You are on page 1of 62

VOLUME PEKERJAAN ARSITEKTUR SKG PANGKALAN BRANDAN

N SPESIF UNI WARE ELECTR GUARD


URAIAN OFFICE GENSET TOTAL
O IKASI T HOUSE ICAL HOUSE
1 Pas Dinding M2 435.76 262.87 559.45 257.11 52.98 1,568.16
2 Plaster M2 797.64 468.73 1,050.95 514.22 92.99 2,924.54
3 Aci M2 797.64 468.73 1,050.95 514.22 92.99 2,924.54
4 Ceramic Tile 400x400 M2 183.08 - 187.07 - - 370.14
5 Ceramic Tile 300x300 M2 - 16.00 - - 30.00 46.00
6 Floor Hardener M2 - 86.00 81.20 140.00 - 307.20
7 Smooth Plastered at Terrace M2 60.00 46.00 115.50 52.00 - 273.50
8 Plint Ceramic 400x100 M' 176.73 - 158.10 - - 334.83
9 Plint Ceramic 300x100 M' - 16.00 - - 32.50 48.50
10 Floor Ceramic Tile 200x200 M2 10.95 6.00 8.24 - 3.75 28.94
11 Wall Ceramic Tile 200x250 M2 73.87 21.85 67.94 - 6.60 170.25
12 Beton Expose M2 - - - 376.36 54.91 431.27
13 Plafond M2 270.00 36.00 425.50 - - 731.50
14 Painting M2 1,067.64 504.73 1,476.45 890.58 147.90 4,087.31
15 Bak Mandi PCS 2.00 1.00 2.00 - - 5.00
16 Closet Duduk PCS 2.00 1.00 2.00 - 1.00 6.00
17
18
19
20
21
22
SKEDUL PEKERJAAN

PROYEK
KONTRAKTOR
DATE

May-14
NO NAMA VOLUME UNIT
28 29 30 31 1 2 3 4 5 6 7 8

A DIESEL FUEL PUMP FOUNDATION


1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 7.34 M3 2 2
3 Sand Bedding 1.23 M3
4 Lean Concrete 0.62 M3
5 Pabrikasi Pembesian 391.96 KG 3
6 Install Pembesian 391.96 KG 3
7 Bekisting 11.54 M2 4
8 Cor 5.80 M3
9 Back Filling 1.33 M3 1
10 Buang Sisa Galian 6.01 M3 2
B PORTABLE WATER PUMP FOUNDATION
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 5.10 M3 2 2
3 Sand Bedding 1.04 M3
4 Lean Concrete 0.52 M3
5 Pabrikasi Pembesian 249.92 KG 3
6 Install Pembesian 249.92 KG 3
7 Bekisting 7.34 M2 4
8 Cor 3.10 M3
9 Back Filling 0.95 M3 1
10 Buang Sisa Galian 4.15 M3 2
C KO DRUM PUMP FOUNDATION
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 3.74 M3 2 2
3 Sand Bedding 0.78 M3
4 Lean Concrete 0.39 M3
5 Pabrikasi Pembesian 214.69 KG 3
6 Install Pembesian 214.69 KG 3
7 Bekisting 5.21 M2 4
8 Cor 2.82 M3
9 Back Filling 0.58 M3

386071771.xlsx_SKEDUL PBA
SKEDUL PEKERJAAN

PROYEK
KONTRAKTOR
DATE

May-14
NO NAMA VOLUME UNIT
28 29 30 31 1 2 3 4 5 6 7 8

10 Buang Sisa Galian 3.16 M3


D CONDENSATE TRANSFER PUMP FOUND
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 3.74 M3 2 2
3 Sand Bedding 0.78 M3
4 Lean Concrete 0.39 M3
5 Pabrikasi Pembesian 214.69 KG 3
6 Install Pembesian 214.69 KG 3
7 Bekisting 5.21 M2
8 Cor 2.82 M3
9 Back Filling 0.58 M3
10 Buang Sisa Galian 3.16 M3
E JOCKEY PUMP FOUNDATION
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 1.04 M3 2 2
3 Sand Bedding 0.20 M3
4 Lean Concrete 0.10 M3
5 Pabrikasi Pembesian 102.64 KG 3
6 Install Pembesian 102.64 KG
7 Bekisting 3.24 M2
8 Cor 0.84 M3
9 Back Filling 0.32 M3
10 Buang Sisa Galian 0.72 M3
F INSTRUMENT AIR RECEIVER
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 2.38 M3 2
3 Potong Tiang Pancang 2.00 PCS
4 Sand Bedding 0.48 M3
5 Lean Concrete 0.24 M3
6 Pabrikasi Pembesian 283.49 KG 3
7 Install Pembesian 283.49 KG
8 Bekisting 4.80 M2

386071771.xlsx_SKEDUL PBA
SKEDUL PEKERJAAN

PROYEK
KONTRAKTOR
DATE

May-14
NO NAMA VOLUME UNIT
28 29 30 31 1 2 3 4 5 6 7 8

9 Cor 2.50 M3
10 Back Filling 0.45 M3
11 Buang Sisa Galian 1.93 M3
G UTILITY AIR RECEIVER
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 1.78 M3
3 Potong Tiang Pancang 2.00 PCS
4 Sand Bedding 0.29 M3
5 Lean Concrete 0.14 M3
6 Pabrikasi Pembesian 176.80 KG
7 Install Pembesian 176.80 KG
8 Bekisting 4.20 M2
9 Cor 1.68 M3
10 Back Filling 0.45 M3
11 Buang Sisa Galian 1.33 M3
H DIESEL FIRE WATER PUMP
1 Marking & Pasang Bowplank 1.00 ls 2
2 Galian 5.59 M3
3 Potong Tiang Pancang 4.00 PCS
4 Sand Bedding 0.80 M3
5 Lean Concrete 0.40 M3
6 Pabrikasi Pembesian 722.25 KG
7 Install Pembesian 722.25 KG
8 Bekisting 9.12 M2
9 Cor 5.64 M3
10 Back Filling 0.99 M3
11 Buang Sisa Galian 4.60 M3
I FUEL GAS FILTER
1 Marking & Pasang Bowplank 1.00 ls
2 Galian 1.33 M3
3 Sand Bedding 0.20 M3
4 Lean Concrete 0.10 M3

386071771.xlsx_SKEDUL PBA
SKEDUL PEKERJAAN

PROYEK
KONTRAKTOR
DATE

May-14
NO NAMA VOLUME UNIT
28 29 30 31 1 2 3 4 5 6 7 8

5 Pabrikasi Pembesian 164.53 KG


6 Install Pembesian 164.53 KG
7 Bekisting 4.48 M2
8 Cor 1.00 M3
9 Back Filling 0.52 M3
10 Buang Sisa Galian 0.81 M3
J INSTRUMENT AIR COMPRESSOR
1 Marking & Pasang Bowplank 1.00 ls
2 Galian 10.74 M3
3 Sand Bedding 2.28 M3
4 Lean Concrete 1.14 M3
5 Pabrikasi Pembesian 1,074.21 KG
6 Install Pembesian 1,074.21 KG
7 Bekisting 12.24 M2
8 Cor 12.43 M3
9 Back Filling 1.11 M3
10 Buang Sisa Galian 9.64 M3
K ELECTRIC FIRE WATER PUMP
1 Marking & Pasang Bowplank 1.00 ls
2 Galian 6.39 M3
3 Sand Bedding 1.34 M3
4 Lean Concrete 0.67 M3
5 Pabrikasi Pembesian 344.42 KG
6 Install Pembesian 344.42 KG
7 Bekisting 6.42 M2
8 Cor 4.50 M3
9 Back Filling 0.77 M3
10 Buang Sisa Galian 5.62 M3
L SECURITY GUARD
1 Marking & Pasang Bowplank 1.00 ls
2 Pile Cap & Pedestal #N/A
Excavation M3

386071771.xlsx_SKEDUL PBA
SKEDUL PEKERJAAN

PROYEK
KONTRAKTOR
DATE

May-14
NO NAMA VOLUME UNIT
28 29 30 31 1 2 3 4 5 6 7 8

Sand Bedding M3
Lean Concrete M3
Install Pembesian KG
Bekisting M2
Cor M3
3 Tie Beam & Slab
Sand Bedding M3
Lean Concrete M3
Install Pembesian KG
Bekisting M2
Cor M3
4 Steel Structure Work
Erection
Roof Sheet
5 Architecture Work
Erection
Roof Sheet

JUMLAH TENAGA 2 7 9 12 16 19 21

386071771.xlsx_SKEDUL PBA
SKEDUL PEKERJAAN

PROYEK
KONTRAKTOR
DATE

May-14
NO NAMA VOLUME UNIT
28 29 30 31 1 2 3 4 5 6 7 8

386071771.xlsx_SKEDUL PBA
UL PEKERJAAN

: SKG PANGKALAN BRANDAN


: PT. WIKA
: MAY 2014

Jun-14
KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

386071771.xlsx_SKEDUL PBA
UL PEKERJAAN

: SKG PANGKALAN BRANDAN


: PT. WIKA
: MAY 2014

Jun-14
KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1
2

3
4

1
2

2
2

3
4

386071771.xlsx_SKEDUL PBA
UL PEKERJAAN

: SKG PANGKALAN BRANDAN


: PT. WIKA
: MAY 2014

Jun-14
KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1
2

2
2
2

3
3
4

1
2

2
2
2

3
3 3
4

1
2

2
2 2

386071771.xlsx_SKEDUL PBA
UL PEKERJAAN

: SKG PANGKALAN BRANDAN


: PT. WIKA
: MAY 2014

Jun-14
KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

3
3
4

1
2

2
2 2

3 3
3 3 3
4

1
2

2
2 2

3
3
4

1
2

386071771.xlsx_SKEDUL PBA
UL PEKERJAAN

: SKG PANGKALAN BRANDAN


: PT. WIKA
: MAY 2014

Jun-14
KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

24 22 22 20 20 17 9 4 3

Jakarta, Feb 2014


Dibuat Oleh:

