Professional Documents
Culture Documents
B. ABUTMENT B
1.0 Gabions 50 pcs 2,830.00 700.00 3,530.00 176,500.00
Prepared by :
A. Methodology
1.0 Removal of Damage Concrete lining (July 18, 2023)
2.0 Filling of Boulders on the scoured area up to the level of Sheet Pile (July 18-21, 2023)
3.0 Filling of grouting on the boulders, (Rubble Masonry) (July 22-24, 2023)
4.0 Backfilling of the remaining gaps to achieve top elevation of road (July 25-27, 2023)
5.0 Construction of Approach slab, in parallel concrete lining restoration will also continue (July 28-31,2023)
6.0 Installation of barriers. (August 1-2, 2023)
REMARKS
Project : Access and infrastructure Project
Location : San Marcelino, Zamabales
Subject : Bridge 2 Access Works
Date : August 4, 2023
DIRECT COST SUBMITTED
ITEM ACTIVITY QTY UNIT UP AMOUNT UP AMOUNT
2.0 Backfilling
2.1 Dumptruck 240 hrs 1850 444,000.00 2,220.00 532,800.00
2.2 Excavator 240 hrs 2950 708,000.00 3,392.50 814,200.00
2.3 Compactor 80 hrs 3500 280,000.00 4,025.00 322,000.00
Retrievable
Project : Access and infrastructure Project
Location : San Marcelino, Zamabales
Subject : RCBC Construction at Sta. 600
Date : August 8, 2023
1.0 Diversion
2.1 Excavation 150 m3 August 11, 2023 August 11, 2023 1 backhoe
2.2 RCPC August 12, 2023 August 14, 2023 4 Carp 6 Helper from 2.1
2.3 Backfill August 15, 2023 August 16, 2023 from 2.1 3 Dumptruck 1 loader
2.0 RCBC 1 Compactor
2.1 Excavation 150 m3 August 14, 2023 August 14, 2023 1 backhoe 1 Grader
2.2 Lean Concrete 24.28892 m3 August 15, 2023 August 15, 2023
3.0 Foundation
3.1 Rebar August 16, 2023 August 19, 2023 4 fabricator 8 Installer
3.2 Formworks & Concrete 12.96 m3 August 20, 2023 August 20, 2023 from 2.2
4.0 Wall
4.1 Rebar August 21, 2023 August 24, 2023 from 3.1
4.2 Formworks & Concrete 25.92 m3 August 25, 2023 August 25, 2023 from 3.2
5.0 Top Slab
5.1 Rebar August 26, 2023 August 29, 2023 from 4.1
5.2 Formworks & Concrete 12.96 m3 August 30, 2023 August 30, 2023 from 4.2
Curring August 31, 2023 September 06, 2023
6.0 Backfilling September 07, 2023 September 14, 2023 from 2.3
B. RCBC
1.0 Concrete
1.1 Lean Concrete (3000 psi @ 28 days) 22.38 m3 8,119.82 181,751.78
1.2 RCBC Double Barrel (4000 psi @ 28 days) 191.62 m3 9,309.66 1,783,916.46
2.0 Rebar
2.1 12mm 3,725.40 kg 69.57 259,176.24
2.2 16mm 7,926.76 kg 69.57 551,464.51
2.3 20mm 8,260.22 kg 69.57 574,663.57
3.0 Formworks 696.39 sq.m. 1,521.69 1,059,691.51
4.0 Imported Fill Materials 5,711.27 m3 726.94 4,151,747.06
5.0 Sub Base Course 172.80 m3 1,120.56 193,632.77
6.0 Base Course 129.60 m3 1,534.08 198,816.77
C. Grouted Stepped Chute
1.0 Grouted Steps (boulder, Gabion and Grout) 216.00 m3 5,814.45 1,255,921.20
2.0 Compacted Filling Materials 1,345.54 m3 726.94 978,129.24
D. Steel Sheet Pile Type IV 35,614.80 kg 83.04 2,957,452.99
E. Pile Cap
1.0 Concrete (4000 psi) 26.01 m3 9,309.66 242,144.26
