COMERCIAL BUILDING AT NALUKODY ,Changanaserry, KERALA

CONSTRUCTION PHASE 1
MAIN BUILDING GF,FF,SF,TF,ROOF
Activity % Activity %
Actual Start Actual Start Actual Finish Remarks
BASEMENT FLOOR STRUCTRAL Complete Complete
STRUCTURA
L ZONE Excavation & compaction 0% 0% 15-Mar-2024
1 Strip footing construction 20-Mar-2024 0% 0% 10-Apr-2024
2 Fixing of Sleeves/Puddle Flanges 25-Mar-2024 0% 0% 08-Apr-2024
3 RCC wall construction 11-Apr-2024 0% 0% 30-Apr-2024
4 External water proofing 05-May-2024 0% 0% 15-May-2024
5 Back filling 10-May-2024 0% 0% 30-May-2024
6 Grade slab 25-May-2024 0% 0% 10-Jun-2024
7 Equipment foundation & stair construction 05-Jun-2024 0% 0% 15-Jun-2024
8 Roof beam & slab construction 16-Jun-2024 0% 0% 30-Jun-2024
9 Fixing of Sleeves in roof slab 27-Jun-2024 0% 0% 30-Jun-2024
GROUND FLOOR STRUCTURAL
10 Ground floor columns work 02-Jul-2024 0% 0% 17-Jul-2024
Ground floor roof slab shuttering and steel work ( first
11 floor slab ) 17-Jul-2024 0% 0% 30-Jul-2024
FIRST FLOOR STRUCTURAL
12 First floor columns 03-Aug-2024 0% 0% 17-Aug-2024
13 First floor roof slab work (secend floor slab ) 17-Aug-2024 0% 0% 05-Sep-2024
SECEND FLOOR STRUCTURAL
14 Secend floor columns 07-Sep-2024 0% 0% 22-Sep-2024
15 Secend floor roof slab (Third floor slab ) 20-Sep-2024 0% 0% 10-Oct-2024
THIRD FLOOR STRUCTURAL
16 Thrid floor columns 10-Oct-2024 0% 0% 27-Oct-2024
17 Third floor roof slab (4th foor slab /terrace) 25-Oct-2024 0% 0% 15-Nov-2024
18 terace wate rtank and staircase roof slab 15-Oct-2024 0% 0% 30-Oct-2024
BLOCK WORK
19 Basement block work 15-Jul-2024 0% 0% 22-Jul-2024
20 Ground floor block work 17-Aug-2024 0% 0% 30-Aug-2024
21 First floor block work 17-Sep-2024 0% 0% 30-Sep-2024
22 Secend floor block work 25-Oct-2024 0% 0% 05-Nov-2024
23 Third floor block work 01-Dec-2024 0% 0% 06-Jan-2025
24 Roof parapet work 10-Dec-2024 0% 0% 15-Dec-2024
25
26
PLASTERING WORK CORDINATED WITH MEP
27 Basement plastering 01-Aug-2024 0% 0% 15-Aug-2024
28 Ground floor plastering 10-Sep-2024 0% 0% 15-Sep-2024
29 Ffirat floor plastering 10-Oct-2024 0% 0% 30-Oct-2024
30 Secend floor plastering 12-Nov-2024 0% 0% 05-Dec-2024
31 Third floor plastering 10-Jan-2025 0% 0% 30-Jan-2025
32 Forth floor -roof plastering 15-Jan-2025 0% 0% 30-Jan-2025
33 EXTERNAL PLASTERING 10-Dec-2024 0% 0% 30-Jan-2025
TOTAL DURATION OF STRUCTURAL WORK ( INCLUDING
BLOCK WORK AND PLASTERING )
20-Mar-2024 30-Jan-2025

FINISHING

1 MEP FIRST FIX 10-May-2024 0% 0% 10-Jan-2025


2 MEP FINAL FIX 12-Nov-2024 0% 0% 10-Jun-2025
3 Doors and windows 30-Oct-2024 0% 0% 10-Jun-2025
4 Floor finishing 15-Nov-2024 0% 0% 05-May-2025
5 Air conditioning 15-Dec-2024 0% 0% 05-Jun-2025
6 Plumbing Equipments/sanitary 01-Jan-2025 0% 0% 05-Jun-2025
7 Electrical & lighting 01-Jun-2025 0% 0% 05-Jul-2025
8 Switches, sockets & DB fixing 01-May-2025 0% 0% 05-Jul-2025
9 Fire fighting pipe work 15-Nov-2024 0% 0% 10-Jun-2025
10 Fire fighting final fix 10-Jan-2025 0% 0% 10-Jun-2025
11 Testing & Commissioning 15-Jun-2025 0% 0% 02-Jul-2025
12 PAINTING WORK-INTERNAL 10-Dec-2024 0% 0% 30-May-2025
13 PAINTING WORK -EXTERNAL 15-Feb-2025 0% 0% 20-Jun-2025
14 Snag Work 10-Jun-2025 0% 0% 03-Jul-2025
15 Handing Over 06-Jul-2025 0% 0% 21-Jul-2025

THE COMPLETION OF WORKKS DEPENDS UPON THE FINISHING OF ELEVATION STEEL STRUCTURAL WORKS