386071771.xlsx_SKEDUL PBA
UL PEKERJAAN

: SKG PANGKALAN BRANDAN


: PT. WIKA
: MAY 2014

Jun-14
KETERANGAN
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Agung Hery K
Eng

386071771.xlsx_SKEDUL PBA
MONITORING RENCANA-REALISASI PEMAKAIAN BESI BETON
SKG PANGKALAN BRANDAN

STOK BESI SESUAI DATA GUDANG (BTG 12M')


No Tanggal KETERANGAN
8 10 13 16 19 22 TOTAL
1 - - - - - - -

JUMLAH BATANG - - - - - -
JUMLAH BERAT - - - - - - -

KEBUTUHAN BESI SESUAI DIAMETER UNTUK TIAP BANGUNAN (KG)


No URAIAN KETERANGAN
8 10 13 16 19 22 TOTAL
1 Office Building - 912 6,090 4,120 2,939 - 14,061 SLS-40-CIV-DW-003
2 Electrical Building - 1,148 12,065 4,275 5,179 - 22,666 SLS-40-CIV-DW-009
3 Warehouse Building - 524 3,926 3,473 - - 7,923 SLS-40-CIV-DW-005
4 Genset Building 97 3,228 5,005 7,351 2,887 - 18,568 SLS-40-CIV-DW-018
5 Instrument Air Selter - 206 2,569 597 - - 3,372 SLS-40-CIV-DW-011
6 Fire Water Jockey Pump Shelter - 233 2,518 597 - - 3,348 SLS-40-CIV-DW-013
7 Booster Compressor Shelter - 643 9,736 2,328 - - 12,707 SLS-40-CIV-DW-016
8 Security Guard - 1,197 946 889 - - 3,032 SLS-40-CIV-DW-007
9 Fire Water Pond - 395 2,667 73,547 - - 76,609 SLS-40-CIV-DW-025
10 Existing Control Room Modification - - 1,667 - - - 1,667 SLS-40-CIV-DW-062
11 Portable Water Storage Tank Foundation - 60 77 575 - - 712 SLS-40-CIV-DW-026
12 API Separator - - - 4,280 - - 4,280 SLS-40-CIV-DW-041
13 Pipe Rack Foundation - 677 1,968 3,778 - - 6,424 SLS-40-CIV-DW-047
14 Pipe Support Foundation - 2,218 1,034 6,968 - - 10,219 SLS-40-CIV-DW-057
15 Pipe Bridge Foundation - 39 - 810 - - 849 SLS-40-CIV-DW-035
16 Pipe Stanchion Foundation - 900 2,794 10,547 - - 14,240 SLS-40-CIV-DW-058
17 Slug Catcher Foundation - 85 138 1,050 236 - 1,509 SLS-40-CIV-DW-023
18 Condensate Drum Foundation - 62 67 417 292 - 837 SLS-40-CIV-DW-033
19 Flare KO Drum Foundation - 57 71 433 292 - 852 SLS-40-CIV-DW-046
20 Diesel Fuel Storage Tank Foundation - 55 41 448 266 - 811 SLS-40-CIV-DW-028
21 Flare Stack Foundation - 189 431 235 - - 856 SLS-40-CIV-DW-022
22 Other Vessel Equipment Foundation
23 Utility Air Receiver - 20 33 124 - - 177 SLS-40-CIV-DW-031
24 Emergency Gas Engine Generator - 146 267 - 2,439 - 2,851 SLS-40-CIV-DW-052
25 Emergency Diesel Engine Generator - 146 267 - 2,439 - 2,851 SLS-40-CIV-DW-053
26 Diesel Fire Water Pump - 38 67 - 618 - 722 SLS-40-CIV-DW-055
27 Fuel Gas Filter - 21 33 110 - - 165 SLS-40-CIV-DW-056
28 Instrument Air Compressor - 25 - 1,049 - - 1,074 SLS-40-CIV-DW-059
29 Electric Fire Water Pump - 9 335 - - - 344 SLS-40-CIV-DW-060
30 Instrument Air Receiver - 59 33 191 - - 283 SLS-40-CIV-DW-061
31 Condensate Transfer Pump - 9 206 - - - 215 SLS-40-CIV-DW-051
32 KO Drum Pump - 9 206 - - - 215 SLS-40-CIV-DW-049
33 Portable Water Pump - 9 240 - - - 250 SLS-40-CIV-DW-050
34 Diesel Fuel Pump - 29 363 - - - 392 SLS-40-CIV-DW-032
35 Jockey Pump - 10 41 51 - - 103 SLS-40-CIV-DW-054
36 Saluran - 27,085 1,973 - - - 29,058 SLS-40-CIV-DW-039
37 Indoturbin - 148 313 758 - 12,532 13,750 Data Agung Fit
38 - 148 188 1,042 - 14,323 15,700 Data Agung Fit

JUMLAH BERAT (KG) 97 40,737 58,375 130,041 17,586 26,855 273,691


JUMLAH BATANG (WASTE 10%) 23 6,058 5,137 7,554 725 826 20,323

PENDATANGAN BESI SESUAI DATA GUDANG


No Tanggal KETERANGAN
8 10 13 16 19 22 TOTAL

1 1-May-14 344 5,327 2,842 5,863 477 813 15,666 Data 30 May
2 2-May-14 - - - - - - -

TOTAL PENDATANGAN 344 5,327 2,842 5,863 477 813


JUMLAH BERAT 1,629 39,409 35,532 111,039 12,739 29,111 229,459
DEVIASI 321 (731) (2,295) (1,691) (248) (13)

WASTE BERAT
BBS NETTO 273,690.85 2.50% 7 Ton Ra Calculated by:
TOTAL PEMAKAIAN 229,458.66 -16.16% (44) Ton Ri

Agung Hery K.

386071771.xlsx_VOL BESI_05/04/2018
BOQ SALURAN DRAINASE PANGKALAN BRANDAN
DRAINAGE PROPERTIES REINFORCEMENT BAR U40 VOLUME CIVIL WORKS
JUMLA PANJA
NO TYPE SALURAN DIAM PANJA JUMLA SAND LEAN
WIDT HEIGH THICK THICK LENG JARAK H NG BERAT GALIAN
ETER NG H BEDDIN CONCRE
H T -1 -2 TH BESI BESI TOT BESI TANAH
BESI BESI BESI Y G TE
X BESI KG M3 M3 M3
1 UD-1 10 600 600 100 - 72.00 2.20 150 481 15 2,138 1,318 85.68 5.76 2.88
2 UD-1 10 600 600 100 - 55.00 2.20 150 367 15 1,632 1,006 65.45 4.40 2.20
3 BC-1 #N/A 600 600 150 250 6.00 4.10 #N/A #N/A #N/A #N/A #N/A 10.35 0.48 0.24
4 UD-1 10 600 600 100 - 135.00 2.20 150 901 15 4,007 2,470 160.65 10.80 5.40
5 UD-1 10 600 600 100 - 127.50 2.20 150 851 15 3,785 2,333 151.73 10.20 5.10
6 UD-1 10 600 600 100 - 8.50 2.20 150 57 15 253 156 10.12 0.68 0.34
7 UD-1 10 600 600 100 - 5.00 2.20 150 34 15 150 92 5.95 0.40 0.20
8 BC-1 #N/A 600 600 150 250 6.00 4.10 #N/A #N/A #N/A #N/A #N/A 10.35 0.48 0.24
9 UD-1 10 600 600 100 - 18 2.20 150 121 15 536 331 21.42 1.44 0.72
10 UD-1 10 600 600 100 - 83 2.20 150 554 15 2,464 1,519 98.77 6.64 3.32
11 UD-1 10 600 600 100 - 10 2.20 150 67 15 297 183 11.90 0.80 0.40
12 BC-1 #N/A 600 600 150 250 6 4.10 #N/A #N/A #N/A #N/A #N/A 10.35 0.48 0.24
13 UD-2 10 800 800 100 - 30 2.80 150 201 19 1,133 698 50.40 3.00 1.50
14 UD-1 10 600 600 100 - 120 2.20 150 801 15 3,562 2,196 142.80 9.60 4.80
15 UD-1 10 600 600 100 - 83 2.20 150 554 15 2,464 1,519 98.77 6.64 3.32
16 UD-1 10 600 600 100 - 20 2.20 150 134 15 595 367 23.80 1.60 0.80
17 BC-2 13 800 800 150 250 6 5.10 200 31 26 314 327 13.77 0.60 0.30
18 UD-2 10 800 800 100 - 5 2.80 150 34 19 190 117 8.40 0.50 0.25
19 UD-1 10 600 600 100 - 50 2.20 150 334 15 1,485 915 59.50 4.00 2.00
20 UD-1 10 600 600 100 - 80 2.20 150 534 15 2,375 1,464 95.20 6.40 3.20
21 UD-1 10 600 600 100 - 60 2.20 150 401 15 1,782 1,099 71.40 4.80 2.40
22 UD-1 10 600 600 100 - 80 2.20 150 534 15 2,375 1,464 95.20 6.40 3.20
23 BC-1 #N/A 600 600 150 250 6 4.10 #N/A #N/A #N/A #N/A #N/A 10.35 0.48 0.24
24 UD-2 10 800 800 100 - 70 2.80 150 467 19 2,638 1,626 117.60 7.00 3.50
25 UD-2 10 800 800 100 - 127 2.80 150 847 19 4,785 2,950 213.36 12.70 6.35
26 UD-1 10 600 600 100 - 25 2.20 150 167 15 742 458 29.75 2.00 1.00
27 UD-1 10 600 600 100 - 5 2.20 150 34 15 150 92 5.95 0.40 0.20
28 BC-1 #N/A 600 600 150 250 6 4.10 #N/A #N/A #N/A #N/A #N/A 10.35 0.48 0.24
29 UD-2 10 800 800 100 - 42 2.80 150 281 19 1,585 977 70.56 4.20 2.10
386071771.xlsx_23.DRAINAGE Calculated by @gg
05/04/2018
30 UD-1 10 600 600 100 - 25 2.20 150 167 15 742 458 29.75 2.00 1.00
31 UD-1 10 600 600 100 - 29 2.20 150 194 15 862 531 34.51 2.32 1.16
32 BC-2 13 800 800 150 250 6 5.10 200 31 26 314 327 13.77 0.60 0.30
33 UD-2 10 800 800 100 - 20 2.80 150 134 19 755 466 33.60 2.00 1.00
34 CB-1 #N/A 1,000 950 100 - 10 3.30 #N/A #N/A #N/A #N/A #N/A 21.60 1.20 0.60
RESUME VOLUME ### ### 121.5 60.7
SATUAN KG M3 M3 M3