2.0 Formworks 47.58 sq.m. 1,521.69 72,402.01
3.0 Rebar
3.1 12mm 247.03 kg 69.57 17,185.95
3.2 16mm 193.42 kg 69.57 13,456.38
3.3 20mm 84.54 kg 69.57 5,881.67
3.4 25mm 516.30 kg 69.57 35,918.73
F. Pre-Cast Pile
1.0 Driven Pile 400x400x16m 21.00 piles 300,733.33 6,315,400.00
2.0 Casting Bed
Concrete 20.34 m3 8,119.82 165,157.14
Rebar 192.00 kg 69.57 13,357.44
Formworks 14.86 sq.m. 1,521.69 22,612.31
G. Diversion Road
1.0 Excavation 36 m3 390.00 14,040.00
2.0 RCPC 18 lm 6,097.00 109,746.00
3.0 Gabions 34 pcs 2,925.00 99,450.00
4.0 Equipment
5.0 Backhoe 1 520 hrs 4,173.00 2,169,960.00
6.0 Backhoe 2 470 hrs 4,173.00 1,961,310.00
2,880.00
4,000.00
6,880.00
Amount (PhP)
27,040.00
27,040.00
33,920.00
Amount (PhP)
117,514.53
117,514.53
151,434.53
15,143.45
15,143.45
-
8,119.82
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : RCBC at Existing Barangay Road
Item No./Description : Ready Mix Concrete 4000 psi at 28 Days
Unit of Measurement : m3
Output per hour : 3.42125
Quantity : 191.62
25,200.00
35,000.00
60,200.00
Amount (PhP)
315,000.00
315,000.00
375,200.00
Amount (PhP)
1,111,395.64
1,111,395.64
1,486,595.64
148,659.56
148,659.56
-
9,309.66
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : RCBC at Existing Barangay Road
Item No./Description : Rebar
Unit of Measurement : kg
Output per hour : 54.11
Quantity : 19912.4
165,600.00
57,500.00
223,100.00
Amount (PhP)
-
223,100.00
Amount (PhP)
174,237.06
370,734.44
386,330.53
931,302.04
1,154,402.04
115,440.20
115,440.20
-
69.57
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : RCBC at Existing Barangay Road
Item No./Description : Formworks
Unit of Measurement : sq.m
Output per hour : 1.8925
Quantity : 696.391
165,600.00
230,000.00
395,600.00
Amount (PhP)
-
395,600.00
Amount (PhP)
487,473.83
487,473.83
883,073.83
88,307.38
88,307.38
-
1,521.69
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : Embankment at Existing Barangay Road
Item No./Description : Imported Fill
Unit of Measurement : m3
Output per hour : 32.45
Quantity : 5711.27
-
Amount (PhP)
446,160.00
299,200.00
528,000.00
187,440.00
1,460,800.00
1,460,800.00
Amount (PhP)
1,998,942.79
1,998,942.79
3,459,742.79
345,974.28
345,974.28
-
726.94
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : Embankment at Existing Barangay Road
Item No./Description : Subbase Course
Unit of Measurement : m3
Output per hour : 21.6
Quantity : 172.8
-
Amount (PhP)
32,000.00
17,040.00
49,040.00
49,040.00
Amount (PhP)
112,320.00
112,320.00
161,360.00
16,136.00
16,136.00
-
1,120.56
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : Embankment at Existing Barangay Road
Item No./Description : Base Course
Unit of Measurement : m3
Output per hour : 16.2
Quantity : 129.6
-
Amount (PhP)
32,000.00
17,040.00
49,040.00
49,040.00
Amount (PhP)
116,640.00
116,640.00
165,680.00
16,568.00
