of Effort Remaining Work Milestone Page 18 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A5710 Anti Carbonate Paint with spray Plaster 8d 26-Aug-24 04-Sep-24 26-Aug-24 03-Sep-24 0d Anti Carbonate Paint with spray Plaster
Generator & Swimming Pool Pump Room 6d 04-Sep-24 11-Sep-24 04-Sep-24 10-Sep-24 0d 11-Sep-24, Generator & Swimming Pool Pump Room
A5720 Epoxy Paint on Fair Face Ceiling 2d 04-Sep-24 06-Sep-24 04-Sep-24 05-Sep-24 0d Epoxy Paint on Fair Face Ceiling
A5730 Epoxy Sysem Paint on Walls 4d 06-Sep-24 11-Sep-24 06-Sep-24 10-Sep-24 0d Epoxy Sysem Paint on Walls
1st Floor 26d 11-Sep-24 11-Oct-24 11-Sep-24 10-Oct-24 0d 11-Oct-24, 1st Floor
Apartment, Corridor & Wet Area 18d 11-Sep-24 02-Oct-24 11-Sep-24 01-Oct-24 0d 02-Oct-24, Apartment, Corridor & Wet Area
A5740 Paint of Ceiling with Fenomastic Emulsion 8d 11-Sep-24 20-Sep-24 11-Sep-24 19-Sep-24 0d Paint of Ceiling with Fenomastic Emulsion
A5750 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n10d
Paint20-Sep-24 02-Oct-24 20-Sep-24 01-Oct-24 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsio n Paint
Service Area & Electrical Room 6d 02-Oct-24 09-Oct-24 02-Oct-24 08-Oct-24 0d 09-Oct-24, Service Area & Electrical Room
A5760 Epoxy Paint on Fair Face Ceiling 2d 02-Oct-24 04-Oct-24 02-Oct-24 03-Oct-24 0d Epoxy Paint on Fair Face Ceiling
A5770 Epoxy Sysem Paint on Walls 4d 04-Oct-24 09-Oct-24 04-Oct-24 08-Oct-24 0d Epoxy Sysem Paint on Walls
GYM, Steam & Sauna 2d 09-Oct-24 11-Oct-24 09-Oct-24 10-Oct-24 0d 11-Oct-24, GYM, Steam & Sauna
A5780 Paint of Ceiling with Fenomastic Emulsion 2d 09-Oct-24 11-Oct-24 09-Oct-24 10-Oct-24 0d Paint of Ceiling with Fenomastic Emulsion
2nd Floor 24d 11-Oct-24 08-Nov-24 11-Oct-24 07-Nov-24 0d 08-Nov-24, 2nd Floor
Apartment, Corridor & Wet Area 18d 11-Oct-24 01-Nov-24 11-Oct-24 31-Oct-24 0d 01-Nov-24, Apartment, Corridor & Wet Area
A5790 Paint of Ceiling with Fenomastic Emulsion 8d 11-Oct-24 21-Oct-24 11-Oct-24 19-Oct-24 0d Paint of Ceiling with Fenomastic Emulsion
A5800 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n10d
Paint21-Oct-24 01-Nov-24 21-Oct-24 31-Oct-24 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsion Paint
Service Area & Electrical Room 6d 01-Nov-24 08-Nov-24 01-Nov-24 07-Nov-24 0d 08-Nov-24, Service Area & Electrical Room
A5890 Epoxy Paint on Fair Face Ceiling 2d 01-Nov-24 04-Nov-24 01-Nov-24 02-Nov-24 0d Epoxy Paint on Fair Face Ceiling
A5900 Epoxy Sysem Paint on Walls 4d 04-Nov-24 08-Nov-24 04-Nov-24 07-Nov-24 0d Epoxy Sysem Paint on Walls
3rd Floor 24d 08-Nov-24 10-Dec-24 08-Nov-24 09-Dec-24 0d 10-Dec-24, 3rd Floor
Apartment, Corridor & Wet Area 18d 08-Nov-24 29-Nov-24 08-Nov-24 28-Nov-24 0d 29-Nov-24, Apartment, Corridor & Wet Area
A5810 Paint of Ceiling with Fenomastic Emulsion 8d 08-Nov-24 18-Nov-24 08-Nov-24 16-Nov-24 0d Paint of Ceiling with Fenomastic Emulsion
A5820 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n10d
Paint18-Nov-24 29-Nov-24 18-Nov-24 28-Nov-24 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsio n Paint
Service Area & Electrical Room 6d 29-Nov-24 10-Dec-24 29-Nov-24 09-Dec-24 0d 10-Dec-24, Service Area & Electrical Room
A5910 Epoxy Paint on Fair Face Ceiling 2d 29-Nov-24 05-Dec-24 29-Nov-24 04-Dec-24 0d Epoxy Paint on Fair Face Ceiling
A5920 Epoxy Sysem Paint on Walls 4d 05-Dec-24 10-Dec-24 05-Dec-24 09-Dec-24 0d Epoxy Sysem Paint on Walls
4th Floor 24d 10-Dec-24 08-Jan-25 10-Dec-24 07-Jan-25 0d 08-Jan-25, 4th Floor
Apartment, Corridor & Wet Area 18d 10-Dec-24 31-Dec-24 10-Dec-24 30-Dec-24 0d 31-Dec-24, Apartment, Corridor & Wet Area
A5830 Paint of Ceiling with Fenomastic Emulsion 8d 10-Dec-24 19-Dec-24 10-Dec-24 18-Dec-24 0d Paint of Ceiling with Fenomastic Emulsion
A5840 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n10d
Paint19-Dec-24 31-Dec-24 19-Dec-24 30-Dec-24 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsio n Paint
Service Area & Electrical Room 6d 31-Dec-24 08-Jan-25 31-Dec-24 07-Jan-25 0d 08-Jan-25, Service Area & Electrical Room
A5930 Epoxy Paint on Fair Face Ceiling 2d 31-Dec-24 03-Jan-25 31-Dec-24 02-Jan-25 0d Epoxy Paint on Fair Face Ceiling
A5940 Epoxy Sysem Paint on Walls 4d 03-Jan-25 08-Jan-25 03-Jan-25 07-Jan-25 0d Epoxy Sysem Paint on Walls
5th Floor 22d 08-Jan-25 03-Feb-25 08-Jan-25 01-Feb-25 0d 03-Feb-25, 5th Floor
Apartment, Corridor & Wet Area 16d 08-Jan-25 27-Jan-25 08-Jan-25 25-Jan-25 0d 27-Jan-25, Apartment, Corridor & Wet Area
A5850 Paint of Ceiling with Fenomastic Emulsion 6d 08-Jan-25 15-Jan-25 08-Jan-25 14-Jan-25 0d Paint of Ceiling with Fenomastic Emulsion
A5860 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n10d
Paint15-Jan-25 27-Jan-25 15-Jan-25 25-Jan-25 0d Paint of Walls wit h 2 Coats of Fenomastic Emulsio n P
Service Area & Electrical Room 6d 27-Jan-25 03-Feb-25 27-Jan-25 01-Feb-25 0d 03-Feb-25, Service Area & Electrical Room
A5950 Epoxy Paint on Fair Face Ceiling 2d 27-Jan-25 29-Jan-25 27-Jan-25 28-Jan-25 0d Epoxy Paint on Fair Face Ceiling
A5960 Epoxy Sysem Paint on Walls 4d 29-Jan-25 03-Feb-25 29-Jan-25 01-Feb-25 0d Epoxy Sysem Paint on Walls
6th Floor 26d 03-Feb-25 05-Mar-25 03-Feb-25 04-Mar-25 0d 05-Mar-25, 6th Floor
Apartment, Corridor & Wet Area 20d 03-Feb-25 26-Feb-25 03-Feb-25 25-Feb-25 0d 26-Feb-25, Apartment, Corridor & Wet Area
A5870 Paint of Ceiling with Fenomastic Emulsion 8d 03-Feb-25 12-Feb-25 03-Feb-25 11-Feb-25 0d Paint of Ceiling with Fenomastic Emulsion
A5880 Paint of Walls wit h 2 Coats of Fenomastic Emulsio n12d
Paint12-Feb-25 26-Feb-25 12-Feb-25 25-Feb-25 0d Paint of Walls with 2 Coats of Fenomastic Emul
Service Area & Electrical Room 6d 26-Feb-25 05-Mar-25 26-Feb-25 04-Mar-25 0d 05-Mar-25, Service Area & Electrical Room
A5970 Epoxy Paint on Fair Face Ceiling 2d 26-Feb-25 28-Feb-25 26-Feb-25 27-Feb-25 0d Epoxy Paint on Fair Face Ceiling