386071771.xlsx_23.DRAINAGE Calculated by @gg


05/04/2018
N DRAINASE PANGKALAN BRANDAN BOQ SALURAN DRAINASE PANGKALA
VOLUME CIVIL WORKS
NO TYPE SALURAN BETON REMAR
K250 KS
M3
1 UD-1 14.40
2 UD-1 11.00
3 BC-1 3.24
4 UD-1 27.00
5 UD-1 25.50
6 UD-1 1.70
7 UD-1 1.00
8 BC-1 3.24
9 UD-1 3.60
10 UD-1 16.60
11 UD-1 2.00
12 BC-1 3.24
13 UD-2 7.80
14 UD-1 24.00
15 UD-1 16.60
16 UD-1 4.00
17 BC-2 4.08
18 UD-2 1.30
19 UD-1 10.00
20 UD-1 16.00
21 UD-1 12.00
22 UD-1 16.00
23 BC-1 3.24
24 UD-2 18.20
25 UD-2 33.02
26 UD-1 5.00
27 UD-1 1.00
28 BC-1 3.24
29 UD-2 10.92
386071771.xlsx_23.DRAINAGE Calculated by @gg
05/04/2018
30 UD-1 5.00
31 UD-1 5.80
32 BC-2 4.08
33 UD-2 5.20
34 CB-1 2.60
321.6 RESUME VO
M3 SA

386071771.xlsx_23.DRAINAGE Calculated by @gg


05/04/2018
BOQ EQUIPMENT FOUNDATION PANGKALAN BRANDAN
31 32 33 34 35 36 37 38
CONDEN
PORTABL DIESEL
NO ITEM OF WORK UNITS SATE KO DRUM JOCKEY
E WATER FUEL REMARK
TRANSFE PUMP PUMP
PUMP PUMP
R PUMP
SLS-40-CIV-DW-051
SLS-40-CIV-DW-049
SLS-40-CIV-DW-050
SLS-40-CIV-DW-032
SLS-40-CIV-DW-054

1 CONCRETE SPUN PILE PCS - - - - - - -


2 CONCRETE K-250 M3 2.82 2.82 3.10 5.80 0.84 - -
3 REINFORCEMENT BAR U40 KG 214.69 214.69 249.92 391.96 102.64 - -
4 FORMWORK M2 5.21 5.21 7.34 11.54 3.24 - -
5 SAND BEDDING M3 0.78 0.78 1.04 1.23 0.20 - -
6 LEAN CONCRETE M3 0.39 0.39 0.52 0.62 0.10 - -
7 SOIL EXCAVATION M3 3.74 3.74 5.10 7.34 1.04 - -
8 SOIL BACKFILLING M3 0.58 0.58 0.95 1.33 0.32 - -

386071771.xlsx_22.EQP FOUND (2) Calculated by @gg


05/04/2018
BOQ EQUIPMENT FOUNDATION PANGKALAN BRANDAN
23 24 EMERGE
25 26 27 28 29 30
EMERGE
UTILITY NCY DIESEL INSTRUM ELECTRIC INSTRUM
NCY GAS FUEL
NO ITEM OF WORK UNITS AIR DIESEL FIRE ENT AIR FIRE ENT AIR
ENGINE GAS REMARK
RECEIVE ENGINE WATER COMPRE WATER RECEIVE
GENERAT FILTER
R GENERAT PUMP SSOR PUMP R
OR SLS-40-CIV-DW-053
SLS-40-CIV-DW-031
SLS-40-CIV-DW-052 OR SLS-40-CIV-DW-055
SLS-40-CIV-DW-056
SLS-40-CIV-DW-059
SLS-40-CIV-DW-060
SLS-40-CIV-DW-061

1 CONCRETE SPUN PILE PCS 2.00 16.00 16.00 4.00 2.00 - - 2.00
2 CONCRETE K-250 M 3
1.68 37.66 37.66 5.64 1.00 12.43 4.50 2.50
3 REINFORCEMENT BAR U40 KG 176.80 2,851.48 2,851.48 722.25 164.53 1,074.21 344.42 283.49
4 FORMWORK M 2
4.20 28.08 28.08 9.12 4.48 12.24 6.42 4.80
5 SAND BEDDING M 3
0.29 3.06 3.06 0.80 0.20 2.28 1.34 0.48
6 LEAN CONCRETE M 3
0.14 1.53 1.53 0.40 0.10 1.14 0.67 0.24
7 SOIL EXCAVATION M 3
1.78 36.43 36.43 5.59 1.33 10.74 6.39 2.38
8 SOIL BACKFILLING M 3
0.45 3.50 3.50 0.99 0.52 1.11 0.77 0.45

386071771.xlsx_22.EQP FOUND Calculated by @gg


05/04/2018
BOQ FLARE STACK FOUNDATION PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 9.00 PCS
2 CONCRETE K-250 0.45 M3
3 REINFORCEMENT BAR U40 275.80 KG

B PILE CAP
1 EXCAVATION WORK 16.16 M3
2 SAND BEDDING 100MM THICK 1.06 M3
3 LEAN CONCRETE K-125 50MM THK 0.53 M3
4 FORMWORK PASANGAN BATAKO 11.70 M2
5 CONCRETE K-250 4.05 M3
6 REINFORCEMENT BAR U40 333.06 KG
7 SOIL BACKFILLING 10.52 M3

C PEDESTAL/KOLOM
1 FORMWORK 15.20 M2
2 CONCRETE K-250 3.88 M3
3 REINFORCEMENT BAR U40 246.88 KG

D LAIN-LAIN
1 MTO STEEL STRUCTURE - KG
2 ANCHOR A36, M40 4 PCS
3 STEELWORK PAINTING - M2

386071771.xlsx_21.FLARE STACK Calculated by @gg


Printed_05/04/2018
BOQ DIESEL FUEL STORAGE TANK FOUNDATION PANGKALAN
BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 2.00 PCS
2 CONCRETE K-250 0.10 M3
3 REINFORCEMENT BAR U40 38.27 KG

B PILE CAP
1 EXCAVATION WORK 6.38 M3
2 SAND BEDDING 100MM THICK 0.67 M3
3 LEAN CONCRETE K-125 50MM THK 0.34 M3
4 FORMWORK PASANGAN BATAKO 9.52 M2
5 CONCRETE K-250 3.70 M3
6 REINFORCEMENT BAR U40 382.57 KG
7 SOIL BACKFILLING 1.67 M3

C PEDESTAL/KOLOM
1 FORMWORK 2.64 M2
2 CONCRETE K-250 0.58 M3
3 REINFORCEMENT BAR U40 298.91 KG

D TIE BEAM
1 EXCAVATION WORK 1.50 M3
2 SAND BEDDING 100MM THICK 0.15 M3
3 LEAN CONCRETE K-125 50MM THK 0.08 M3
4 FORMWORK PASANGAN BATAKO 3.78 M2
5 CONCRETE K-250 0.77 M3
6 REINFORCEMENT BAR U40 90.91 KG
7 SOIL BACKFILLING 0.50 M3

386071771.xlsx_20.DIESEL FUEL Calculated by @gg


Printed_05/04/2018
BOQ FLARE KO DRUM FOUNDATION PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 4.00 PCS
2 CONCRETE K-250 0.20 M3
3 REINFORCEMENT BAR U40 76.54 KG

B PILE CAP
1 EXCAVATION WORK 5.46 M3
2 SAND BEDDING 100MM THICK 0.76 M3
3 LEAN CONCRETE K-125 50MM THK 0.38 M3
4 FORMWORK PASANGAN BATAKO 7.40 M2
5 CONCRETE K-250 3.00 M3
6 REINFORCEMENT BAR U40 361.10 KG
7 SOIL BACKFILLING 1.33 M3

C PEDESTAL/KOLOM
1 FORMWORK 3.00 M2
2 CONCRETE K-250 0.68 M3
3 REINFORCEMENT BAR U40 322.46 KG

D TIE BEAM
1 EXCAVATION WORK 1.30 M3
2 SAND BEDDING 100MM THICK 0.18 M3
3 LEAN CONCRETE K-125 50MM THK 0.09 M3
4 FORMWORK PASANGAN BATAKO 3.00 M2
5 CONCRETE K-250 0.63 M3
6 REINFORCEMENT BAR U40 87.62 KG
7 SOIL BACKFILLING 0.41 M3

386071771.xlsx_19.FLARE KO Calculated by @gg


Printed_05/04/2018
BOQ CONDENSATE DRUM FOUNDATION PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 4.00 PCS
2 CONCRETE K-250 0.20 M3
3 REINFORCEMENT BAR U40 76.54 KG

B PILE CAP
1 EXCAVATION WORK 5.46 M3
2 SAND BEDDING 100MM THICK 0.76 M3
3 LEAN CONCRETE K-125 50MM THK 0.38 M3
4 FORMWORK PASANGAN BATAKO 7.40 M2
5 CONCRETE K-250 3.00 M3
6 REINFORCEMENT BAR U40 330.80 KG
7 SOIL BACKFILLING 1.33 M3

