SCHEDULE PERBAIKAN CHIPSEAL HAULING ROAD AREA REMEDIATION DAN REALIGNEMENT

DURASI
Feb-24 Mar-24 Apr-24 May-24 Jun-24 Aug-24 Sep-24
No item Volume Units Periode
WEEK WEEK WEEK WEEK WEEK WEEK WEEK
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 Widening KM 29.5 40.00
1.1 Earthworks 17.00
1.1.1 Fill Pavement Scorea m3 1,486.50 5.00
1.1.2 Fill Pavement Base B m3 891.90 5.00
1.1.3 Fill Pavement Base A m3 1,140.00 5.00
1.2 Open Traffic 14.00
1.3 Chipseal Pavement 9.00
1.3.1 Smoothing/trimming Surface Base m2 5,600.00 2.00
1.3.2 Primecoat m2 5,600.00 2.00
1.3.3 Chipseal Double Layer m2 4,900.00 5.00
2 Realignement KM 6.5 60.00
2.1 Earthworks 28.00
2.1.1 Fill OB m3 36,113.00 7.00
2.1.2 Fill Pavement Boulder/Scorea m3 4,531.80 7.00
2.1.3 Fill Base B m3 1,890.00 7.00
2.1.4 Fill Base A m3 2,365.40 7.00
2.2 Open Traffic 14.00
2.3 Chipseal Pavement 18.00
2.3.1 Smoothing/trimming Surface Base m2 11,827.00 4.00
2.3.2 Primecoat m2 11,827.00 4.00
2.3.3 Chipseal Double Layer m2 10,178.00 10.00
3 Realignement KM 4 56.00
3.1 Earthworks 33.00
3.1.1 Fill OB m3 2,241.25 7.00
3.1.2 Fill Pavement Boulder/Scorea m3 1,902.21 12.00
3.1.3 Fill Base B m3 448.25 7.00
3.1.4 Fill Base A m3 1,268.14 7.00
3.2 Open Traffic 14.00
3.3 Chipseal Pavement 9.00
3.3.1 Smoothing/trimming Surface Base m2 6,340.70 2.00
3.3.2 Primecoat m2 6,340.70 2.00
2.3.3 Chipseal Double Layer m2 5,446.00 5.00
4 Remediation KM 19 137.00
3.1 Earthworks 114.00
3.1.1 Pemasangan Kayu Galam batang 3,200.00 90.00
3.1.2 Fill Pavement Base B m3 1,440.00 5.00
3.1.3 Fill Pavement Base A m3 960.00 5.00
3.2 Open Traffic 14.00
3.3 Chipseal Pavement 9.00
3.3.1 Smoothing/trimming Surface Base m2 4,800.00 2.00
3.3.2 Primecoat m2 4,800.00 2.00
3.3.3 Chipseal Double Layer m2 4,200.00 5.00