A5980 Epoxy Sysem Paint on Walls 4d 28-Feb-25 05-Mar-25 28-Feb-25 04-Mar-25 0d Epoxy Sysem Paint on Walls
External Paint 67d 28-Feb-25 17-May-25 28-Feb-25 24-May-25 7d 17-May-25, External Paint
A5990 One Coat of Acrylic Emulsion Primer 10d 28-Feb-25 13-Mar-25 28-Feb-25 12-Mar-25 0d One Coat of Acrylic Emulsion Primer
A6000 One Coat of Textocompound Texture 20d 13-Mar-25 04-Apr-25 13-Mar-25 03-Apr-25 0d One Coat of Textocompound Texture
A6010 First Coat of Jotoshield Color 20d 04-Apr-25 28-Apr-25 04-Apr-25 26-Apr-25 0d First Coat of Jotoshield Color
A6020 Final Coat of Jotoshield Color 20d 16-Apr-25 09-May-25 16-Apr-25 08-May-25 0d Final Coat of Jotoshield Color

Actual Level of Effort Remaining Work Milestone Page 19 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A6300 Desmantling of Scaffolding 7d 09-May-25 17-May-25 17-May-25 24-May-25 7d Desmantling of Scaffolding
Carpentary & Joinery Work 210d 16-Aug-24 23-Apr-25 01-Oct-24 01-May-25 8d 23-Apr-25, Carpentary & Joinery Work
Ground Floor 8d 16-Aug-24 26-Aug-24 01-Oct-24 09-Oct-24 39d 26-Aug-24, Ground Floor
A6040 Staircase Doors including ironmongery works 2d 16-Aug-24 19-Aug-24 01-Oct-24 02-Oct-24 39d Staircase Doors including ironmongery works
A6030 Service Rooms Doors including ironmongery works 3d 19-Aug-24 22-Aug-24 03-Oct-24 05-Oct-24 39d Service Rooms Doors including ironmongery works
A6050 Toilet Doors including ironmongery works 3d 22-Aug-24 26-Aug-24 07-Oct-24 09-Oct-24 39d Toilet Doors including ironmongery works
Podium Floor 4d 11-Sep-24 16-Sep-24 10-Oct-24 14-Oct-24 25d 16-Sep-24, Podium Floor
A6060 Service Rooms Doors including ironmongery works 2d 11-Sep-24 13-Sep-24 10-Oct-24 11-Oct-24 25d Service Rooms Doors including ironmongery works
A6070 Staircase Doors including ironmongery works 2d 13-Sep-24 16-Sep-24 12-Oct-24 14-Oct-24 25d Staircase Doors including ironmongery works
1st Floor 28d 11-Oct-24 13-Nov-24 15-Oct-24 15-Nov-24 3d 13-Nov-24, 1st Floor
A6120 Bed Room Doors including ironmongery works 6d 11-Oct-24 18-Oct-24 15-Oct-24 21-Oct-24 3d Bed Room Doors including ironmongery works
A6100 Toilet Doors including ironmongery works 10d 18-Oct-24 30-Oct-24 22-Oct-24 01-Nov-24 3d Toilet Doors including ironmongery works
A6080 Service Rooms Doors including ironmongery works 2d 30-Oct-24 01-Nov-24 02-Nov-24 04-Nov-24 3d Service Rooms Doors including ironmongery works
A6090 Staircase Doors including ironmongery works 2d 01-Nov-24 04-Nov-24 05-Nov-24 06-Nov-24 3d Staircase Doors including ironmongery works
A6130 Gym Door including ironmongery works 2d 04-Nov-24 06-Nov-24 07-Nov-24 08-Nov-24 3d Gym Door including ironmongery works
A6110 Main Doors including ironmongery works 6d 06-Nov-24 13-Nov-24 09-Nov-24 15-Nov-24 3d Main Doors including ironmongery works
2nd Floor 29d 13-Nov-24 20-Dec-24 16-Nov-24 23-Dec-24 3d 20-Dec-24, 2nd Floor
A6140 Bed Room Doors including ironmongery works 6d 13-Nov-24 20-Nov-24 16-Nov-24 22-Nov-24 3d Bed Room Doors including ironmongery works
A6150 Toilet Doors including ironmongery works 10d 20-Nov-24 05-Dec-24 23-Nov-24 07-Dec-24 3d Toilet Doors including ironmongery works
A6160 Service Rooms Doors including ironmongery works 2d 05-Dec-24 07-Dec-24 09-Dec-24 10-Dec-24 3d Service Rooms Doors including ironmongery works
A6170 Staircase Doors including ironmongery works 2d 07-Dec-24 10-Dec-24 11-Dec-24 12-Dec-24 3d Staircase Doors including ironmongery works
A6180 Laundry Doors including ironmongery works 3d 10-Dec-24 13-Dec-24 13-Dec-24 16-Dec-24 3d Laundry Doors including ironmongery works
A6190 Main Doors including ironmongery works 6d 13-Dec-24 20-Dec-24 17-Dec-24 23-Dec-24 3d Main Doors including ironmongery works
3rd Floor 26d 20-Dec-24 21-Jan-25 24-Dec-24 23-Jan-25 3d 21-Jan-25, 3rd Floor
A6260 Bed Room Doors including ironmongery works 6d 20-Dec-24 27-Dec-24 24-Dec-24 30-Dec-24 3d Bed Room Doors including ironmongery works
A6270 Toilet Doors including ironmongery works 10d 27-Dec-24 09-Jan-25 31-Dec-24 11-Jan-25 3d Toilet Doors including ironmongery works
A6280 Service Rooms Doors including ironmongery works 2d 09-Jan-25 11-Jan-25 13-Jan-25 14-Jan-25 3d Service Rooms Doors including ironmongery works
A6290 Staircase Doors including ironmongery works 2d 11-Jan-25 14-Jan-25 15-Jan-25 16-Jan-25 3d Staircase Doors including ironmongery works
A6310 Main Doors including ironmongery works 6d 14-Jan-25 21-Jan-25 17-Jan-25 23-Jan-25 3d Main Doors including ironmongery works
4th Floor 27d 21-Jan-25 21-Feb-25 24-Jan-25 01-Mar-25 8d 21-Feb-25, 4th Floor
A6200 Bed Room Doors including ironmongery works 6d 21-Jan-25 28-Jan-25 24-Jan-25 30-Jan-25 3d Bed Room Doors including ironmongery works
A6210 Toilet Doors including ironmongery works 8d 28-Jan-25 06-Feb-25 31-Jan-25 08-Feb-25 3d Toilet Doors including ironmongery works
A6220 Service Rooms Doors including ironmongery works 2d 06-Feb-25 08-Feb-25 15-Feb-25 17-Feb-25 8d Service Rooms Doors including ironmongery works
A6230 Staircase Doors including ironmongery works 2d 08-Feb-25 11-Feb-25 18-Feb-25 19-Feb-25 8d Staircase Doors including ironmongery works
A6240 Laundry Doors including ironmongery works 3d 11-Feb-25 14-Feb-25 20-Feb-25 22-Feb-25 8d Laundry Doors including ironmongery works
A6250 Main Doors including ironmongery works 6d 14-Feb-25 21-Feb-25 24-Feb-25 01-Mar-25 8d Main Doors including ironmongery works
5th Floor 26d 21-Feb-25 24-Mar-25 03-Mar-25 01-Apr-25 8d 24-Mar-25, 5th Floor
A6320 Bed Room Doors including ironmongery works 6d 21-Feb-25 28-Feb-25 03-Mar-25 10-Mar-25 8d Bed Room Doors including ironmongery works
A6330 Toilet Doors including ironmongery works 10d 28-Feb-25 13-Mar-25 11-Mar-25 21-Mar-25 8d Toilet Doors including ironmongery works