C PEDESTAL/KOLOM
1 FORMWORK 3.00 M2
2 CONCRETE K-250 0.68 M3
3 REINFORCEMENT BAR U40 322.46 KG

D TIE BEAM
1 EXCAVATION WORK 1.69 M3
2 SAND BEDDING 100MM THICK 0.23 M3
3 LEAN CONCRETE K-125 50MM THK 0.11 M3
4 FORMWORK PASANGAN BATAKO 3.75 M2
5 CONCRETE K-250 0.81 M3
6 REINFORCEMENT BAR U40 106.75 KG
7 SOIL BACKFILLING 0.54 M3

386071771.xlsx_18.CONDENSATE DRUM Calculated by @gg


Printed_05/04/2018
BOQ SLUG CATCHER FOUNDATION PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 8.00 PCS
2 CONCRETE K-250 0.40 M3
3 REINFORCEMENT BAR U40 153.09 KG

B PILE CAP
1 EXCAVATION WORK 9.87 M3
2 SAND BEDDING 100MM THICK 1.41 M3
3 LEAN CONCRETE K-125 50MM THK 0.70 M3
4 FORMWORK PASANGAN BATAKO 10.00 M2
5 CONCRETE K-250 6.00 M3
6 REINFORCEMENT BAR U40 931.16 KG
7 SOIL BACKFILLING 1.76 M3

C PEDESTAL/KOLOM
1 FORMWORK 3.36 M2
2 CONCRETE K-250 0.58 M3
3 REINFORCEMENT BAR U40 270.61 KG

D TIE BEAM
1 EXCAVATION WORK 2.67 M3
2 SAND BEDDING 100MM THICK 0.37 M3
3 LEAN CONCRETE K-125 50MM THK 0.18 M3
4 FORMWORK PASANGAN BATAKO 4.80 M2
5 CONCRETE K-250 1.44 M3
6 REINFORCEMENT BAR U40 149.94 KG
7 SOIL BACKFILLING 0.68 M3

386071771.xlsx_17.SLUG CATCHER Calculated by @gg


Printed_05/04/2018
BOQ PIPE STANCHION PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 72.00 PCS
2 CONCRETE K-250 3.60 M3
3 REINFORCEMENT BAR U40 1,377.80 KG

B PILE CAP
1 EXCAVATION WORK 159.49 M3
2 SAND BEDDING 100MM THICK 13.57 M3
3 LEAN CONCRETE K-125 50MM THK 6.79 M3
4 FORMWORK PASANGAN BATAKO 202.80 M2
5 CONCRETE K-250 53.75 M3
6 REINFORCEMENT BAR U40 9,141.48 KG
7 SOIL BACKFILLING 85.38 M3

C PEDESTAL/KOLOM
1 FORMWORK 120.00 M2
2 CONCRETE K-250 16.47 M3
3 REINFORCEMENT BAR U40 3,720.90 KG

D LAIN-LAIN
1 MTO STEEL STRUCTURE 31,547.86 KG
2 ANCHOR A36, M24 376 PCS
3 STEELWORK PAINTING M2

386071771.xlsx_16.PIPE STANCHION 05/04/2018


BOQ PIPE BRIDGE PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE - PCS
2 CONCRETE K-250 - M3
3 REINFORCEMENT BAR U40 - KG

B PILE CAP
1 EXCAVATION WORK 9.44 M3
2 SAND BEDDING 100MM THICK 1.54 M3
3 LEAN CONCRETE K-125 50MM THK 0.77 M3
4 FORMWORK PASANGAN BATAKO 12.80 M2
5 CONCRETE K-250 4.80 M3
6 REINFORCEMENT BAR U40 654.02 KG
7 SOIL BACKFILLING 2.33 M3

C PEDESTAL/KOLOM
1 FORMWORK 6.40 M2
2 CONCRETE K-250 0.64 M3
3 REINFORCEMENT BAR U40 195.01 KG

D TIE BEAM
1 EXCAVATION WORK - M3
2 SAND BEDDING 100MM THICK - M3
3 LEAN CONCRETE K-125 50MM THK - M3
4 FORMWORK PASANGAN BATAKO - M2
5 CONCRETE K-250 - M3
6 REINFORCEMENT BAR U40 - KG
7 SOIL BACKFILLING - M3

386071771.xlsx_15.PIPE BRIDGE Calculated by @gg


Printed_05/04/2018
BOQ PIPE SUPPORT PANGKALAN BRANDAN

NO ITEM OF WORK UNITS TYPE 1 TYPE 2 TYPE 3 TYPE 4 TYPE 5 TOTAL

A CIVIL WORKS
1 CONCRETE SPUN PILE PCS 8.00 4.00 1.00 - - 13.00
2 CONCRETE K-250 M3 5.80 5.93 1.49 27.88 16.90 58.01
3 REINFORCEMENT BAR U40 KG 959.39 730.28 219.66 5,043.83 3,265.69 10,218.84
4 FORMWORK M2 32.40 23.88 6.93 150.66 79.86 293.73
5 SAND BEDDING M3 0.97 0.78 0.22 5.94 4.31 12.22
6 LEAN CONCRETE M3 0.48 0.39 0.11 2.97 2.16 6.11
7 SOIL EXCAVATION M3 16.70 13.05 3.65 81.65 59.40 174.46
8 SOIL BACKFILLING M3 6.83 4.39 1.22 26.81 19.67 58.91

B STEEL WORKS
1 MTO STEEL WORKS KG
2 PAINTING M2

386071771.xlsx_14.PIPE SUPPORT Calculated by @gg


Printed_05/04/2018
BOQ PIPE RACK PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 38.00 PCS
2 CONCRETE K-250 1.90 M3
3 REINFORCEMENT BAR U40 727.17 KG

B PILE CAP
1 EXCAVATION WORK 71.14 M3
2 SAND BEDDING 100MM THICK 4.60 M3
3 LEAN CONCRETE K-125 50MM THK 2.30 M3
4 FORMWORK PASANGAN BATAKO 88.92 M2
5 CONCRETE K-250 20.01 M3
6 REINFORCEMENT BAR U40 3,778.31 KG
7 SOIL BACKFILLING 44.23 M3

C PEDESTAL/KOLOM
1 FORMWORK 54.72 M2
2 CONCRETE K-250 6.16 M3
3 REINFORCEMENT BAR U40 1,273.29 KG

D TIE BEAM
1 EXCAVATION WORK 17.10 M3
2 SAND BEDDING 100MM THICK 3.04 M3
3 LEAN CONCRETE K-125 50MM THK 1.52 M3
4 FORMWORK PASANGAN BATAKO 47.88 M2
5 CONCRETE K-250 4.56 M3
6 REINFORCEMENT BAR U40 645.07 KG
7 SOIL BACKFILLING 7.98 M3

E LAIN-LAIN
1 MTO STEEL STRUCTURE 38,092.96 KG
2 ANCHOR A36, M22 152 PCS
3 STEELWORK PAINTING M2

386071771.xlsx_13.PIPE RACK Calculated by @gg


Printed_05/04/2018
BOQ API SEPARATOR PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A PILE
1 CONCRETE PILE Ø200 MM 8.00 PCS
2 CONCRETE K-250 - M3
3 REINFORCEMENT BAR U40 - KG

B RAFT FOUNDATION/PILE CAP


1 EXCAVATION WORK 71.08 M3
2 SAND BEDDING 100MM THICK 2.40 M3
3 LEAN CONCRETE K-125 50MM THK 1.20 M3
4 FORMWORK PASANGAN BATAKO 7.28 M2
5 CONCRETE K-250 7.66 M3
6 REINFORCEMENT BAR U40 731.41 KG
7 SOIL BACKFILLING (3,315.17) M3

C DINDING
1 FORMWORK 141.09 M2
2 CONCRETE K-250 24.69 M3
3 REINFORCEMENT BAR U40 2,991.65 KG

D TOP SLAB
1 FORMWORK 17.87 M2
2 CONCRETE K-250 3.57 M3
3 REINFORCEMENT BAR U40 556.63 KG

E LAIN-LAIN
1 WATERPROOFING MEMBRANE 117.79 M2
2 TUTUP MANHOLE 4 UNIT

386071771.xlsx_12.API SEPARATOR Calculated by @gg


Printed_05/04/2018
BOQ PORTABLE WATER STORAGE TANK PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 4.00 PCS
2 CONCRETE K-250 0.20 M3
3 REINFORCEMENT BAR U40 76.54 KG

B PILE CAP
1 EXCAVATION WORK 5.51 M3
2 SAND BEDDING 100MM THICK 0.57 M3
3 LEAN CONCRETE K-125 50MM THK 0.29 M3
4 FORMWORK PASANGAN BATAKO 9.24 M2
5 CONCRETE K-250 3.02 M3
6 REINFORCEMENT BAR U40 313.75 KG
7 SOIL BACKFILLING 1.63 M3

C PEDESTAL/KOLOM
1 FORMWORK 2.88 M2
2 CONCRETE K-250 0.48 M3
3 REINFORCEMENT BAR U40 242.58 KG

D TIE BEAM
1 EXCAVATION WORK 1.22 M3
2 SAND BEDDING 100MM THICK 0.13 M3
3 LEAN CONCRETE K-125 50MM THK 0.06 M3
4 FORMWORK PASANGAN BATAKO 3.08 M2
5 CONCRETE K-250 0.67 M3
6 REINFORCEMENT BAR U40 74.97 KG
7 SOIL BACKFILLING 0.36 M3

E LAIN-LAIN
1 MTO STEEL STRUCTURE - KG
2 ANCHOR A36, M24 16 PCS
3 STEELWORK PAINTING M2

386071771.xlsx_11.WATER STO TANK Calculated by @gg


Printed_05/04/2018
BOQ EXISTING CONTROL ROOM MODIFICATION
PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A CABLE TRENCH 27 M' 0.80 1.00


1 EXCAVATION WORK 4.86 M3
2 SAND BEDDING 100MM THICK 3.24 M3
3 LEAN CONCRETE K-125 50MM THK 1.62 M3
4 FORMWORK PASANGAN BATAKO 54.00 M2
5 FORMWORK SISI DALAM 54.00 M2
6 CONCRETE K-250, 150 MM THK 11.34 M3
7 REINFORCEMENT BAR U40, D13-200 TOP&BOTTOM 1,666.91 KG
8 CHECKER PLATE COVER, BORDES PLATE 3MM THK 10.80 M2

