Program Schedule

Sl Description of Description of Work in Hindrance free Area Approx. Quantity Unit Target Date of Completion RATE AMOUNT
No. Structure

Abutment wall, Counterfort wall, Return Wall of 600 Cum 15.03.2024


1 Bridge No - 7 Abutment -1 & Abutment -2 5294.36 3,176,616.00

i) Box portion in all respect , 450 Cum 28.02.2024


2 Bridge No -7A ii) Return Wall Raft, wall towards Br No-7 5294.36 2,382,462.00

3 Bridge No -10 Flooring with rubble stone 27.676 Cum 07.02.2024 2210.19 61,169.22
4 Bridge No -11 Flooring with rubble stone 48.163 Cum 04.02.2024 2210.19 106,449.38
Pitching with stone boulders 42.286 Cum 28.01.2024 2100.45 88,819.63
5 Bridge No -14 Flooring with rubble stone 41.004 Cum 22.01.2024 2210.19 90,626.63
Pitching with stone boulders 28.496 Cum 06.02.2024 2100.45 59,854.42
6 Bridge No -15
Flooring with rubble stone 35.778 Cum 25.01.2024 2210.19 79,076.18
Pitching with stone boulders 28.496 Cum 14.02.2024 2100.45 59,854.42
7 Bridge No -15A
Flooring with rubble stone 29.370 Cum 28.01.2024 2210.19 64,913.28
8 Bridge No -16 Flooring with rubble stone 25.612 Cum 02.02.2024 2210.19 56,607.39
Retaining Wall 60.00 Cum 15.02.2024 5444.54 326,672.40
9 Bridge No -17 Blanketing in Approach from Ch :-7740 to 7860 and 1600 Cum
1496.9 2,395,040.00
7880 to 7900 m . 25.01.2024
Flooring with rubble stone 25.612 Cum 10.02.2024 2210.19 56,607.39
10 Bridge No -18
Blanketing from Ch :- 8000 to 8080 m. 400.000 Cum 31.01.2024 1496.9 598,760.00
Sl Description of Description of Work in Hindrance free Area Approx. Quantity Unit Target Date of Completion RATE AMOUNT
No. Structure

11 Wharf Wall & Final Lift from Ch:- 7835 to 7863 , 7213 to 7220 m 50.000 Cum 05.02.2024
5444.54 272,227.00
Loading Platform (LHS)
(LHS & RHS) Procurement of Boulder = 10800.000 Cum 25.02.2024 (L.H.S)
Weekly Procurement = 1000 31.03.2024 (R.H.S) -

Boulder flooring (1200 m) 10800.000 Cum 31.03.2024 1355.29 14,637,132.00


WBM ( 1200 m) 3600.000 Cum 05.03.2024 (L.H.S)
2261.95 8,143,020.00
20.04.2024 (R.H.S)
12 Building Work RCC of Gr Floor Roof Slab of EI Building 31.01.2024 502,216.00
RCC of Lintel Beam of TMS Building 30.01.2024 101,562.00
RCC of Roof Slab of TMS Building 20.02.2024 225,422.00
13 Track Linking 02.02.2024 (up to 2000 trm)
Work Track linking at Yard Portion 6000 Trm 25.02.2024 (up to 4000 trm) 815.11 4,890,660.00
15.03.2024 (up to 6000 trm)
10.02.2024 (2 set)
1 in 12 Points & X-ing 12 set 05.03.2024 (5 set) 155559.95 1,866,719.40
25.03.2024 (5 set)
1in 8.5 Points & X-ing 1 set 25.02.2024 116669.96 116,669.96
02.02.2024 (1 set)
DS 5 set 25.02.2024 (3 set) 41482.65 207,413.25
15.03.2024 (1 set)
14 Diversion Road Earth Filling from Br No-16 to 17. 1500 Cum 31.03.2024 150.74 226,110.00
from Ch:-6625 to GSB 3700 cum 20.02.2024 1936.3 7,164,310.00
Br No-17 to MIC WMM 1576.2 cum 05.03.2024 2066.83 3,257,737.45
Road Bitumen Penetration macadam 10360 sqm 20.03.2024 391.42 4,055,111.20
Seal Coat 10360 sqm 25.03.2024 57.67 597,461.20
55,867,299.79