17 Steel
Footings MT 316 50,000 4,000 15,809,577 1,264,766 17,074,343
Retaining wall raft MT 198 50,000 4,000 9,900,000 792,000 10,692,000
STP bottom slab / Raft MT 23 50,000 4,000 1,138,500 91,080 1,229,580
Retaining wall - Lower Basement to upper Basement-
MT 105 50,000 4,000 5,250,000 420,000 5,670,000
M25
Retaining wall - Upper Basement to GF-M25 MT 80 50,000 4,000 4,000,000 320,000 4,320,000
Puzzle Parking wall MT 24 50,000 4,000 1,215,495 97,240 1,312,735
Drive way grade slab MT 16 50,000 4,000 815,750 65,260 881,010
Puzzle parking pit Grade slab MT 63 50,000 4,000 3,172,076 253,766 3,425,842
18 Columns 4,000
Lower Basement to upper Basement- M45 (Tower
MT 88 50,000 4,000 4,400,000 352,000 4,752,000
column s- 65nos and podium - 30nos)
Upper basement to GF -M45( Tower column s- 65nos
MT 59 50,000 4,000 2,950,000 236,000 3,186,000
and podium - 30nos)
GF TO 1st Floor (Retail)-M45 MT 39 50,000 4,000 1,950,000 156,000 2,106,000
1st floor to 2nd Floor -M45 MT 39 50,000 4,000 1,950,000 156,000 2,106,000
2nd floor to 3rd Floor-M45 MT 40 50,000 4,000 2,000,000 160,000 2,160,000
3rd floor to 4th Floor-M45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
4Th Floor to 5th Floor-M45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
5th Floor to 6TH Floor-M45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
6th Floor to 7th Floor-M45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
7th Floor to 8th floor-M45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
8th floor to 9th Floor-M45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
9th Floor to 10th Floor-45 MT 32 50,000 4,000 1,600,000 128,000 1,728,000
10th Floor to 11th Floor MT 32 50,000 4,000 1,600,000 128,000 1,728,000
11Th Floor to 12th Floor MT 32 50,000 4,000 1,600,000 128,000 1,728,000
12th Floor to Terrace Floor MT 16 50,000 4,000 800,000 64,000 864,000
Terrace to LMR TOP MT 6 50,000 4,000 320,541 25,643 346,184
19 Shear wall 50,000
Lower Basement to upper Basement MT 19 50,000 4,000 964,950 77,196 1,042,146
GF TO 1st Floor (Retail)-M45 MT 16 50,000 4,000 800,000 64,000 864,000
1st floor to 2nd Floor MT 15 50,000 4,000 750,000 60,000 810,000
2nd Floor to 3rd Floor MT 15 50,000 4,000 750,000 60,000 810,000
3rd floor to 4th Floor MT 9 50,000 4,000 427,491 34,199 461,690
4Th Floor to 5th Floor MT 9 50,000 4,000 427,491 34,199 461,690
5th Floor to 6TH Floor MT 9 50,000 4,000 427,491 34,199 461,690
6th Floor to 7th Floor MT 9 50,000 4,000 427,491 34,199 461,690
7th Floor to 8th floor MT 9 50,000 4,000 427,491 34,199 461,690
8th floor to 9th Floor MT 9 50,000 4,000 427,491 34,199 461,690
9th Floor to 10th Floor MT 9 50,000 4,000 427,491 34,199 461,690
10th Floor to 11th Floor MT 9 50,000 4,000 427,491 34,199 461,690
11Th Floor to 12th Floor MT 9 50,000 4,000 427,491 34,199 461,690
12th Floor to Terrace Floor MT 9 50,000 4,000 427,491 34,199 461,690
Terrace to LMR TOP MT 9 50,000 4,000 427,491 34,199 461,690
20 Slab & Capitals 50,000
Upper Basement- M30(including capitals and beams,
MT 231 50,000 4,000 11,550,000 924,000 12,474,000
ramp)
Ground Floor-M35(including capitals and beams, ramp) MT 231 50,000 4,000 11,550,000 924,000 12,474,000
First Floor- Retail MT 86 50,000 4,000 4,279,500 342,360 4,621,860
First - Parking Level -01-M30 MT 87 50,000 4,000 4,358,813 348,705 4,707,518
First - Parking Level -02-M30 MT 87 50,000 4,000 4,358,813 348,705 4,707,518
Second Floor -M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Third Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Fourth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Fifth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Sixth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Seventh Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Eighth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Nineth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Tenth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Eleventh Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Twelveth Floor-M30 MT 170 50,000 4,000 8,500,000 680,000 9,180,000