B ARCHITECTURE
1 PAS DINDING 21.03 3 63.09 M2
2 PLASTER 122.40 M2
3 ACI 122.40 M2
4 DOOR WINDOW 1.89 M2
D-1 0.9 2.1 1 1.89 M2
5 FLOOR FINISHED 5.85 4.665
CERAMIC TILE 400x400 27.29 M2
PLINT CERAMIC 400x100 42.06 M'
6 PLAFOND
GLASSFIBER REINFORCED CEMENT BOARD 6MM THK 27.29 M2
8 PAINTING 149.69 M2

386071771.xlsx_10.CONTROL ROOM MDF Calculated by @gg


Printed_05/04/2018
BOQ WATER POND PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 160.00 PCS
2 CONCRETE K-250 8.00 M3
3 REINFORCEMENT BAR U40 3,061.79 KG

B RAFT FOUNDATION/PILE CAP


1 EXCAVATION WORK 4,815.55 M3
2 SAND BEDDING 100MM THICK 157.08 M3
3 LEAN CONCRETE K-125 50MM THK 78.54 M3
4 FORMWORK PASANGAN BATAKO 64.16 M2
5 CONCRETE K-250 621.89 M3
6 REINFORCEMENT BAR U40 49,517.44 KG
7 SOIL BACKFILLING 583.05 M3

C DINDING
1 FORMWORK 1,274.40 M2
2 CONCRETE K-250 254.88 M3
3 REINFORCEMENT BAR U40 24,029.52 KG

D LAIN-LAIN
1 WATERPROOFING MEMBRANE 508.50 M2
2 TANGGA INSPEKSI 2 UNIT

386071771.xlsx_9.WATER POND Calculated by @gg


Printed_05/04/2018
BOQ SECURITY GUARD PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 4.00 PCS
2 CONCRETE K-250 0.20 M3
3 REINFORCEMENT BAR U40 76.54 KG

B PILE CAP
1 EXCAVATION WORK 7.49 M3
2 SAND BEDDING 100MM THICK 0.48 M3
3 LEAN CONCRETE K-125 50MM THK 0.24 M3
4 FORMWORK PASANGAN BATAKO 9.36 M2
5 CONCRETE K-250 2.11 M3
6 REINFORCEMENT BAR U40 397.72 KG
7 SOIL BACKFILLING 4.66 M3

C PEDESTAL/KOLOM
1 FORMWORK 12.70 M2
2 CONCRETE K-250 0.64 M3
3 REINFORCEMENT BAR U40 180.17 KG

D TIE BEAM
1 EXCAVATION WORK 3.92 M3
2 SAND BEDDING 100MM THICK 0.76 M3
3 LEAN CONCRETE K-125 50MM THK 0.38 M3
4 FORMWORK PASANGAN BATAKO 10.95 M2
5 CONCRETE K-250 0.82 M3
6 REINFORCEMENT BAR U40 247.63 KG
7 SOIL BACKFILLING 1.96 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 3.38 M3
2 LEAN CONCRETE K-125 50MM THK 1.69 M3
3 CONCRETE K-250 5.06 M3
4 REINFORCEMENT BAR U40 849.97 KG

F ROOF BEAM
1 FORMWORK 13.75 M2

Calculated by @gg
386071771.xlsx_8.GUARD Printed_05/04/2018
BOQ SECURITY GUARD PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

2 CONCRETE K-250 1.03 M3


3 REINFORCEMENT BAR U40 263.44 KG

G ROOF SLAB
1 FORMWORK 41.16 M2
2 CONCRETE K-250 3.61 M3
3 REINFORCEMENT BAR U40 1,016.79 KG

H ARCHITECTURE
1 PAS DINDING 14 5.5 52.98 M2
2 PLASTER 92.99 M2
3 ACI 92.99 M2
4 DOOR WINDOW 3.19 M2
D-01 2.1 0.75 1 1.58 M2
T-01 0.5 0.7 1 0.35 M2
T-02 1.8 0.7 1 1.26 M2
5 FLOOR FINISHED
CERAMIC TILE 300x300 30.00 M2
PLINT CERAMIC 300x100 32.50 M'
6 TOILET
FLOOR CERAMIC TILE 200x200 3.75 M2
WALL CERAMIC TILE 200x250 6.60 M2
WASTAFEL 1.00 UNIT
CLOSET DUDUK 1.00 UNIT
7 BETON EXPOSE 54.91 M2
8 PAINTING 147.90 M2

I LAIN-LAIN
1 ROOF DRAIN 4" GALVANIZED STEEL 2.00 PCS
2 DOWNSPOUT PVC 4" 2.00 PCS
3 WATERPROOFING ROOFDECK (MEMBRANE) 36.14 M2

Calculated by @gg
386071771.xlsx_8.GUARD Printed_05/04/2018
BOQ BOOSTER COMPRESSOR SHELTER PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 25.00 PCS
2 CONCRETE K-250 1.25 M3
3 REINFORCEMENT BAR U40 478.40 KG

B PILE CAP
1 EXCAVATION WORK 43.68 M3
2 SAND BEDDING 100MM THICK 2.92 M3
3 LEAN CONCRETE K-125 50MM THK 1.46 M3
4 FORMWORK PASANGAN BATAKO 48.10 M2
5 CONCRETE K-250 13.75 M3
6 REINFORCEMENT BAR U40 2,327.90 KG
7 SOIL BACKFILLING 25.56 M3

C PEDESTAL/KOLOM
1 FORMWORK 21.60 M2
2 CONCRETE K-250 2.43 M3
3 REINFORCEMENT BAR U40 502.62 KG

D TIE BEAM
1 EXCAVATION WORK 33.28 M3
2 SAND BEDDING 100MM THICK 4.84 M3
3 LEAN CONCRETE K-125 50MM THK 2.42 M3
4 FORMWORK PASANGAN BATAKO 96.96 M2
5 CONCRETE K-250 9.68 M3
6 REINFORCEMENT BAR U40 1,279.49 KG
7 SOIL BACKFILLING 16.34 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 36.40 M3
2 LEAN CONCRETE K-125 50MM THK 18.20 M3
3 CONCRETE K-250 54.60 M3
4 REINFORCEMENT BAR U40 8,118.95 KG

F ROOF
1 MTO STEEL STRUCTURE 36,876.63 KG
2 PURLIN C100x50x5x7.5 527.00 M'
3 BRACING Ø10 164.12 M'
4 TURN BUCKLE 16.00 PCS
5 SAGROD Ø12 272.43 M'
6 ROOF SHEET ZINCALUMN 0.45 THK INCL INSULATION 527.83 M2

Calculated by @gg
386071771.xlsx_7.BOOSTER Printed_05/04/2018
BOQ BOOSTER COMPRESSOR SHELTER PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

7 ROOF DRAIN 4" GALVANIZED STEEL 10 PCS


8 GUTTER ZINCALUMN 0.45 MM THK 62.00 M'
9 DOWNSPOUT PVC 6" 125.00 M'
10 LISPLANK 500MM HEIGHT 96.05 M'

G LAIN-LAIN
1 WALL CLADDING 2.2 28.6 13.6 2.8 223.76 M2
2 ELECTRICAL FOR ALL ROOM 1 LS
3 ANCHOR A36, M24 60 PCS
4 STEELWORK PAINTING

Calculated by @gg
386071771.xlsx_7.BOOSTER Printed_05/04/2018
BOQ FIRE WATER JOCKEY PUMP SHELTER

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 6.00 PCS
2 CONCRETE K-250 0.30 M3
3 REINFORCEMENT BAR U40 114.82 KG

B PILE CAP
1 EXCAVATION WORK 11.23 M3
2 SAND BEDDING 100MM THICK 0.73 M3
3 LEAN CONCRETE K-125 50MM THK 0.36 M3
4 FORMWORK PASANGAN BATAKO 14.04 M2
5 CONCRETE K-250 3.16 M3
6 REINFORCEMENT BAR U40 596.57 KG
7 SOIL BACKFILLING 6.98 M3

C PEDESTAL/KOLOM
1 FORMWORK 8.64 M2
2 CONCRETE K-250 0.97 M3
3 REINFORCEMENT BAR U40 201.05 KG

D TIE BEAM
1 EXCAVATION WORK 12.54 M3
2 SAND BEDDING 100MM THICK 1.90 M3
3 LEAN CONCRETE K-125 50MM THK 0.95 M3
4 FORMWORK PASANGAN BATAKO 30.64 M2
5 CONCRETE K-250 4.56 M3
6 REINFORCEMENT BAR U40 434.91 KG
7 SOIL BACKFILLING 5.13 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 8.40 M3
2 LEAN CONCRETE K-125 50MM THK 4.20 M3
3 CONCRETE K-250 12.60 M3
4 REINFORCEMENT BAR U40 2,000.17 KG

F ROOF
1 MTO STEEL STRUCTURE 2,851.72 KG
2 PURLIN C100x50x5x7.5 196 196.00 M'
3 BRACING Ø10 137.54 M'
4 TURN BUCKLE 20.00 PCS
5 SAGROD Ø12 134.09 M'
6 ROOF SHEET ZINCALUMN 0.45 THK INCL INSULATION 134.09 M2

Calculated by @gg
386071771.xlsx_6.FIRE WATER Printed_05/04/2018
BOQ FIRE WATER JOCKEY PUMP SHELTER

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

7 ROOF DRAIN 4" GALVANIZED STEEL 6 PCS


8 GUTTER ZINCALUMN 0.45 MM THK 28.00 M'
9 DOWNSPOUT PVC 6" 39.00 M'
10 LISPLANK 500MM HEIGHT 47.16 M'

G LAIN-LAIN
1 WALL CLADDING 2.5 12.5 7.6 1.3 110.38 M2

Calculated by @gg
386071771.xlsx_6.FIRE WATER Printed_05/04/2018
BOQ INSTRUMENT AIR SHELTER PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 6.00 PCS
2 CONCRETE K-250 0.30 M3
3 REINFORCEMENT BAR U40 114.82 KG