A6340 Service Rooms Doors including ironmongery works 2d 13-Mar-25 15-Mar-25 22-Mar-25 23-Mar-25 8d Service Rooms Doors including ironmongery
A6350 Staircase Doors including ironmongery works 2d 15-Mar-25 18-Mar-25 24-Mar-25 25-Mar-25 8d Staircase Doors including ironmongery work
A6360 Main Doors including ironmongery works 6d 18-Mar-25 24-Mar-25 26-Mar-25 01-Apr-25 8d Main Doors including ironmongery works
6th Floor 26d 24-Mar-25 23-Apr-25 02-Apr-25 01-May-25 8d 23-Apr-25, 6th Floor
A6370 Bed Room Doors including ironmongery works 6d 24-Mar-25 31-Mar-25 02-Apr-25 08-Apr-25 8d Bed Room Doors including ironmongery w
A6380 Toilet Doors including ironmongery works 10d 31-Mar-25 11-Apr-25 09-Apr-25 19-Apr-25 8d Toilet Doors including ironmongery work
A6390 Service Rooms Doors including ironmongery works 2d 11-Apr-25 14-Apr-25 21-Apr-25 22-Apr-25 8d Service Rooms Doors including ironmo
A6400 Staircase Doors including ironmongery works 2d 14-Apr-25 16-Apr-25 23-Apr-25 24-Apr-25 8d Staircase Doors including ironmongery
A6410 Main Doors including ironmongery works 6d 16-Apr-25 23-Apr-25 25-Apr-25 01-May-25 8d Main Doors including ironmongery wo
Lift Pit 13d 22-May-24 06-Jun-24 17-Sep-24 01-Oct-24 101d 06-Jun-24, Lift Pit
A6730 2 Coats of Bitumen for Thermal Protection 3d 22-May-24 25-May-24 17-Sep-24 19-Sep-24 101d 2 Coats of Bitumen for Thermal Protection
A6750 Installation of Lift Machine Room Cat Ladder 3d 25-May-24 29-May-24 20-Sep-24 23-Sep-24 101d Installation of Lift Machine Room Cat Ladder

Actual Level of Effort Remaining Work Milestone Page 20 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A6740 Installation of Steel Ladder in Lift Pit 7d 29-May-24 06-Jun-24 24-Sep-24 01-Oct-24 101d Installation of Steel Ladder in Lift Pit
Stair Case 22d 19-Dec-24 15-Jan-25 30-Apr-25 24-May-25 112d 15-Jan-25, Stair Case
A6760 Fixing of Natural Granite with anti-slip grooves 14d 19-Dec-24 06-Jan-25 30-Apr-25 15-May-25 112d Fixing of Natural Granite with anti-slip grooves
A6770 Natural Granite Skirting 4d 06-Jan-25 10-Jan-25 16-May-25 20-May-25 112d Natural Granite Skirting
A6780 Fenomestic Emulsion Paint 4d 10-Jan-25 15-Jan-25 21-May-25 24-May-25 112d Fenomestic Emulsion Paint
Garbage Chute 19d 19-Dec-24 11-Jan-25 24-Jan-25 14-Feb-25 30d 11-Jan-25, Garbage Chute
A6800 Fixing and Grout of Ceramic Glossy Tile 10d 19-Dec-24 31-Dec-24 24-Jan-25 04-Feb-25 30d Fixing and Grout of Ceramic Glossy Tile
A6790 Fixing and Grout of Ceramic Anti Slip Matt Tile 5d 31-Dec-24 07-Jan-25 05-Feb-25 10-Feb-25 30d Fixing and Grout of Ceramic Anti Slip Matt Tile
A6810 Epoxy Paint on Fair-Face 4d 07-Jan-25 11-Jan-25 11-Feb-25 14-Feb-25 30d Epoxy Paint on Fair-Face
MEP 3rd Fix 86d 06-Feb-25 17-May-25 10-Feb-25 24-May-25 7d 17-May-25, MEP 3rd Fix
Basement Floor 3d 06-Feb-25 10-Feb-25 10-Feb-25 12-Feb-25 3d 10-Feb-25, Basement Floor
A6820 Installation of Pump 3d 06-Feb-25 10-Feb-25 10-Feb-25 12-Feb-25 3d Installation of Pump
Ground Floor 57d 08-Feb-25 16-Apr-25 12-Feb-25 03-May-25 16d 16-Apr-25, Ground Floor
A6860 Water Supply Accessories 6d 08-Feb-25 15-Feb-25 12-Feb-25 18-Feb-25 3d Water Supply Accessories
A6850 Drainage Parts 3d 15-Feb-25 19-Feb-25 21-Feb-25 24-Feb-25 5d Drainage Parts
A6880 Fire Fighting Nozzles, Sensors etc fixing 5d 19-Feb-25 25-Feb-25 25-Feb-25 01-Mar-25 5d Fire Fighting Nozzles, Sensors etc fixing
A6870 Electrical Fixtures 8d 25-Feb-25 06-Mar-25 03-Mar-25 12-Mar-25 5d Electrical Fixtures
A6840 Ventilation & Smoke Management Fixtures 5d 06-Mar-25 13-Mar-25 20-Mar-25 24-Mar-25 11d Ventilation & Smoke Management Fixtures
A6910 Access Control System Components 7d 13-Mar-25 21-Mar-25 25-Mar-25 01-Apr-25 11d Access Control System Components
A6930 Gate Barrier System 10d 21-Mar-25 01-Apr-25 02-Apr-25 12-Apr-25 11d Gate Barrier System
A6900 CCTV System Cameras, etc. 5d 01-Apr-25 07-Apr-25 14-Apr-25 18-Apr-25 11d CCTV System Cameras, etc.
A6890 Telephone System accessories 4d 07-Apr-25 11-Apr-25 25-Apr-25 29-Apr-25 16d Telephone System accessories
A6830 Air Conditioner (AC) 4d 11-Apr-25 16-Apr-25 30-Apr-25 03-May-25 16d Air Conditioner (AC)
Podium Floor 48d 15-Feb-25 12-Apr-25 19-Feb-25 24-Apr-25 11d 12-Apr-25, Podium Floor
A6940 Water Supply Accessories 6d 15-Feb-25 22-Feb-25 19-Feb-25 25-Feb-25 3d Water Supply Accessories
A6950 Drainage Parts 3d 22-Feb-25 26-Feb-25 03-Mar-25 05-Mar-25 7d Drainage Parts
A6960 Fire Fighting Nozzles, Sensors etc fixing 5d 26-Feb-25 04-Mar-25 10-Mar-25 14-Mar-25 9d Fire Fighting Nozzles, Sensors etc fixing
A6970 Electrical Fixtures 10d 06-Mar-25 19-Mar-25 15-Mar-25 25-Mar-25 7d Electrical Fixtures
A6980 Ventilation & Smoke Management Fixtures 5d 19-Mar-25 24-Mar-25 28-Mar-25 02-Apr-25 9d Ventilation & Smoke Management Fixtures
A7010 CCTV System Cameras, etc. 5d 07-Apr-25 12-Apr-25 19-Apr-25 24-Apr-25 11d CCTV System Cameras, etc.
1st Floor 53d 22-Feb-25 25-Apr-25 26-Feb-25 07-May-25 11d 25-Apr-25, 1st Floor
A7020 Water Supply Accessories 7d 22-Feb-25 03-Mar-25 26-Feb-25 05-Mar-25 3d Water Supply Accessories
A7030 Drainage Parts 7d 03-Mar-25 12-Mar-25 06-Mar-25 14-Mar-25 3d Drainage Parts
A7040 Fire Fighting Nozzles, Sensors etc fixing 5d 12-Mar-25 18-Mar-25 21-Mar-25 25-Mar-25 8d Fire Fighting Nozzles, Sensors etc fixing
A7050 Electrical Fixtures 7d 19-Mar-25 26-Mar-25 26-Mar-25 02-Apr-25 7d Electrical Fixtures
A7060 Ventilation & Smoke Management Fixtures 5d 26-Mar-25 01-Apr-25 03-Apr-25 08-Apr-25 7d Ventilation & Smoke Management Fixture
A7070 Access Control System Components 3d 01-Apr-25 04-Apr-25 18-Apr-25 21-Apr-25 15d Access Control System Components
A7080 Audio Intercom System Accessories 3d 04-Apr-25 08-Apr-25 22-Apr-25 24-Apr-25 15d Audio Intercom System Accessories
A7090 CCTV System Cameras, etc. 5d 12-Apr-25 18-Apr-25 25-Apr-25 30-Apr-25 11d CCTV System Cameras, etc.