Terrace MT 98 50,000 4,000 4,898,876 391,910 5,290,786
LMR bottom MT 20 50,000 4,000 977,813 78,225 1,056,038
LMR Top MT 20 50,000 4,000 977,813 78,225 1,056,038
Chiller plastform MT 19 50,000 4,000 967,500 77,400 1,044,900
21 Stairacse 50,000
Lower Basement to upper Basement MT 18 50,000 4,000 893,750 71,500 965,250
Upper basement to GF MT 18 50,000 4,000 893,750 71,500 965,250
GF TO 1st Floor MT 18 50,000 4,000 893,750 71,500 965,250
1st floor to 2nd Floor MT 18 50,000 4,000 893,750 71,500 965,250
2nd Floor to 3rd Floor MT 17 50,000 4,000 838,750 67,100 905,850
3rd floor to 4th Floor MT 17 50,000 4,000 838,750 67,100 905,850
4Th Floor to 5th Floor MT 17 50,000 4,000 838,750 67,100 905,850
5th Floor to 6TH Floor MT 17 50,000 4,000 838,750 67,100 905,850
6th Floor to 7th Floor MT 17 50,000 4,000 838,750 67,100 905,850
7th Floor to 8th floor MT 17 50,000 4,000 838,750 67,100 905,850
8th floor to 9th Floor MT 17 50,000 4,000 838,750 67,100 905,850
9th Floor to 10th Floor MT 17 50,000 4,000 838,750 67,100 905,850
10th Floor to 11th Floor MT 17 50,000 4,000 838,750 67,100 905,850
11Th Floor to 12th Floor MT 17 50,000 4,000 838,750 67,100 905,850
12th Floor to Terrace Floor MT 17 50,000 4,000 838,750 67,100 905,850
Above Terrace MT 17 50,000 4,000 838,750 67,100 905,850 319,860,000.00
22 Block works
Lower Basement
8" sqmt 67 769 180 51,139 11,970 63,109
6" sqmt 146 544 170 79,440 24,825 104,265
4" sqmt 8 442 160 3,315 1,200 4,515
Upper Basement
8" sqmt 67 769 180 51,139 11,970 63,109
6" sqmt 146 544 170 79,440 24,825 104,265
4" sqmt 8 442 160 3,315 1,200 4,515
Ground Floor
6" sqmt 1,829 544 170 994,766 310,864 1,305,631
4" sqmt 168 442 160 74,194 26,858 101,052
First Floor- Retail / Parking
6" sqmt 1,829 544 170 994,766 310,864 1,305,631
4" sqmt 168 442 160 74,194 26,858 101,052
44 Other Activities
Retail area screeding Ground floor cum 2,010 4,175 60 8,391,750 120,600
Retail area screedingFirst Floor cum 2,010 4,175 60 8,391,750 120,600
Retail area screeding Second floor cum 2,010 4,175 60 8,391,750 120,600
Food court cum 2,300 4,175 60 9,602,500 138,000
46 ASSETS
SHUTTERING MATERIAL COST 47,849,065
TOWER CRANE 6,500,000
TOWER CRANE OPERATOR+ELECTRICITY 1,200,000
DG-65&125 KVA 1,500,000
TOUGH RIDER 700,000
OPERATOR FOR TOUGH RIDER 400,000
CUTTING & BENDING MACHINE 300,000
PASSENGER/GOODS HOIST 1,500,000
MINI TANDON ROLLER 600,000
47 EXPENSES
TEMPORAY ELECTRICTY BILL 4,500,000
TOOLS & TACKELS 1,100,000
SAFETY MATERIALS 1,700,000
TOILET MAINTENACE 210,000
FOOD EXPENSES 300,000
LAB TESTING CHARGES 400,000
SURVEYOR CHARGES 350,000
ELECTRICAL ITEMS 900,000
PLUMBING ITEMS 500,000
CONSUMABLES 1,050,000
CONVEYANCE 250,000
FREIGHT CHARGES 300,000
HIRE CHARGES 850,000
PRINTING & STATIONARY 200,000
COMPUTER & PRINTER 300,000
REPIAR & MAINTENACE 425,000
STAFF AMENITIES 700,000
TELEPHONE EXPENSES 100,000
WATER(LABOUR SHED+OFFICE) 1,100,000
DIESEL-125KVA TOWER CRANE DG 2,196,000
DIESEL-65KVA DG 366,000
PETROL 150,000
CASH EXPENSES 2,000,000
1,445,142,852
1,756
LOWER BASEMENT DOORS
WIDTH HEIGHT NOS WIDTH
FD1 1.8 2.4 4 9 36 48254 D1 0.9
FD1A 1.8 2.4 4 9 36 48254 D2 1.05
FD2 1.2 2.4 3 9 27 32170 D3 0.75
FD2A 1.2 2.1 2 9 18 28148 D4 0.6
FD3 1.5 2.4 2 9 18 40212 D5 1.5
FD4 1.05 2.4 1 9 9 28148 WINDOWS
FD5 0.9 1.8 6 9 54 18095 W1 1
FD6 0.75 1.8 5 9 45 15080 W2 1.15
FD7 0.65 1.8 5 9 45 13069 W3 2.4
FD8 2 2.4 3 9 27 53616 W4 1.2
FD9 1.5 2.4 2 9 18 40212 W5 1.2
HEIGHT NOS
2.1 8 10 80 7875.63 4166.667
2.1 2 10 20 9188.235
2.1 2 10 20 6563.025
2.1 5 10 50 5250.42
2.4 4 10 40 15001.2
10 0
1.2 8 13 104 5000.4
1.2 8 13 104 5750.46
1.5 2 13 26 15001.2
1.2 2 13 26 6000.48
1.2 2 13 26 6000.48