B PILE CAP
1 EXCAVATION WORK 9.94 M3
2 SAND BEDDING 100MM THICK 0.73 M3
3 LEAN CONCRETE K-125 50MM THK 0.36 M3
4 FORMWORK PASANGAN BATAKO 14.04 M2
5 CONCRETE K-250 3.16 M3
6 REINFORCEMENT BAR U40 596.57 KG
7 SOIL BACKFILLING 5.69 M3

C PEDESTAL/KOLOM
1 FORMWORK 7.92 M2
2 CONCRETE K-250 1.19 M3
3 REINFORCEMENT BAR U40 251.93 KG

D TIE BEAM
1 EXCAVATION WORK 8.25 M3
2 SAND BEDDING 100MM THICK 1.20 M3
3 LEAN CONCRETE K-125 50MM THK 0.60 M3
4 FORMWORK PASANGAN BATAKO 24.16 M2
5 CONCRETE K-250 2.40 M3
6 REINFORCEMENT BAR U40 325.25 KG
7 SOIL BACKFILLING 4.05 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 8.80 M3
2 LEAN CONCRETE K-125 50MM THK 4.40 M3
3 CONCRETE K-250 13.20 M3
4 REINFORCEMENT BAR U40 2,083.52 KG

F ROOF
1 MTO STEEL STRUCTURE 2,432.90 KG
2 PURLIN C100x50x5x7.5 110.00 M'
3 BRACING Ø10 46.04 M'
4 TURN BUCKLE 8.00 PCS
5 SAGROD Ø12 85.13 M'
6 ROOF SHEET ZINCALUMN 0.45 THK INCL INSULATION 93.65 M2

Calculated by @gg
386071771.xlsx_5.INS AIR SHELTER Printed_05/04/2018
BOQ INSTRUMENT AIR SHELTER PANGKALAN BRANDAN

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

7 ROOF DRAIN 4" GALVANIZED STEEL 4 PCS


8 GUTTER ZINCALUMN 0.45 MM THK 22.00 M'
9 DOWNSPOUT PVC 6" 26.00 M'
10 LISPLANK 500MM HEIGHT 39.03 M'

G LAIN-LAIN
1 WALL CLADDING 2 9.6 6.6 1.1 72.06 M2
2 ELECTRICAL FOR ALL ROOM 1 LS
3 ANCHOR A36, M24 24 PCS
4 STEELWORK PAINTING

Calculated by @gg
386071771.xlsx_5.INS AIR SHELTER Printed_05/04/2018
BOQ GENSET BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 18.00 PCS
2 CONCRETE K-250 0.90 M3
3 REINFORCEMENT BAR U40 344.45 KG

B PILE CAP
1 EXCAVATION WORK 27.32 M3
2 SAND BEDDING 100MM THICK 2.08 M3
3 LEAN CONCRETE K-125 50MM THK 1.04 M3
4 FORMWORK PASANGAN BATAKO 32.76 M2
5 CONCRETE K-250 10.00 M3
6 REINFORCEMENT BAR U40 1,647.68 KG
7 SOIL BACKFILLING 14.20 M3

C PEDESTAL/KOLOM
1 FORMWORK 82.53 M2
2 CONCRETE K-250 7.22 M3
3 REINFORCEMENT BAR U40 1,623.74 KG

D TIE BEAM
1 EXCAVATION WORK 19.14 M3
2 SAND BEDDING 100MM THICK 2.90 M3
3 LEAN CONCRETE K-125 50MM THK 1.45 M3
4 FORMWORK PASANGAN BATAKO 46.64 M2
5 CONCRETE K-250 6.96 M3
6 REINFORCEMENT BAR U40 1,621.45 KG
7 SOIL BACKFILLING 7.83 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 19.20 M3
2 LEAN CONCRETE K-125 50MM THK 9.60 M3
3 CONCRETE K-250 28.80 M3
4 REINFORCEMENT BAR U40 4,366.92 KG

F ROOF BEAM (INCLUDE LINTEL BEAM)


1 FORMWORK 143.20 M2
2 CONCRETE K-250 18.20 M3

386071771.xlsx_4.GENSET Calculated by @gg


Printed_05/04/2018
BOQ GENSET BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

3 REINFORCEMENT BAR U40 2,804.96 KG

G ROOF SLAB
1 FORMWORK 233.16 M2
2 CONCRETE K-250 32.70 M3
3 REINFORCEMENT BAR U40 1,792.17 KG

H ARCHITECTURE
1 PAS DINDING 48 6 257.11 M2
2 PLASTER 514.22 M2
3 ACI 514.22 M2
4 DOOR WINDOW 30.89 M2
D-01 3 3.5 2 21.00 M2
D-02 0.9 2.1 1 1.89 M2
W-01 2 0.5 8 8.00 M2
5 FLOOR FINISHED
FLOOR HARDENER 140.00 M2
SMOOTH PLASTERED AT TERRACE 52.00 M2
6 BETON EXPOSE 376.36 M2
7 PAINTING 890.58 M2

I LAIN-LAIN
1 ROOF DRAIN 4" GALVANIZED STEEL 4.00 PCS
2 DOWNSPOUT PVC 6" 32.00 M'
3 WATERPROOFING ROOFDECK (MEMBRANE) 56.80 M2

386071771.xlsx_4.GENSET Calculated by @gg


Printed_05/04/2018
BOQ WAREHOUSE & WORKSHOP BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 12.00 PCS
2 CONCRETE K-250 0.60 M3
3 REINFORCEMENT BAR U40 229.63 KG

B PILE CAP
1 EXCAVATION WORK 19.87 M3
2 SAND BEDDING 100MM THICK 1.45 M3
3 LEAN CONCRETE K-125 50MM THK 0.73 M3
4 FORMWORK PASANGAN BATAKO 28.08 M2
5 CONCRETE K-250 6.32 M3
6 REINFORCEMENT BAR U40 1,193.15 KG
7 SOIL BACKFILLING 11.38 M3

C PEDESTAL/KOLOM
1 FORMWORK 15.84 M2
2 CONCRETE K-250 2.38 M3
3 REINFORCEMENT BAR U40 717.36 KG

D TIE BEAM
1 EXCAVATION WORK 25.58 M3
2 SAND BEDDING 100MM THICK 3.88 M3
3 LEAN CONCRETE K-125 50MM THK 1.94 M3
4 FORMWORK PASANGAN BATAKO 62.24 M2
5 CONCRETE K-250 9.30 M3
6 REINFORCEMENT BAR U40 2,246.68 KG
7 SOIL BACKFILLING 10.46 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 15.40 M3
2 LEAN CONCRETE K-125 50MM THK 7.70 M3
3 CONCRETE K-250 23.10 M3
4 REINFORCEMENT BAR U40 3,536.32 KG

F ROOF
1 MTO STEEL STRUCTURE 3,328.70 KG
2 PURLIN C100x50x5x7.5 168.00 M'
3 BRACING Ø10 76.89 M'
4 TURN BUCKLE 12.00 PCS
5 SAGROD Ø12 35.12 M'
6 ROOF SHEET ZINCALUMN 0.45 THK INCL INSULATION 163.88 M2
7 ROOF DRAIN 4" GALVANIZED STEEL 8 PCS
386071771.xlsx_3.WAREHOUSE Calculated by @gg
Printed_05/04/2018
BOQ WAREHOUSE & WORKSHOP BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

8 GUTTER ZINCALUMN 0.45 MM THK 28.00 M'


9 DOWNSPOUT PVC 6" 52.00 M'
10 LISPLANK 500MM HEIGHT 51.41 M'

G ARCHITECTURE
1 PAS DINDING 52.5 4.3 262.87 M2
2 PLASTER 468.73 M2
3 ACI 468.73 M2
4 DOOR WINDOW 17.58 M2
D-1 0.97 2.15 1 2.09 M2
D-2 1.8 3 1 5.40 M2
D-3 0.78 2.15 1 1.68 M2
D-4 0.9 2.6 1 2.34 M2
BV-1 0.85 0.5 2 0.85 M2
W-1 0.7 1.6 1 1.12 M2
AV-1 3.7 0.6 1 2.22 M2 Alumn Vent
AV-2 1.45 0.65 2 1.89 M2 Alumn Vent
5 FLOOR FINISHED
CERAMIC TILE 300x300 16.00 M2
SMOOTH PLASTERED AT TERRACE 46.00 M2
PLINT CERAMIC 300x100 16.00 M'
FLOOR HARDENER 86.00 M2

6 TOILET
FLOOR CERAMIC TILE 200x200 6.00 M2
WALL CERAMIC TILE 200x250 21.85 M2
BAK MANDI 1 UNIT
CLOSET DUDUK 1 UNIT
7 PLAFOND
PLAFOND 36.00 M2
8 PAINTING 504.73 M2

H LAIN-LAIN
1 WALL CLADDING 1.2 8.3 9.6 1.64 39.31 M2
2 AC CENTRAL FOR ALL ROOM 1 LS
3 ELECTRICAL FOR ALL ROOM 1 LS
4 ANCHOR A36, M24 40 PCS
5 STEELWORK PAINTING

386071771.xlsx_3.WAREHOUSE Calculated by @gg


Printed_05/04/2018
BOQ ELECTRICAL BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 30.00 PCS
2 CONCRETE K-250 1.50 M3
3 REINFORCEMENT BAR U40 574.08 KG

B PILE CAP
1 EXCAVATION WORK 61.47 M3
2 SAND BEDDING 100MM THICK 3.59 M3
3 LEAN CONCRETE K-125 50MM THK 1.80 M3
4 FORMWORK PASANGAN BATAKO 55.12 M2
5 CONCRETE K-250 17.43 M3
6 REINFORCEMENT BAR U40 2,830.73 KG
7 SOIL BACKFILLING 38.65 M3