A7100 Telephone System accessories 3d 18-Apr-25 22-Apr-25 01-May-25 03-May-25 11d Telephone System accessories
A7110 Air Conditioner (AC) 3d 22-Apr-25 25-Apr-25 05-May-25 07-May-25 11d Air Conditioner (AC)
2nd Floor 49d 03-Mar-25 29-Apr-25 14-Mar-25 10-May-25 11d 29-Apr-25, 2nd Floor
A7120 Water Supply Accessories 5d 03-Mar-25 10-Mar-25 14-Mar-25 19-Mar-25 9d Water Supply Accessories
A7130 Drainage Parts 5d 12-Mar-25 18-Mar-25 20-Mar-25 24-Mar-25 7d Drainage Parts
A7140 Fire Fighting Nozzles, Sensors etc fixing 5d 18-Mar-25 23-Mar-25 27-Mar-25 01-Apr-25 9d Fire Fighting Nozzles, Sensors etc fixing
A7150 Electrical Fixtures 5d 26-Mar-25 01-Apr-25 03-Apr-25 08-Apr-25 7d Electrical Fixtures
A7160 Ventilation & Smoke Management Fixtures 5d 01-Apr-25 07-Apr-25 09-Apr-25 14-Apr-25 7d Ventilation & Smoke Management Fixtur
A7170 Access Control System Components 3d 07-Apr-25 10-Apr-25 24-Apr-25 26-Apr-25 15d Access Control System Components
A7180 Audio Intercom System Accessories 3d 10-Apr-25 14-Apr-25 28-Apr-25 30-Apr-25 15d Audio Intercom System Accessories
A7190 CCTV System Cameras, etc. 3d 18-Apr-25 22-Apr-25 01-May-25 03-May-25 11d CCTV System Cameras, etc.
A7200 Telephone System accessories 3d 22-Apr-25 25-Apr-25 05-May-25 07-May-25 11d Telephone System accessories

Actual Level of Effort Remaining Work Milestone Page 21 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A7210 Air Conditioner (AC) 3d 25-Apr-25 29-Apr-25 08-May-25 10-May-25 11d Air Conditioner (AC)
3rd Floor 47d 10-Mar-25 02-May-25 21-Mar-25 14-May-25 11d 02-May-25, 3rd Floor
A7220 Water Supply Accessories 5d 10-Mar-25 15-Mar-25 21-Mar-25 25-Mar-25 10d Water Supply Accessories
A7230 Drainage Parts 5d 18-Mar-25 23-Mar-25 26-Mar-25 31-Mar-25 8d Drainage Parts
A7240 Fire Fighting Nozzles, Sensors etc fixing 5d 23-Mar-25 28-Mar-25 02-Apr-25 07-Apr-25 9d Fire Fighting Nozzles, Sensors etc fixing
A7250 Electrical Fixtures 5d 01-Apr-25 07-Apr-25 09-Apr-25 14-Apr-25 7d Electrical Fixtures
A7260 Ventilation & Smoke Management Fixtures 5d 07-Apr-25 12-Apr-25 15-Apr-25 19-Apr-25 7d Ventilation & Smoke Management Fixtu
A7270 Access Control System Components 3d 12-Apr-25 16-Apr-25 28-Apr-25 30-Apr-25 13d Access Control System Components
A7280 Audio Intercom System Accessories 3d 16-Apr-25 19-Apr-25 01-May-25 03-May-25 13d Audio Intercom System Accessories
A7290 CCTV System Cameras, etc. 3d 22-Apr-25 25-Apr-25 05-May-25 07-May-25 11d CCTV System Cameras, etc.
A7300 Telephone System accessories 3d 25-Apr-25 29-Apr-25 08-May-25 10-May-25 11d Telephone System accessories
A7310 Air Conditioner (AC) 3d 29-Apr-25 02-May-25 12-May-25 14-May-25 11d Air Conditioner (AC)
4th Floor 45d 15-Mar-25 06-May-25 26-Mar-25 17-May-25 11d 06-May-25, 4th Floor
A7320 Water Supply Accessories 5d 15-Mar-25 21-Mar-25 26-Mar-25 31-Mar-25 10d Water Supply Accessories
A7330 Drainage Parts 5d 23-Mar-25 28-Mar-25 01-Apr-25 05-Apr-25 8d Drainage Parts
A7340 Fire Fighting Nozzles, Sensors etc fixing 5d 28-Mar-25 03-Apr-25 08-Apr-25 12-Apr-25 9d Fire Fighting Nozzles, Sensors etc fixing
A7350 Electrical Fixtures 5d 07-Apr-25 12-Apr-25 15-Apr-25 19-Apr-25 7d Electrical Fixtures
A7360 Ventilation & Smoke Management Fixtures 5d 12-Apr-25 18-Apr-25 21-Apr-25 25-Apr-25 7d Ventilation & Smoke Management Fixt
A7370 Access Control System Components 3d 18-Apr-25 22-Apr-25 01-May-25 03-May-25 11d Access Control System Components
A7380 Audio Intercom System Accessories 3d 22-Apr-25 25-Apr-25 05-May-25 07-May-25 11d Audio Intercom System Accessories
A7390 CCTV System Cameras, etc. 3d 25-Apr-25 29-Apr-25 08-May-25 10-May-25 11d CCTV System Cameras, etc.
A7400 Telephone System accessories 3d 29-Apr-25 02-May-25 12-May-25 14-May-25 11d Telephone System accessories
A7410 Air Conditioner (AC) 3d 02-May-25 06-May-25 15-May-25 17-May-25 11d Air Conditioner (AC)
5th Floor 45d 21-Mar-25 12-May-25 01-Apr-25 21-May-25 9d 12-May-25, 5th Floor
A7420 Water Supply Accessories 5d 21-Mar-25 26-Mar-25 01-Apr-25 05-Apr-25 10d Water Supply Accessories
A7430 Drainage Parts 5d 28-Mar-25 03-Apr-25 07-Apr-25 11-Apr-25 8d Drainage Parts
A7440 Fire Fighting Nozzles, Sensors etc fixing 5d 03-Apr-25 09-Apr-25 14-Apr-25 18-Apr-25 9d Fire Fighting Nozzles, Sensors etc fixing
A7450 Electrical Fixtures 5d 09-Apr-25 15-Apr-25 21-Apr-25 25-Apr-25 10d Electrical Fixtures
A7460 Ventilation & Smoke Management Fixtures 5d 18-Apr-25 24-Apr-25 26-Apr-25 01-May-25 7d Ventilation & Smoke Management Fix
A7470 Access Control System Components 3d 24-Apr-25 28-Apr-25 05-May-25 07-May-25 9d Access Control System Components
A7480 Audio Intercom System Accessories 3d 28-Apr-25 01-May-25 08-May-25 10-May-25 9d Audio Intercom System Accessories
A7490 CCTV System Cameras, etc. 3d 01-May-25 05-May-25 12-May-25 14-May-25 9d CCTV System Cameras, etc.