16,568.00
-
1,534.08
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : RCBC at Existing Barangay Road
Item No./Description : Grouted Stepped Chute
Unit of Measurement : m3
Output per hour : 6.585
Quantity : 216
29,519.70
30,749.69
60,269.40
Amount (PhP)
221,725.78
80,687.19
302,412.98
362,682.38
Amount (PhP)
302,400.00
176,429.44
26,239.74
132,192.00
46,656.00
683,917.17
1,046,599.55
104,659.95
104,659.95
-
5,814.45
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : RCBC at Existing Barangay Road
Item No./Description : Steel Sheet Pile Type IV
Unit of Measurement : kg
Output per hour : 1112.96
Quantity : 35614.8
5,760.00
5,760.00
Amount (PhP)
48,000.00
48,000.00
53,760.00
Amount (PhP)
2,410,765.81
2,410,765.81
2,464,525.81
246,452.58
246,452.58
-
83.04
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project : San Marcelino Access and Infrastructute
Package : RCBC at Existing Barangay Road
Item No./Description : Pre-Cast Pile
Unit of Measurement : pcs
Output per hour : 0.09
Quantity : 21
104,400.00
145,000.00
249,400.00
Amount (PhP)
784,160.00
2,823,040.00
3,607,200.00
3,856,600.00
Amount (PhP)
311,808.00
660,716.67
282,240.00
85,311.12
40,688.88
25,468.50
1,406,233.17
5,262,833.17
526,283.32
526,283.32
-
300,733.33
Cutting List
Double Barrel 1 2 3 Total Unit Spacing
1 962.50 3,300.00 962.50 5,225.00 mm 250
2 270.00 3,370.00 270.00 3,910.00 mm 250
3 962.50 962.50 1,925.00 mm 250
4 270.00 6,510.00 270.00 7,050.00 mm 300
5 1,650.00 1,650.00 mm 250
6 1,725.00 1,725.00 mm 150
7 270.00 3,370.00 270.00 3,910.00 mm 250
8 1,650.00 1,650.00 mm 150
9 13,988.00 13,988.00 mm 200
10 487.50 989.95 487.50 1,964.95 mm 250
11 100 270 100 470.00 mm 200
Compacted
Filling Material
Sta. 0+500
Sta. 0+520
Sta. 0+540 3.2052150821
Sta. 0+560 6.5 116.4625809852 cu.m.
Sta. 0+565 10.11 49.83 cu.m.
Sta. 0+570 1st Layer 1.1 33.63 cu.m.
Sta. 0+570 2nd Layer 14.61 74.16 cu.m.
Sta. 0+575 1st Layer 12.944 210.66 cu.m.
Sta. 0+575 2nd Layer 18.3 98.73 cu.m.
Sta. 0+580 1st Layer 33.63 139.722 cu.m.
Sta. 0+580 2nd Layer 27.5980352824 137.6941058472 cu.m.
Sta. 0+600 1st Layer 66.65 1203.36 cu.m.
Sta. 0+600 2nd Layer 17.88 545.7364233888 cu.m.
Sta. 0+620 1st Layer 34.6 1215 cu.m.
Sta. 0+620 2nd Layer 30.56 581.28 cu.m.
Sta. 0+640 1st Layer 5.27 478.44 cu.m.
Sta. 0+640 2nd Layer 12.17 512.76 cu.m.
Sta. 0+660 5.18 208.2 cu.m.
Sta. 0+680 1.81 83.88 cu.m.
21.72 cu.m.
5711.2651102212
3280.812
Ø PCS Weight RCBC Rebar Summary
20 116 1,494.72 12mm 3,725.40
20 116 1,118.53 16mm 7,926.76
20 232 1,101.37 20mm 8,260.22
20 96 1,669.07
20 232 944.03
20 190 808.27
16 116 715.86
16 380 989.61
16 239 5,276.52
20 232 1,124.23
12 5616 2,343.38
Total: 15,242.21
14,126.93 kg 10,702.22
3,424.71
Note:
1 Pre-cast Pile
20mm 509.63 kg 7.85
12mm 163.08 kg 8.15
672.71
Concrete 2.56 cu.m.
Formworks 19.20 sq.m. 783.69 16457.49
C C width
11.12
3.95