C PEDESTAL/KOLOM
1 FORMWORK 28.80 M2
2 CONCRETE K-250 3.24 M3
3 REINFORCEMENT BAR U40 593.89 KG

D TIE BEAM
1 EXCAVATION WORK 71.39 M3
2 SAND BEDDING 100MM THICK 9.66 M3
3 LEAN CONCRETE K-125 50MM THK 4.83 M3
4 FORMWORK PASANGAN BATAKO 180.54 M2
5 CONCRETE K-250 27.00 M3
6 REINFORCEMENT BAR U40 7,536.90 KG
7 SOIL BACKFILLING 29.90 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 42.55 M3
2 LEAN CONCRETE K-125 50MM THK 21.28 M3
3 CONCRETE K-250 63.83 M3
4 REINFORCEMENT BAR U40 9,381.88 KG

F CABLE TRENCH
1 EXCAVATION WORK 40.20 M3
2 SAND BEDDING 100MM THICK 3.35 M3
3 LEAN CONCRETE K-125 50MM THK 1.68 M3
4 FORMWORK PASANGAN BATAKO 79.30 M2
5 FORMWORK SISI DALAM (PLYWOOD) 79.30 M2
6 CONCRETE K-250 11.90 M3
7 REINFORCEMENT BAR U40 1,748.49 KG
8 CHECKER PLATE COVER 33.50 M2

386071771.xlsx_2.ELECTRICAL Calculated by @gg


Printed_05/04/2018
BOQ ELECTRICAL BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

G ROOF
1 MTO STEEL STRUCTURE 6,708.19 KG
2 PURLIN C100x50x5x7.5 460.00 M'
3 BRACING Ø10 - M'
4 TURN BUCKLE - PCS
5 SAGROD Ø12 157.50 M'
6 ROOF SHEET ZINCALUMN 0.45 THK INCL INSULATION 452.81 M2
7 ROOF DRAIN 4" GALVANIZED STEEL 8 PCS
8 GUTTER ZINCALUMN 0.45 MM THK 46.00 M'
9 DOWNSPOUT PVC 6" 60.80 M'
10 LISPLANK 500MM HEIGHT 85.37 M'

H ARCHITECTURE
1 PAS DINDING 138.775 4.3 559.45 M2
2 PLASTER 1,050.95 M2
3 ACI 1,050.95 M2
4 DOOR WINDOW 74.72 M2
D-1 0.97 2.6 4 10.09 M2
D-2 1.72 2.7 3 13.93 M2
D-3 0.78 2.15 2 3.35 M2
D-4 1.07 2.6 1 2.78 M2
D-5 2.57 3.05 1 7.84 M3
BV-1 0.85 0.5 1 0.43 M2
BV-2 1.25 0.5 3 1.88 M2
BV-3 0.85 0.5 1 0.43 M2
W-2 1.25 1.6 17 34.00 M2
5 FLOOR FINISHED
CERAMIC TILE 400x400 187.07 M2
SMOOTH PLASTERED AT TERRACE 115.50 M2
PLINT CERAMIC 400x100 158.10 M'
FLOOR HARDENER 81.20 M2

6 TOILET
FLOOR CERAMIC TILE 200x200 8.24 M2
WALL CERAMIC TILE 200x250 67.94 M2
BAK MANDI 2 UNIT
CLOSET DUDUK 2 UNIT
7 PLAFOND
PLAFOND 425.50 M2
8 PAINTING 1,476.45 M2

I LAIN-LAIN
1 AC CENTRAL FOR ALL ROOM 1 LS
2 ELECTRICAL FOR ALL ROOM 1 LS

386071771.xlsx_2.ELECTRICAL Calculated by @gg


Printed_05/04/2018
BOQ ELECTRICAL BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

3 ANCHOR A36, M22 32 PCS


4 STEELWORK PAINTING

386071771.xlsx_2.ELECTRICAL Calculated by @gg


Printed_05/04/2018
BOQ OFFICE BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

A SPUN PILE
1 CONCRETE SPUN PILE 24.00 PCS
2 CONCRETE K-250 1.20 M3
3 REINFORCEMENT BAR U40 459.27 KG

B PILE CAP
1 EXCAVATION WORK 47.52 M3
2 SAND BEDDING 100MM THICK 2.77 M3
3 LEAN CONCRETE K-125 50MM THK 1.39 M3
4 FORMWORK PASANGAN BATAKO 43.68 M2
5 CONCRETE K-250 13.34 M3
6 REINFORCEMENT BAR U40 2,196.91 KG
7 SOIL BACKFILLING 30.02 M3

C PEDESTAL/KOLOM
1 FORMWORK 21.60 M2
2 CONCRETE K-250 2.43 M3
3 REINFORCEMENT BAR U40 445.42 KG

D TIE BEAM
1 EXCAVATION WORK 57.17 M3
2 SAND BEDDING 100MM THICK 7.81 M3
3 LEAN CONCRETE K-125 50MM THK 3.90 M3
4 FORMWORK PASANGAN BATAKO 144.28 M2
5 CONCRETE K-250 21.56 M3
6 REINFORCEMENT BAR U40 5,594.75 KG
7 SOIL BACKFILLING 23.90 M3

E SLAB ON GRADE
1 SAND BEDDING 100MM THICK 23.80 M3
2 LEAN CONCRETE K-125 50MM THK 11.90 M3
3 CONCRETE K-250 35.70 M3
4 REINFORCEMENT BAR U40 5,364.21 KG

F ROOF
1 MTO STEEL STRUCTURE 4,226.94 KG
2 PURLIN C100x50x5x7.5 324 324.00 M'
3 BRACING Ø10 99.74 M'
4 TURN BUCKLE 12.00 PCS
5 SAGROD Ø12 90.00 M'
6 ROOF SHEET ZINCALUMN 0.45 THK INCL INSULATION 287.33 M2
7 ROOF DRAIN 4" GALVANIZED STEEL 8 PCS
386071771.xlsx_1.OFFICE Calculated by @gg
Printed_05/04/2018
BOQ OFFICE BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

8 GUTTER ZINCALUMN 0.45 MM THK 36.00 M'


9 DOWNSPOUT PVC 6" 48.00 M'
10 LISPLANK 500MM HEIGHT 67.93 M'

G ARCHITECTURE
1 PAS DINDING 116.4 4 435.76 M2
2 PLASTER 797.64 M2
3 ACI 797.64 M2
4 DOOR WINDOW 53.85 M2
D-1 0.97 2.6 5 12.61 M2
D-2 1.72 2.7 3 13.93 M2
D-3 0.78 2.15 2 3.35 M2
D-4 0.9 2.6 1 2.34 M2
BV-2 1.25 0.5 1 0.63 M2
W-1 0.645 1.6 3 3.10 M2
W-2 1.25 1.6 3 6.00 M2
W-2A 1.25 1.6 2 4.00 M2
W-4 2.465 1.6 2 7.89 M2
5 FLOOR FINISHED
CERAMIC TILE 400x400 183.08 M2
SMOOTH PLASTERED AT TERRACE 60.00 M2
PLINT CERAMIC 400x100 176.73 M'
6 TOILET/PANTRY/TEMPAT WUDHU
FLOOR CERAMIC TILE 200x200 6.00 M2
WALL CERAMIC TILE 200x250 47.05 M2
BAK MANDI 2 UNIT
CLOSET DUDUK 2 UNIT
FLOOR CERAMIC TILE 200x200 1.80 M2
WALL CERAMIC TILE 200x250 6.30 M2
KITCHEN SINK (INCLUDE INSTALASI) 1 UNIT
FAUCET (INCLUDE INSTALASI) 2 PCS
FLOOR CERAMIC TILE 200x200 3.15 M2
WALL CERAMIC TILE 200x250 20.52 M2
FAUCET (INCLUDE INSTALASI) 2 PCS
7 PLAFOND
PLAFOND 270.00 M2
8 PAINTING 1,067.64 M2

H LAIN-LAIN
1 BACKDROP RECEPTIONIST 7M WIDTH, 3.6M HEIGHT 1 LS
2 AC CENTRAL FOR ALL ROOM 1 LS
3 ELECTRICAL FOR ALL ROOM 1 LS
386071771.xlsx_1.OFFICE Calculated by @gg
Printed_05/04/2018
BOQ OFFICE BUILDING

NO ITEM OF WORK QTY UNITS UNIT PRICE TOTAL

386071771.xlsx_1.OFFICE Calculated by @gg


Printed_05/04/2018
Rekapitulasi MTO Steel Structure Pangkalan Brandan

No Building Type PIC No CL No DW Weight (kg)

1 Office/Administration Building Building EHS 001 002, 003 4,226.94


2 Electrical Building Building EHS 002 008,009 6,708.19
3 Warehouse & Workshop Building Building DAA 003 004,005 3,328.70
4 Genset building Building DAA 004 018,019 -
5 Instrument Air Shelter Shelter DAA 005 010,011 2,432.90
6 Fire Water Pumps Shelter Shelter EHS 006 012,013 2,851.72
7 Booster Compressor Shelter Shelter EHS 007 015,016,017 36,876.63
8 Security/Guard Post Building EHS 008 006,007 -
9 Potable Water Storage Tank Tower Tower BEP 019 026,027 312.21
10 Pipe Rack Steel str. EHS 026 047,048 38,092.96
11 Pipe Supports Steel str. EHS 027 057 ?
12 Pipe Stachion Steel str. EHS 038 058,061 31,547.86
13 Pipe Bridge (2 unit) Steel str. EHS 028 035 3,964.73
Total 130,342.84
B.3.5 Procurement & Construction of Civil SKG Pang
Jasa Perancangan, Pengadaan dan Konstruksi Pembangunan SKG Rantau Panjang dan

Volume
Item Description
a

Civil works, foundation(1), upper structure(2), fabrication, flooring,


4 Office/Administration Building roofing, interior, architecture, plumbing, sanitary and finishing, 1
as specify on drawing and specification

4.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 28

kolom dan rafter dari baja profil (A 36),dinding dari pasangan


bata, atap dari bahan zincalume 0.45 mm, jumlah lantai = 1
office building lantai. Tinggi bangunan = 4 m (sampe nok 6.43 m ), plafond : 180.00
glass fiber reinforced cement board 6 mm thk - frame,
dilengkapi dengan AC central dan plumbing.