A7500 Telephone System accessories 3d 05-May-25 08-May-25 15-May-25 17-May-25 9d Telephone System accessories
A7510 Air Conditioner (AC) 3d 08-May-25 12-May-25 19-May-25 21-May-25 9d Air Conditioner (AC)
6th Floor 45d 26-Mar-25 17-May-25 07-Apr-25 24-May-25 7d 17-May-25, 6th Floor
A7520 Water Supply Accessories 5d 26-Mar-25 01-Apr-25 07-Apr-25 11-Apr-25 10d Water Supply Accessories
A7530 Drainage Parts 5d 03-Apr-25 09-Apr-25 12-Apr-25 17-Apr-25 8d Drainage Parts
A7540 Fire Fighting Nozzles, Sensors etc fixing 5d 09-Apr-25 15-Apr-25 19-Apr-25 24-Apr-25 9d Fire Fighting Nozzles, Sensors etc fixin
A7550 Electrical Fixtures 5d 15-Apr-25 21-Apr-25 26-Apr-25 01-May-25 10d Electrical Fixtures
A7560 Ventilation & Smoke Management Fixtures 5d 24-Apr-25 30-Apr-25 02-May-25 07-May-25 7d Ventilation & Smoke Management F
A7570 Access Control System Components 3d 30-Apr-25 03-May-25 08-May-25 10-May-25 7d Access Control System Componen
A7580 Audio Intercom System Accessories 3d 03-May-25 07-May-25 12-May-25 14-May-25 7d Audio Intercom System Accessorie
A7590 CCTV System Cameras, etc. 3d 07-May-25 10-May-25 15-May-25 17-May-25 7d CCTV System Cameras, etc.
A7600 Telephone System accessories 3d 10-May-25 14-May-25 19-May-25 21-May-25 7d Telephone System accessories
A7610 Air Conditioner (AC) 3d 14-May-25 17-May-25 22-May-25 24-May-25 7d Air Conditioner (AC)
Provisional Sum Items 394d 13-Feb-24 23-May-25 08-Aug-24 24-May-25 2d 23-May-25, Provisional Sum Item
Light Fixtures 59d 06-Mar-25 14-May-25 13-Mar-25 21-May-25 7d 14-May-25, Light Fixtures
A7700 Installation of Light Fixtures at Ground Floor 7d 06-Mar-25 15-Mar-25 13-Mar-25 20-Mar-25 5d Installation of Light Fixtures at Ground Floor
A7710 Installation of Light Fixtures at Podium Floor 7d 19-Mar-25 26-Mar-25 26-Mar-25 02-Apr-25 7d Installation of Light Fixtures at Podium Floo
A7720 Installation of Light Fixtures at 1st Floor 7d 26-Mar-25 03-Apr-25 03-Apr-25 10-Apr-25 7d Installation of Light Fixtures at 1st Floor
A7730 Installation of Light Fixtures at 2nd Floor 7d 03-Apr-25 11-Apr-25 11-Apr-25 18-Apr-25 7d Installation of Light Fixtures at 2nd Floo

Actual Level of Effort Remaining Work Milestone Page 22 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A7740 Installation of Light Fixtures at 3rd Floor 7d 11-Apr-25 19-Apr-25 19-Apr-25 26-Apr-25 7d Installation of Light Fixtures at 3rd Floo
A7750 Installation of Light Fixtures at 4th Floor 7d 19-Apr-25 28-Apr-25 28-Apr-25 05-May-25 7d Installation of Light Fixtures at 4th Fl
A7760 Installation of Light Fixtures at 5th Floor 7d 28-Apr-25 06-May-25 06-May-25 13-May-25 7d Installation of Light Fixtures at 5th F
A7770 Installation of Light Fixtures at 6th Floor 7d 06-May-25 14-May-25 14-May-25 21-May-25 7d Installation of Light Fixtures at 6th
Kitchen Cabinets & Wardrobes 128d 16-Dec-24 16-May-25 06-Jan-25 24-May-25 8d 16-May-25, Kitchen Cabinets & W
A8000 Fixing of Kitchen Cabinets & Wardrobes at 1st Floor20d 16-Dec-24 09-Jan-25 06-Jan-25 28-Jan-25 16d Fixing of Kitchen Cabinets & Wardrobes at 1st Floor
A8010 Fixing of Kitchen Cabinets & Wardrobes at 2nd Floor
20d 09-Jan-25 01-Feb-25 29-Jan-25 20-Feb-25 16d Fixing of Kitchen Cabinets & Wardrobes at 2nd Floo
A8020 Fixing of Kitchen Cabinets & Wardrobes at 3rd Floor
20d 01-Feb-25 25-Feb-25 21-Feb-25 17-Mar-25 16d Fixing of Kitchen Cabinets & Wardrobes at 3rd F
A8030 Fixing of Kitchen Cabinets & Wardrobes at 4th Floor
20d 25-Feb-25 21-Mar-25 18-Mar-25 08-Apr-25 16d Fixing of Kitchen Cabinets & Wardrobes at
A8040 Fixing of Kitchen Cabinets & Wardrobes at 5th Floor
20d 24-Mar-25 16-Apr-25 09-Apr-25 01-May-25 14d Fixing of Kitchen Cabinets & Wardrobe
A8050 Fixing of Kitchen Cabinets & Wardrobes at 6th Floor
20d 23-Apr-25 16-May-25 02-May-25 24-May-25 8d Fixing of Kitchen Cabinets & Ward
Mirrors, Sanitary Ware, Mixer & Accessories 64d 19-Feb-25 05-May-25 10-Mar-25 24-May-25 18d 05-May-25, Mirrors, Sanitary Ware,
A7780 Fixing of Sanitary Ware Mixtures & Accessories at Ground
5d 19-Feb-25
Floor 25-Feb-25 10-Mar-25 14-Mar-25 15d Fixing of Sanitary Ware Mixtures & Accessories
A7790 Fixing of Sanitary Ware Mixtures & Accessories at 1st9d
Floor
12-Mar-25 22-Mar-25 15-Mar-25 24-Mar-25 3d Fixing of Sanitary Ware Mixtures & Accesso
A7800 Fixing of Sanitary Ware Mixtures & Accessories at 2nd
7dFloor
22-Mar-25 29-Mar-25 25-Mar-25 01-Apr-25 3d Fixing of Sanitary Ware Mixtures & Access
A7810 Fixing of Sanitary Ware Mixtures & Accessories at 3rd7dFloor
29-Mar-25 07-Apr-25 02-Apr-25 09-Apr-25 3d Fixing of Sanitary Ware Mixtures & Acces
A7820 Fixing of Sanitary Ware Mixtures & Accessories at 4th7dFloor
07-Apr-25 15-Apr-25 10-Apr-25 17-Apr-25 3d Fixing of Sanitary Ware Mixtures & Acc
A7830 Fixing of Sanitary Ware Mixtures & Accessories at 5th7dFloor
15-Apr-25 23-Apr-25 18-Apr-25 25-Apr-25 3d Fixing of Sanitary Ware Mixtures & Ac
A7840 Fixing of Sanitary Ware Mixtures & Accessories at 6th7dFloor
15-Apr-25 23-Apr-25 18-Apr-25 25-Apr-25 3d Fixing of Sanitary Ware Mixtures & Ac
A7920 Fixing of Mirrors throughout Building 10d 23-Apr-25 05-May-25 14-May-25 24-May-25 18d Fixing of Mirrors throughout Building
Plunge Pools 394d 13-Feb-24 23-May-25 08-Aug-24 24-May-25 2d 23-May-25, Plunge Pools
1st Floor 106d 14-Aug-24 19-Dec-24 16-Sep-24 25-Feb-25 58d 19-Dec-24, 1st Floor
M&F-FF-1180 Concrete works 8d 14-Aug-24 23-Aug-24 16-Sep-24 24-Sep-24 28d Concrete works
M&F-FF-1190 MEP 1st Fix 8d 23-Aug-24 02-Sep-24 25-Sep-24 03-Oct-24 28d MEP 1st Fix
