JADWAL PENGECORAN

JADWAL PENGECORAN SEPTEMBER


ITEM PEKERJAAN VOLUME TANGGAL 1-Sep-18
159 m3 14 FEBRUARI 2018 2-Sep-18
159 m3 15 FEBRUARI 2018 Pengecoran Isian P3 256 m3 3-Sep-18
177 m3 16 FEBRUARI 2018 4-Sep-18
Pengecoran Beton Isian P1
177 m3 17 FEBRUARI 2018 5-Sep-18
177 m3 18 FEBRUARI 2018 11-Sep-18
Pengecoran Pile Cap P3 263 m3
212.25 m3 11-Apr-18 12-Sep-18
175 13 MEI 2018 Pengecoran Pier Head P2 88.7 m3 31 Agustus 2018
Pengecoran Pile Cap P1 175 14 MEI 2018 Pengecoran Kolom P3 36.23 m3 16-Sep-18
176 15 MEI 2018 Pengecoran Pier Head P3 149 m3 18-Sep-18
Pengecoran Kolom P1 36 m3 4 JULI 2018
Pengecoran Pier Head P1 149 m3 14 JULI 2018
467 m3 15 JULI 2018
467 m3 16 JULI 2018
Pengecoran Beton Isian P2
467 m3 17 JULI 2018
467 m3 18 JULI 2018

JADWAL PENGECORAN AGUSTUS


232 m3 5 Agustus 2018
230 m3 6 Agustus 2018
Pengecoran Pile Cap P2
230 m3 7 Agustus 2018
235 m3 8 Agustus 2018
Pengecoran Kolom P2 31.5 m3 14 Agustus 2018
Pengecoran Beton Isian 16.78 m3 10Agustus 2018
Pengecoran Pile Head PS
Lampung 74.09 m3 18 Agustus 2018

49 m3 4 Maret 2019
Pengecoran Pile Head Pile Slab 5 Maret 2019
Sumsel 50m3
50 m3 6 Maret 2019

Pengecoran Pile Head Non 28 April 2019


Shrink Sisi Sumsel 49.14 m3

Pengecoran Diafragma 40 m3 01 Mei 2019


Bentang P1 - P2 36 m3 02 Mei 2019
Pengecoran Diafragma 35 m3 05 Mei 2019
Bentang P2 - P3 41 m3 06 Mei 2019
110 m3 08 Mei 2019
91 m3 9 Mei 2019
Pengecoran Lantai P1 - P2
73 m3 10 Mei 2019
90 m3 11 Mei 2019
87 m3 12 Mei 2019
100 m3 13 Mei 2019
Pengecoran Lantai P2 - P3
95 m3 14 Mei 2019
82 m3 15 Mei 2019