Civil works, foundation(1), upper structure(2), fabrication,


5 Electrical Building flooring, roofing, interior, architecture, plumbing, sanitary and 1
finishing, as specify on drawing and specification
5.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 64

kolom dan rafter dari baja profil (A 36),dinding dari pasangan


bata, atap dari bahan zincalume 0.45 mm, jumlah lantai = 1
Electrical building lantai. Tinggi bangunan = 4.6 m (sampe nok 7.4 m ), plafond : 279.00
glass fiber reinforced cement board 6 mm thk - frame,
dilengkapi dengan AC central dan plumbing.

Civil works, foundation(1), upper structure(2), fabrication,


6 Warehouse & Workshop Building flooring, roofing, interior, architecture, plumbing, sanitary and 1
finishing, as specify on drawing and specification

6.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 28

kolom dan rafter dari baja profil (A 36),dinding dari pasangan


bata, atap dari bahan zincalume 0.45 mm, jumlah lantai = 1
lantai. Tinggi bangunan = 4.1 m (sampe nok 5.375 m ), plafond
workshop dan werehouse 108.00
: glass fiber reinforced cement board 6 mm thk - frame untuk
office dan equipment room, dilengkapi dengan aluminium
louver, jendela dan plumbing.

Civil works, foundation(1) (shelter, machine, equipment), upper


7 Genset Shelter structure(2), fabrication, flooring, roofing, architecture and 1
finishing, as specify on drawing and specification

7.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 24

kolom dan rafter dari baja profil (A 36),dinding setengah


terbuka, dimana tinggi yg terbuka 2.6m. Dinding (yang tertutup)
genset shelter dan atap dari bahan zincalume 0.45 mm. Tinggi bangunan = 54.00
4.5 m (sampe nok 6.12 m ) dilengkapi dgn plumbing (gutter
dan drainase)
Civil works, foundation(1) (shelter, machine, equipment), upper
8 Instrument Air Shelter structure(2), fabrication, flooring, roofing, architecture and 1
finishing, as specify on drawing and specification
8.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 24
B.3.5 Procurement & Construction of Civil SKG Pang
Jasa Perancangan, Pengadaan dan Konstruksi Pembangunan SKG Rantau Panjang dan

Volume
Item Description
a

kolom dan rafter dari baja profil (A 36),dinding setengah


terbuka, dimana tinggi yg terbuka 2.8m. Dinding (yang tertutup)
Instrumen air shelter dan atap dari bahan zincalume 0.45 mm. Tinggi bangunan = 54.00
4.5 m (sampe nok 6.12 m ) dilengkapi dgn plumbing (gutter
dan drainase)
Civil works, foundation(1) (shelter, machine, equipment), upper
9 Fire Water Pumps Shelter structure(2), fabrication, flooring, roofing, architecture and 1
finishing, as specify on drawing and specification
9.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 12

kolom dan rafter dari baja profil (A 36),dinding setengah


terbuka, dimana tinggi yg terbukadr ground 2.6m. Dinding
Fire water pump shelter (yang tertutup) dan atap dari bahan zincalume 0.45 mm. Tinggi 48.00
bangunan = 4.85 m (sampe nok 5.347 m ) dilengkapi dgn
plumbing (gutter dan drainase)

Civil works, foundation(1) (shelter, machine, equipment), upper


10 Booster Compressor Shelter structure(2), fabrication, flooring, roofing, architecture and 1
finishing

10.1. Conc Spun Pile D 300, type B, length = 10 m/pcs 16

B. STRUCTURE,
ARCHITECTURAL AND 316.8
PLUMBING
Civil works, foundation(1), upper structure(2), flooring, roofing,
11 Security/Guard Post interior, architecture, plumbing, sanitary and finishing, as specify 1
on drawing and specification
11.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 8

rumah dari beton (balok dan kolom) dgn atap dak. Tinggi
11.15 structure 12.75
struktur 3.7 m, tembok dari dinding bata, didalam terdapat toilet.

Civil works, foundation(1), water proofing, stair, railling, finishing


12 Fire Water Pond 1
and accecories, as specify on drawing and specification

Civil works, foundation(1) and finishing, as specify on drawing


13 Flare Stack Foundation 1
and specification

13.1. Conc Spun Pile D 300, type B, length = 10 m/pcs 32

steel structure A 572, coating to resist heat 8114.05


Civil works, foundation(1) and finishing, as specify on drawing
14 Slug Catcher Foundation 1
and specification
14.1. Conc Spun Pile D 300, type B, length = 10 m/pcs 12
Condensate Drum and Pump Civil works, foundation(1) and finishing, as specify on drawing
15 1
Foundation and specification

15.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 12

Diesel Fuel Storage Tank Civil works, foundation(1) and finishing, as specify on drawing
16 1
Foundation and specification
B.3.5 Procurement & Construction of Civil SKG Pang
Jasa Perancangan, Pengadaan dan Konstruksi Pembangunan SKG Rantau Panjang dan

Volume
Item Description
a

16.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 6

Civil works, foundation(1) and finishing, as specify on drawing


17 Diesel Fuel Daily Tank Foundation 1
and specification

17.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 4

Civil works, foundation(1), upper structure(2), fabrication,


Potable Water Storage Tank Tower
18 accecories and finishing, as specify on drawing and 1
and Foundation
specification

18.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 6

A 36, Paint : primary paint = zinc rich primer 70 micron, 2nd =


steel structure 577.55
epoxy resin 120 micron, epoxy resin 50 micron
B.3.5 Procurement & Construction of Civil SKG Pang
Jasa Perancangan, Pengadaan dan Konstruksi Pembangunan SKG Rantau Panjang dan

Volume
Item Description
a

Civil works, foundation(1) and finishing, as specify on drawing


19 Diesel Fuel Pump Foundation 1
and specification, etc.

19.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 4

steel structure without cladding/wall. roofing is zincalume thk


B.1 Small shelter without cladding 6.00
0.45 mm and heigh of structure = 2m
Civil works, foundation(1) and finishing, as specify on drawing
20 Diesel Fuel Filter Foundation 1
and specification, etc.

20.1. Conc Spun Pile D 300, type B, length = 8 m/pcs 4

steel structure without cladding/wall. roofing is zincalume thk


B.1 Small shelter without cladding 1.44
0.45 mm and heigh of structure = 2m
Potable Water Treatment Civil works, foundation(1) and finishing, as specify on drawing
21 1
Foundation and specification, etc.

21.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 6

Utility & Instrument Air Receiver Civil works, foundation(1) and finishing, as specify on drawing
22 1
Foundation and specification

22.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 8

Civil works, foundation(1), upper structure(2), fabrication,


23 Pipe Rack accecories and finishing, as specify on drawing and 1
specification

23.1. Conc Spun Pile D 300, type B, length = 10 m/pcs 46

Civil works, foundation(1), upper structure(2), fabrication,


24 Pipe Supports accecories and finishing, as specify on drawing and 1
specification

A. FOUNDATION

26.1. Conc Spun Pile D 300, type B, length = 10 m/pcs 161

Civil works, foundation(1), upper structure(2), fabrication,


25 Pipe Culvert and Pipe Bridge manhole, drainage systems, stair, accessories and finishing, as 1
specify on drawing and specification

Other vessel and equipment Civil works, foundation(1) and finishing, as specify on drawing
26 1
foundation and specification
B.3.5 Procurement & Construction of Civil SKG Pang
Jasa Perancangan, Pengadaan dan Konstruksi Pembangunan SKG Rantau Panjang dan

Volume
Item Description
a

A. Pig Launcher & receiver


Foundation

A.1. Conc Spun Pile D 300, type A2, length = 8 m/pcs 8

B. Pig Launcher & receiver shelter


steel structure without cladding/wall. roofing is zincalume thk
B.1 Small shelter without cladding 16.20
0.45 mm and heigh of structure = 2m
C. Flare KO drum (1), suction
scrubber (1), discharge scrubber
(1), Flare KO drum (2), jockey
pump, deep well water pump,
electric driven fire water pump,
electric diesel fire water pump,
suction scrubber (2), discharge
scrubber(2)
A.1. Conc Spun Pile D 300, type A2, length = 10 m/pcs 58
D. Small shelter for part C

steel structure without cladding/wall. roofing is zincalume thk


D.1 Small shelter without cladding 48.42
0.45 mm and heigh of structure = 2m
Construction of Civil SKG Pangkalan Brandan
Konstruksi Pembangunan SKG Rantau Panjang dan SKG Pangkalan Brandan

Unit

lot

pcs

m2

lot

pcs

m2

lot

pcs

m2

lot

pcs

m2

lot

pcs
Construction of Civil SKG Pangkalan Brandan
Konstruksi Pembangunan SKG Rantau Panjang dan SKG Pangkalan Brandan

Unit

m2

lot

pcs

m2

lot

pcs

m2

lot

pcs

m2

lot

lot

pcs

kg
lot
pcs

lot

pcs

lot
Construction of Civil SKG Pangkalan Brandan
Konstruksi Pembangunan SKG Rantau Panjang dan SKG Pangkalan Brandan

Unit

pcs

lot

pcs

lot

pcs

kg
Construction of Civil SKG Pangkalan Brandan
Konstruksi Pembangunan SKG Rantau Panjang dan SKG Pangkalan Brandan

Unit

lot

pcs

m2

lot

pcs

m2

lot

pcs

lot

pcs

lot

pcs

lot

pcs

lot

lot
Construction of Civil SKG Pangkalan Brandan
Konstruksi Pembangunan SKG Rantau Panjang dan SKG Pangkalan Brandan

Unit

pcs

m2

pcs

m2

You might also like