M&F-FF-1200 Guniting 10d 02-Sep-24 13-Sep-24 04-Oct-24 15-Oct-24 28d Guniting
M&F-FF-1210 Waterproofin g 10d 13-Sep-24 25-Sep-24 16-Oct-24 26-Oct-24 28d Waterproofin g
M&F-FF-1220 Plastering 10d 25-Sep-24 07-Oct-24 28-Oct-24 07-Nov-24 28d Plastering
M&F-FF-1230 MEP 2nd Fix 6d 07-Oct-24 14-Oct-24 08-Nov-24 14-Nov-24 28d MEP 2nd Fix
M&F-FF-1240 Waterproofin g 6d 14-Oct-24 21-Oct-24 15-Nov-24 21-Nov-24 28d Waterproofing
M&F-FF-1250 Wall til es 7d 20-Nov-24 28-Nov-24 22-Nov-24 29-Nov-24 2d Wall til es
M&F-FF-1260 Floor Tiles 7d 28-Nov-24 10-Dec-24 04-Dec-24 11-Dec-24 2d Floor Tiles
M&F-FF-1270 Railing and Ladder 4d 10-Dec-24 14-Dec-24 17-Feb-25 20-Feb-25 58d Railing and Ladder
M&F-FF-1280 Final Finishes 4d 14-Dec-24 19-Dec-24 21-Feb-25 25-Feb-25 58d Final Finishes
2nd Floor 309d 13-Feb-24 13-Feb-25 08-Aug-24 18-Apr-25 56d 13-Feb-25, 2nd Floor
M&F-SF-1600 Concrete works 15d 13-Feb-24 01-Mar-24 08-Aug-24 24-Aug-24 151d Concrete works
M&F-SF-1610 MEP 1st Fix 10d 01-Mar-24 14-Mar-24 26-Aug-24 05-Sep-24 151d MEP 1st Fix
M&F-SF-1620 Guniting 15d 14-Mar-24 01-Apr-24 06-Sep-24 23-Sep-24 151d Guniting
M&F-SF-1630 Waterproofin g 20d 01-Apr-24 24-Apr-24 24-Sep-24 16-Oct-24 151d Waterproofin g
M&F-SF-1640 Plastering 20d 24-Apr-24 17-May-24 17-Oct-24 08-Nov-24 151d Plastering
M&F-SF-1650 MEP 2nd Fix 10d 17-May-24 29-May-24 09-Nov-24 20-Nov-24 151d MEP 2nd Fix
M&F-SF-1660 Waterproofin g 15d 29-May-24 15-Jun-24 21-Nov-24 11-Dec-24 151d Waterproofin g
M&F-SF-1680 Wall til es 20d 10-Dec-24 03-Jan-25 12-Dec-24 04-Jan-25 2d Wall tiles
M&F-SF-1690 Floor Tiles 15d 03-Jan-25 21-Jan-25 06-Jan-25 22-Jan-25 2d Floor Tiles
M&F-SF-1700 Railing and Ladder 10d 21-Jan-25 01-Feb-25 22-Mar-25 01-Apr-25 51d Railing and Ladder
M&F-SF-1710 Final Finishes 10d 01-Feb-25 13-Feb-25 08-Apr-25 18-Apr-25 56d Final Finishes
3rd Floor 294d 14-Mar-24 25-Feb-25 18-Sep-24 24-Apr-25 51d 25-Feb-25, 3rd Floor
M&F-ThF-1190 Concrete works 15d 14-Mar-24 01-Apr-24 18-Sep-24 04-Oct-24 161d Concrete works
M&F-ThF-1200 MEP 1st Fix 10d 01-Apr-24 12-Apr-24 05-Oct-24 16-Oct-24 161d MEP 1st Fix
M&F-ThF-1210 Guniting 15d 12-Apr-24 30-Apr-24 17-Oct-24 02-Nov-24 161d Guniting
M&F-ThF-1220 Waterproofin g 20d 30-Apr-24 23-May-24 04-Nov-24 26-Nov-24 161d Waterproofin g
M&F-ThF-1230 Plastering 20d 23-May-24 15-Jun-24 27-Nov-24 23-Dec-24 161d Plastering

Actual Level of Effort Remaining Work Milestone Page 23 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
M&F-ThF-1240 MEP 2nd Fix 10d 15-Jun-24 27-Jun-24 24-Dec-24 04-Jan-25 161d MEP 2nd Fix
M&F-ThF-1250 Waterproofin g 15d 27-Jun-24 15-Jul-24 06-Jan-25 22-Jan-25 161d Waterproofin g
M&F-ThF-1270 Wall til es 20d 21-Jan-25 13-Feb-25 23-Jan-25 14-Feb-25 2d Wall til es
M&F-ThF-1290 Railing and Ladder 10d 01-Feb-25 13-Feb-25 02-Apr-25 12-Apr-25 51d Railing and Ladder
M&F-ThF-1280 Floor Tiles 5d 13-Feb-25 19-Feb-25 15-Feb-25 20-Feb-25 2d Floor Tiles
M&F-ThF-1300 Final Finishes 5d 19-Feb-25 25-Feb-25 19-Apr-25 24-Apr-25 51d Final Finishes
4th Floor 313d 08-Apr-24 12-Apr-25 17-Oct-24 06-May-25 21d 12-Apr-25, 4th Floor
M&F-Fr-1190 Concrete works 15d 08-Apr-24 25-Apr-24 17-Oct-24 02-Nov-24 165d Concrete works
M&F-Fr-1200 MEP 1st Fix 10d 25-Apr-24 07-May-24 04-Nov-24 14-Nov-24 165d MEP 1st Fix
M&F-Fr-1210 Guniting 15d 07-May-24 24-May-24 15-Nov-24 05-Dec-24 165d Guniting
M&F-Fr-1220 Waterproofin g 20d 24-May-24 17-Jun-24 06-Dec-24 28-Dec-24 165d Waterproofin g
M&F-Fr-1230 Plastering 20d 17-Jun-24 10-Jul-24 30-Dec-24 22-Jan-25 165d Plastering
M&F-Fr-1240 MEP 2nd Fix 10d 10-Jul-24 22-Jul-24 23-Jan-25 03-Feb-25 165d MEP 2nd Fix
M&F-Fr-1250 Waterproofin g 15d 22-Jul-24 08-Aug-24 04-Feb-25 20-Feb-25 165d Waterproofing
M&F-Fr-1290 Railing and Ladder 10d 13-Feb-25 25-Feb-25 14-Apr-25 24-Apr-25 51d Railing and Ladder
M&F-Fr-1270 Wall til es 20d 19-Feb-25 15-Mar-25 21-Feb-25 17-Mar-25 2d Wall til es
M&F-Fr-1280 Floor Tiles 15d 15-Mar-25 01-Apr-25 18-Mar-25 02-Apr-25 2d Floor Tiles
M&F-Fr-1300 Final Finishes 10d 01-Apr-25 12-Apr-25 25-Apr-25 06-May-25 21d Final Finishes
5th Floor 320d 03-May-24 16-May-25 23-Dec-24 17-May-25 2d 16-May-25, 5th Floor
M&F-Fi-1190 Concrete works 12d 03-May-24 17-May-24 23-Dec-24 06-Jan-25 197d Concrete works
M&F-Fi-1200 MEP 1st Fix 8d 17-May-24 27-May-24 07-Jan-25 15-Jan-25 197d MEP 1st Fix
M&F-Fi-1210 Guniting 12d 27-May-24 10-Jun-24 16-Jan-25 29-Jan-25 197d Guniting
M&F-Fi-1220 Waterproofin g 17d 10-Jun-24 29-Jun-24 30-Jan-25 18-Feb-25 197d Waterproofin g
M&F-Fi-1230 Plastering 17d 29-Jun-24 19-Jul-24 19-Feb-25 11-Mar-25 197d Plastering
M&F-Fi-1240 MEP 2nd Fix 8d 19-Jul-24 29-Jul-24 12-Mar-25 20-Mar-25 197d MEP 2nd Fix
M&F-Fi-1250 Waterproofin g 12d 29-Jul-24 12-Aug-24 21-Mar-25 02-Apr-25 197d Waterproofin g
M&F-Fi-1290 Railing and Ladder 8d 25-Feb-25 06-Mar-25 28-Apr-25 06-May-25 53d Railing and Ladder
M&F-Fi-1270 Wall til es 17d 01-Apr-25 21-Apr-25 03-Apr-25 22-Apr-25 2d Wall til es
M&F-Fi-1280 Floor Tiles 12d 21-Apr-25 05-May-25 23-Apr-25 06-May-25 2d Floor Tiles
M&F-Fi-1300 Final Finishes 10d 05-May-25 16-May-25 07-May-25 17-May-25 2d Final Finishes
6th Floor 307d 25-May-24 23-May-25 11-Feb-25 24-May-25 2d 23-May-25, 6th Floor
M&F-Si-1190 Concrete works 6d 25-May-24 01-Jun-24 11-Feb-25 17-Feb-25 220d Concrete works
M&F-Si-1200 MEP 1st Fix 5d 01-Jun-24 07-Jun-24 18-Feb-25 22-Feb-25 220d MEP 1st Fix
M&F-Si-1210 Guniting 10d 07-Jun-24 19-Jun-24 24-Feb-25 06-Mar-25 220d Guniting
