August 29, 2023

To : MS. ANABELE R. NATIVIDAD


Vice President – Development
Santa Cruz Solar Energy Inc.

Thru : MS. MARGARITA ROXAS


Project Development Manager
Santa Cruz Solar Energy Inc.

MR. JOHANNES KASCHENBACH


Project Manager
Santa Cruz Solar Energy Inc.

ENGR. PABLITO BULACLAC


Project Manager
Filipinas Dravo Corporation

Project : ACCESS AND INFRASTRUCTURE- SAN MARCELINO

Subject : PROPOSAL FOR CONSTRUCTION OF RCBC


(Option 1: 2.4m x 2.4m and Option 2: 2.75m x2.75m)
AT STA. 0+596.42 AT EXISTING BARANGAY ROAD

Gentlemen,

We are writing you in reference to the above-mentioned subject for the Access and Infrastructure
Project in San Marcelino, Zambales.

We are pleased to submit our proposal that includes two options based on the design of the RCBC.
Option 1 - RCBC with two openings having a dimension of 2.4m by 2.4m designed for a 25-year-return and
50-year-checked amounting to Fourteen Million Six Hundred Thirty-nine Thousand Three
Hundred Fifty-three Pesos and Fifty-four Centavos (Php14, 639,353.54). (See attached Annex A)

Option 2 - is RCBC with two openings having a dimension of 2.75m by 2.75m designed for a 50 -year-return
and 100-year-checked amounting to Fourteen Million Nine Hundred Eighty Thousand One
Hundred Twenty-two Pesos and Sixty-two Centavos (Php14, 980,122.62). (See attached Annex B)

We also suggest not to proceed with the construction of RCBC until the designs for Slope protection
and Weir be accepted and approved. This will be for the protection of the RCBC once it is installed and
constructed. Our designers are working on these and we will submit it as soon as possible.

Should you have any concerns, please do not hesitate to contact us via email or phone number as
stated below.
Email: stacruzsolarenergy.tacc@gmail.com
Contact Number: 09992230969

Very truly yours,

Raymund Mark O. Escalona


Business Development Manager

The Burgundy Place Condominium Unit 306, 174 B. Gonzales Street, Loyola Heights, Quezon City 1108
Telephones: (+632) 929-7661; 426-5618 • Telefax: (+632) 929-7655 • Email: terpasia@yahoo.com
www.terpasia.com
ANNEX A

Project : Access and infrastructure Project


Location : San Marcelino, Zamabales
Subject : RCBC 2.4 x 2.4m Construction at Sta. 0+596.42
Date : September 1, 2023
PROPOSED COST
ITEM ACTIVITY QTY UNIT UP AMOUNT

1.0 General Requirement 1 lot 1,950,650.00 1,950,650.00


1.0 Diversion
2.1 Excavation 150 m3 637.00 95,550.00
2.2 RCPC 18 lm 6,097.00 109,746.00
2.3 Gabions 34 pcs 2,925.00 99,450.00
2.4 Equipment
Backhoe 1 520 hrs 4,173.00 2,169,960.00
Backhoe 2 470 hrs 4,173.00 1,961,310.00
2.0 RCBC
2.1 Excavation 244.13 m3 455.00 111,076.88
2.2 Lean Concrete 24.29 m3 7,150.00 173,665.78
2.3 Concrete 219.84 m3 7,670.00 1,686,176.02
2.4 Rebar 20,745.28 kgs 64.35 1,334,905.10
2.5 Formworks 626.79 m2 1,560.00 977,784.91
2.6 Grouted Steps 99.00 m3 5,525.00 546,975.00
3.0 Backfilling
3.1 Imported Materials 4998.3408 m3 624.00 3,118,964.66
3.2 Sub Base Course 136.32 m3 1,235.00 168,355.20
3.3 Base Course 86.4 m3 1,560.00 134,784.00

TOTAL 14,639,353.54

Prepared by :

Engr. Ryan Legaspi


Terp Asia Construction Corporation
ANNEX B

Project : Access and infrastructure Project


Location : San Marcelino, Zamabales
Subject : RCBC 2.75 x 2.75 m Construction at Sta. 0+596.42
Date : September 1, 2023

PROPOSED COST
ITEM ACTIVITY QTY UNIT UP AMOUNT

1.0 General Requirement 1 lot 1,950,650.00 1,950,650.00


1.0 Diversion
2.1 Excavation 36 m3 390.00 14,040.00
2.2 RCPC 18 lm 6,097.00 109,746.00
2.3 Gabions 34 pcs 2,925.00 99,450.00
2.4 Equipment
Backhoe 1 520 hrs 4,173.00 2,169,960.00
Backhoe 2 470 hrs 4,173.00 1,961,310.00
2.0 RCBC
2.1 Excavation 244.13 m3 390.00 95,208.75
2.2 Lean Concrete 26.79 m3 7,150.00 191,543.14
2.3 Concrete 240.64 m3 7,670.00 1,845,670.76
2.4 Rebar 22,001.01 kgs 64.35 1,415,707.88
2.5 Formworks 690.40 m2 1,560.00 1,077,021.50
2.6 Grouted Steps 99.00 m3 5,525.00 546,975.00
3.0 Backfilling
3.1 Imported Materials 5206.605 m3 624.00 3,248,921.52
3.2 Sub Base Course 136.32 m3 1,014.00 138,228.48
3.3 Base Course 86.4 m3 1,339.00 115,689.60

TOTAL 14,980,122.62

Prepared by :

Engr. Ryan Legaspi


Terp Asia Construction Corporation