M&F-Si-1220 Waterproofin g 12d 19-Jun-24 03-Jul-24 08-Mar-25 21-Mar-25 220d Waterproofin g
M&F-Si-1230 Plastering 12d 03-Jul-24 17-Jul-24 22-Mar-25 03-Apr-25 220d Plastering
M&F-Si-1240 MEP 2nd Fix 8d 17-Jul-24 26-Jul-24 04-Apr-25 12-Apr-25 220d MEP 2nd Fix
M&F-Si-1250 Waterproofin g 10d 26-Jul-24 07-Aug-24 14-Apr-25 24-Apr-25 220d Waterproofin g
M&F-Si-1290 Railing and Ladder 8d 06-Mar-25 17-Mar-25 09-May-25 17-May-25 55d Railing and Ladder
M&F-Si-1270 Wall til es 10d 21-Apr-25 02-May-25 25-Apr-25 06-May-25 4d Wall til es
M&F-Si-1280 Floor Tiles 10d 02-May-25 14-May-25 07-May-25 17-May-25 4d Floor Tiles
M&F-Si-1300 Final Finishes 6d 16-May-25 23-May-25 19-May-25 24-May-25 2d Final Finishes
Aluminium, Glazing, Glass Partitions & Metal Works 158d 10-Jul-24 15-Jan-25 20-Jan-25 24-Apr-25 86d 15-Jan-25, Aluminium, Glazing, Glass Partitions & Meta
A7930 Installation of Aluminium, Glazing, Glass Partitions &10d
Metal
10-Jul-24
Works at Ground
22-Jul-24
Floor 20-Jan-25 30-Jan-25 162d Installation of Aluminium, Glazing, Glass Partitions & Metal Works at Ground Floor
A7940 Installation of Aluminium, Glazing, Glass Partitions &12d
Metal
28-Aug-24
Works at 1st11-Sep-24
Floor 31-Jan-25 13-Feb-25 130d Installation of Aluminium, Glazing, Glass Partitions & Metal Works at 1st Floor
A7950 Installation of Aluminium, Glazing, Glass Partitions &12d
Metal
21-Sep-24
Works at 2nd05-Oct-24
Floor 14-Feb-25 27-Feb-25 121d Installation of Aluminium, Glazing, Glass Partitions & Metal Works at 2nd
A7960 Installation of Aluminium, Glazing, Glass Partitions &12d
Metal
11-Oct-24
Works at 3rd25-Oct-24
Floor 28-Feb-25 14-Mar-25 116d Installation of Aluminium, Glazing, Glass Partitions & Metal Works at 3
A7970 Installation of Aluminium, Glazing, Glass Partitions &12d
Metal
31-Oct-24
Works at 4th14-Nov-24
Floor 15-Mar-25 27-Mar-25 111d Installation of Aluminium, Glazing, Glass Partitions & Metal Works
A7980 Installation of Aluminium, Glazing, Glass Partitions &12d
Metal
05-Dec-24
Works at 5th19-Dec-24
Floor 28-Mar-25 10-Apr-25 96d Installation of Aluminium, Glazing, Glass Partitions & Metal W
A7990 Installation of Aluminium, Glazing, Glass Partitions &12d
Metal
31-Dec-24
Works at 6th15-Jan-25
Floor 11-Apr-25 24-Apr-25 86d Installation of Aluminium, Glazing, Glass Partitions & M
Garbage Disposal System 65d 04-Feb-25 21-Apr-25 12-Mar-25 24-May-25 30d 21-Apr-25, Garbage Disposal System

Actual Level of Effort Remaining Work Milestone Page 24 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A7900 Garbage Chute Disposal System 30d 04-Feb-25 12-Mar-25 12-Mar-25 14-Apr-25 30d Garbage Chute Disposal System
A7890 Provision of Garbage Trolly 10d 03-Apr-25 15-Apr-25 08-May-25 19-May-25 30d Provision of Garbage Trolly
A7910 Installation of PVC Vinyl Wall Guard 5d 15-Apr-25 21-Apr-25 20-May-25 24-May-25 30d Installation of PVC Vinyl Wall Guard
Gym & Kids Area Equipment 10d 03-May-25 15-May-25 14-May-25 24-May-25 9d 15-May-25, Gym & Kids Area Equ
A7850 Gym equipment, kids area & lockers 10d 03-May-25 15-May-25 14-May-25 24-May-25 9d Gym equipment, kids area & lock
Landscaping 15d 28-Apr-25 15-May-25 08-May-25 24-May-25 9d 15-May-25, Landscaping
A7860 Lanscaping Works 15d 28-Apr-25 15-May-25 08-May-25 24-May-25 9d Lanscaping Works
Swimming Pool & Open Shower Area 109d 21-Oct-24 01-Mar-25 13-Jan-25 24-May-25 73d 01-Mar-25, Swimming Pool & Open Shower Are
Civil Works 38d 21-Oct-24 07-Dec-24 13-Jan-25 25-Feb-25 68d 07-Dec-24, Civil Works
M&F-FF-1300 Guniting 10d 21-Oct-24 01-Nov-24 13-Jan-25 23-Jan-25 68d Guniting
M&F-FF-1310 Water proofing 7d 01-Nov-24 09-Nov-24 24-Jan-25 31-Jan-25 68d Water proofing
M&F-FF-1320 Plastering 7d 09-Nov-24 18-Nov-24 01-Feb-25 08-Feb-25 68d Plastering
M&F-FF-1330 MEP 2nd FIX 7d 18-Nov-24 26-Nov-24 10-Feb-25 17-Feb-25 68d MEP 2nd FIX
M&F-FF-1340 Waterproofin g 7d 26-Nov-24 07-Dec-24 18-Feb-25 25-Feb-25 68d Waterproofin g
Finishing Works 61d 19-Dec-24 01-Mar-25 26-Feb-25 24-May-25 73d 01-Mar-25, Finishing Works
M&F-FF-1350 Wall Tiles 10d 19-Dec-24 31-Dec-24 26-Feb-25 10-Mar-25 58d Wall Tiles
M&F-FF-1360 Floor tiles 8d 31-Dec-24 10-Jan-25 11-Mar-25 19-Mar-25 58d Floor tiles
M&F-FF-1370 Railing and ladder 4d 17-Feb-25 21-Feb-25 13-May-25 16-May-25 73d Railing and ladder
M&F-FF-1380 Final Finishes 7d 21-Feb-25 01-Mar-25 17-May-25 24-May-25 73d Final Finishes
MEP 3rd Fix 32d 10-Jan-25 17-Feb-25 20-Mar-25 24-Apr-25 58d 17-Feb-25, MEP 3rd Fix
A7620 Filtration Chamber 4d 10-Jan-25 15-Jan-25 20-Mar-25 23-Mar-25 58d Filtration Chamber
A7630 Control Panel 4d 15-Jan-25 20-Jan-25 24-Mar-25 27-Mar-25 58d Control Panel
A7640 Water Pumps 4d 20-Jan-25 24-Jan-25 28-Mar-25 01-Apr-25 58d Water Pumps
A7650 Chemical Dosing Controls 4d 24-Jan-25 29-Jan-25 02-Apr-25 05-Apr-25 58d Chemical Dosing Controls
A7660 Balancing tank 4d 29-Jan-25 03-Feb-25 07-Apr-25 10-Apr-25 58d Balancing tank
A7670 Back Water Tank 4d 03-Feb-25 07-Feb-25 11-Apr-25 15-Apr-25 58d Back Water Tank
A7680 Heating & Cooling System 4d 07-Feb-25 12-Feb-25 16-Apr-25 19-Apr-25 58d Heating & Cooling System
A7690 Light Fittings 4d 12-Feb-25 17-Feb-25 21-Apr-25 24-Apr-25 58d Light Fittings
Signages, Column Guards, Humps, Traffic Mirrors, Wheel Stopper etc. 24d 23-Mar-25 19-Apr-25 28-Mar-25 24-Apr-25 5d 19-Apr-25, Signages, Column Guards
A7870 Installation on Ground Floor 12d 23-Mar-25 05-Apr-25 28-Mar-25 10-Apr-25 5d Installation on Ground Floor
A7880 Installation on Podium Floor 12d 05-Apr-25 19-Apr-25 11-Apr-25 24-Apr-25 5d Installation on Podium Floor
Lifts 112d 18-Jun-24 26-Oct-24 02-Oct-24 13-Feb-25 90d 26-Oct-24, Lifts
A8090 Installation of Over Head Electrical Equipments 20d 18-Jun-24 11-Jul-24 02-Oct-24 24-Oct-24 90d Installation of Over Head Electrical Equipments
A8100 Machine Installation 20d 11-Jul-24 03-Aug-24 25-Oct-24 16-Nov-24 90d Machine Installation
A8110 Entrance Jamb Fixing 20d 03-Aug-24 27-Aug-24 18-Nov-24 13-Dec-24 90d Entrance Jamb Fixing
A8120 Controller Installation 12d 27-Aug-24 10-Sep-24 14-Dec-24 27-Dec-24 90d Controller Installation
A8130 Shaft Wiring & Roping 20d 10-Sep-24 03-Oct-24 28-Dec-24 21-Jan-25 90d Shaft Wiring & Roping
A8140 Cabin Installation 20d 03-Oct-24 26-Oct-24 22-Jan-25 13-Feb-25 90d Cabin Installation
Sauna & Steam Rooms 11d 18-Mar-25 29-Mar-25 12-Apr-25 24-Apr-25 23d 29-Mar-25, Sauna & Steam Rooms
A8060 Installation of all necessory equipments for Sauna & 7d
Steam
18-Mar-25
Room 25-Mar-25 12-Apr-25 19-Apr-25 23d Installation of all necessory equipments for
A8070 Fixing of Equipments for Sauna & Steam Room 4d 25-Mar-25 29-Mar-25 21-Apr-25 24-Apr-25 23d Fixing of Equipments for Sauna & Steam
10d 16-Apr-25
Facade Lighting, Facade Signage (Digital) & Screening of Roof MEP Services 28-Apr-25 16-Apr-25 26-Apr-25 0d 28-Apr-25, Facade Lighting, Facade
A8080 Installation of Facade Lighting, Signage & Screening
10d
of Roof
16-Apr-25 28-Apr-25 16-Apr-25 26-Apr-25 0d Installation of Facade Lighting, Signa
Authority Inspection, Testing, Commissioning and Handover 176d 26-Oct-24 26-May-25 14-Feb-25 24-May-25 0d 26-May-25, Authority Inspection
Authority Insepection 70d 05-Mar-25 26-May-25 05-Mar-25 23-May-25 -1d 26-May-25, Authority Insepectio
AI-1000 Final As Built drawing Submission to all Authorities 10d 05-Mar-25 18-Mar-25 05-Mar-25 17-Mar-25 0d Final As Built drawing Submission to all Auth
AI-1010 Final As Built drawing approval from authority 5d 18-Mar-25 24-Mar-25 18-Mar-25 23-Mar-25 0d Final As Built drawing approval from author
AI-1020 DEWA 1st inspection 2d 24-Mar-25 26-Mar-25 24-Mar-25 25-Mar-25 0d DEWA 1st inspection
AI-1120 Telecommunication inspection and approval 14d 24-Mar-25 11-Apr-25 26-Mar-25 14-Apr-25 2d Telecommunication inspection and app
AI-1130 SIRA inspection and Approval 14d 24-Mar-25 11-Apr-25 08-Apr-25 25-Apr-25 11d SIRA inspection and Approval
AI-1140 DEWA water inspection and approval 16d 24-Mar-25 15-Apr-25 24-Mar-25 14-Apr-25 0d DEWA water inspection and approval
AI-1030 DEWA comments rectification 8d 26-Mar-25 07-Apr-25 04-Apr-25 15-Apr-25 7d DEWA comments rectification

Actual Level of Effort Remaining Work Milestone Page 25 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
G+P+6 residential and Retail building Baseline-Corrected Classic Schedule Layout 21-Feb-24 07:23
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total 2023 2024 2025
Duration Qtr 2
Float Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
AI-1040 DEWA 2nd inspection and approval 4d 07-Apr-25 11-Apr-25 16-Apr-25 21-Apr-25 7d DEWA 2nd inspection and approval
AI-1150 Power Connection 4d 11-Apr-25 17-Apr-25 22-Apr-25 25-Apr-25 7d Power Connection
AI-1160 Permenant Services Connection 12d 15-Apr-25 01-May-25 15-Apr-25 30-Apr-25 0d Permenant Services Connection
AI-1050 DCD 1st Inspection 2d 25-Apr-25 29-Apr-25 25-Apr-25 28-Apr-25 0d DCD 1st Inspection
AI-1060 DCD Comments rectification 5d 29-Apr-25 06-May-25 29-Apr-25 05-May-25 0d DCD Comments rectification
AI-1070 DCD 2nd inspection and Approval 3d 06-May-25 09-May-25 06-May-25 08-May-25 0d DCD 2nd inspection and Approval
AI-1080 Trakhees 1st Inspection 2d 09-May-25 13-May-25 09-May-25 12-May-25 0d Trakhees 1st Inspection
AI-1090 Trakhees comments rectification 6d 13-May-25 21-May-25 13-May-25 20-May-25 0d Trakhees comments rectification
AI-1100 Trakhees 2nd Inspection and Approval 2d 21-May-25 23-May-25 21-May-25 22-May-25 0d Trakhees 2nd Inspection and Ap
AI-1110 Completion Certificate 1d 23-May-25 26-May-25 23-May-25 23-May-25 0d Completion Certificate
Testing and commissioning 176d 26-Oct-24 26-May-25 14-Feb-25 24-May-25 0d 26-May-25, Testing and commis
A2890 Testing and commissioning of Lifts 40d 26-Oct-24 16-Dec-24 14-Feb-25 01-Apr-25 90d Testing and commissioning of Lifts
A2880 Testing and commissioning of Plumbing and firefighting
25d works
23-Apr-25 22-May-25 26-Apr-25 24-May-25 3d Testing and commissioning of Pl
A2860 Testing and commissioning of Elecrical works 24d 28-Apr-25 26-May-25 28-Apr-25 24-May-25 0d Testing and commissioning of E
A2870 Testing and commissioning of HVAC works 24d 28-Apr-25 26-May-25 28-Apr-25 24-May-25 0d Testing and commissioning of H
Left out works 10d 27-Dec-24 09-Jan-25 14-Apr-25 24-Apr-25 90d 09-Jan-25, Left out works
A1040 tower crane / hoist dismantling 10d 27-Dec-24 09-Jan-25 14-Apr-25 24-Apr-25 90d tower crane / hoist dismantling
Closing out 25d 26-Apr-25 26-May-25 26-Apr-25 24-May-25 0d 26-May-25, Closing out
T&C-1050 Cleaning and Demoblization 25d 26-Apr-25 26-May-25 26-Apr-25 24-May-25 0d Cleaning and Demoblization
A1280 Operational Manual & Warranties submissio n 5d 09-May-25 15-May-25 14-May-25 19-May-25 4d Operational Manual & Warranties
A1290 Operational Manual & Warranties approval 5d 15-May-25 21-May-25 20-May-25 24-May-25 4d Operational Manual & Warrantie
T&C-1080 Handing Over 0d 26-May-25 24-May-25 0d Handing Over,

Actual Level of Effort Remaining Work Milestone Page 26 of 26 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation