You are on page 1of 112

REKAPITULASI VOLUME DRAIN INLET

No. Item pekerjaan Sat Volume Total Inlet 1 Inlet 2 Inlet 3 Inlet 4 Inlet 5 Inlet 6
I Drain Inlet
1 Galian Tanah m3 14,756.81 1,016.37 711.71 259.13 372.16 772.24 756.57
2 Cerucuk Bambu titik 1,836.00 108.00 108.00 108.00 108.00 108.00 108.00
3 Sand Gravel Stone m3 183.60 10.80 10.80 10.80 10.80 10.80 10.80
4 Gabion 2x1x1 m3 1,632.00 96.00 96.00 96.00 96.00 96.00 96.00
5 Concrete Pile titik 3,166.08 429.68 133.28 178.96 140.80 196.08 164.16
6 Lean Concrete m3 555.41 65.92 24.93 35.45 26.25 35.78 29.18
7 Concrete K300 m3 762.73 44.36 36.21 36.56 57.38 50.03 35.94
8 Pembesian kg 106,263.32 5,715.62 4,597.62 4,631.56 7,858.95 6,742.94 4,557.81
9 Box Culvert m1 791.52 107.42 33.32 44.74 35.20 49.02 41.04
10 Sluice Gate unit 34.00 2.00 2.00 2.00 2.00 2.00 2.00
11 Valve Gate unit 34.00 2.00 2.00 2.00 2.00 2.00 2.00
II Tampungan -
1 Galian Tanah m3 404,564.78 1,741.49 1,103.62 60,649.71 17,240.45 46,265.24 1,727.68
2 Back Fill m3 12,237.27 522.45 44.47 1,962.71 820.01 1,224.77 134.63
3 Timbunan & Pemadatan m3 20,210.27 197.37 11,032.38 531.61 695.14 365.72
4 Sand 10cm m3 1,100.81 8.77 8.77 182.37 78.01 114.98 8.77
5 Stone Pitching Size 20cm-30cm m3 5,504.06 43.87 43.87 911.85 390.07 574.89 43.87
6 Stone Masonry 1:2:3 m3 42,490.44 354.45 354.45 7,367.72 3,151.76 4,645.11 354.45
7 Wheep Hole Ø 1 1/2" Distance 1,5m titik 4,050,433.71 1,388.77 1,388.77 2,142,184.15 94,030.44 227,847.33 1,388.77
8 Plestering Finishing Cement 1:3 m2 10,633.84 84.75 84.75 1,761.69 753.61 1,110.69 84.75
9 Concrete K175 (Pagar) m3 1,129.83 8.05 8.05 255.42 56.04 81.50 8.05
10 Pagar BRC m1 272,633.05 1,941.71 1,941.71 61,634.33 13,522.40 19,665.87 1,941.71
III Jalan Inspeksi Tampungan -
1 Sand m3 3,285.94 741.84 176.96 257.36
2 Stone Pitching Size 20cm-30cm m3 8,762.50 1,978.25 471.90 686.30
3 Base Coarse m3 1,095.31 247.28 58.99 85.79

Kesimpulan
Item pekerjaan Satuan Volume Total Inlet 1 Inlet 2 Inlet 3 Inlet 4 Inlet 5 Inlet 6
Tampungan
Galian Tanah m3 325,062.00 90,894.00 13,484.00 25,809.00
Back Fill m3 9,605.20 2,017.40 928.40 1,282.60
Timbunan & Pemadatan m3 77,270.00 18,340.00 4,220.00 5,830.00
Sand 10cm m3 972.10 183.40 84.40 116.60
Stone Pitching Size 20cm-30cm m3 4,860.50 917.00 422.00 583.00
Stone Masonry 1:2:3 m3 41,013.58 7,336.00 3,722.04 5,142.06
Wheep Hole Ø 1 1/2" Distance 1,5m titik 14,581.50 2,751.00 1,266.00 1,749.00
Plestering Finishing Cement 1:3 m2 9,721.00 1,834.00 844.00 1,166.00
Concrete K175 (Pagar) m3 772.70 183.40 42.20 58.30
Pagar BRC m1 15,454.00 3,668.00 844.00 1,166.00
Jalan Inspeksi Tampungan - - - -
Sand m3 3,477.15 825.30 189.90 262.35
Stone Pitching Size 20cm-30cm m3 6,954.30 1,650.60 379.80 524.70
Base Coarse m3 2,318.10 550.20 126.60 174.90
REKAPITULASI VOLUME DRAIN INLET

No. Item pekerjaan Sat Inlet 7 Inlet 8 Inlet 9 Inlet 10 Inlet 11 Inlet 12 Inlet 13
I Drain Inlet
1 Galian Tanah m3 704.17 1,094.31 1,358.30 1,194.09 916.01 857.35 922.51
2 Cerucuk Bambu titik 108.00 108.00 108.00 108.00 108.00 108.00 108.00
3 Sand Gravel Stone m3 10.80 10.80 10.80 10.80 10.80 10.80 10.80
4 Gabion 2x1x1 m3 96.00 96.00 96.00 96.00 96.00 96.00 96.00
5 Concrete Pile titik 156.32 184.00 277.12 137.76 168.56 159.28 192.80
6 Lean Concrete m3 28.25 31.95 44.79 25.62 29.85 28.63 33.22
7 Concrete K300 m3 50.47 50.93 48.86 49.06 43.29 43.51 43.39
8 Pembesian kg 7,092.21 7,106.61 6,980.06 6,856.01 6,306.31 6,364.12 6,349.36
9 Box Culvert m1 39.08 46.00 69.28 34.44 42.14 39.82 48.20
10 Sluice Gate unit 2.00 2.00 2.00 2.00 2.00 2.00 2.00
11 Valve Gate unit 2.00 2.00 2.00 2.00 2.00 2.00 2.00
II Tampungan
1 Galian Tanah m3 20,855.63 27,669.66 1,156.25 10,574.23 26,789.97 19,383.05 65,627.85
2 Back Fill m3 2,249.17 670.00 362.61 359.50 660.07 358.59 724.15
3 Timbunan & Pemadatan m3 1,377.42 874.50 345.35 214.56 844.10 459.44 927.17
4 Sand 10cm m3 208.53 64.31 36.24 34.39 61.84 34.31 67.70
5 Stone Pitching Size 20cm-30cm m3 1,042.65 321.57 181.21 171.97 309.22 171.56 338.48
6 Stone Masonry 1:2:3 m3 7,473.72 2,598.29 1,464.18 1,232.71 2,498.49 1,386.19 2,734.90
7 Wheep Hole Ø 1 1/2" Distance 1,5m titik 703,557.14 128,800.10 25,839.42 19,025.58 121,289.23 35,915.78 145,956.40
8 Plestering Finishing Cement 1:3 m2 2,014.40 621.27 350.10 332.25 597.41 331.45 653.94
9 Concrete K175 (Pagar) m3 145.12 87.19 47.19 46.78 85.90 46.67 94.24
10 Pagar BRC m1 35,017.60 21,039.86 11,387.03 11,289.41 20,727.98 11,260.83 22,740.22
III Jalan Inspeksi Tampungan
1 Sand m3 458.27 275.34 149.02 73.98 271.26 147.37 297.59
2 Stone Pitching Size 20cm-30cm m3 1,222.04 734.25 397.38 197.29 723.36 392.98 793.59
3 Base Coarse m3 152.76 91.78 49.67 24.66 90.42 49.12 99.20

Kesimpulan
Item pekerjaan Satuan Inlet 7 Inlet 8 Inlet 9 Inlet 10 Inlet 11 Inlet 12 Inlet 13
Tampungan
Galian Tanah m3 16,125.50 26,592.50 7,017.50 4,371.00 18,803.00 14,769.50 46,012.00
Back Fill m3 1,189.10 709.50 442.20 249.70 735.90 424.60 787.60
Timbunan & Pemadatan m3 10,810.00 6,450.00 4,020.00 2,270.00 6,690.00 3,860.00 7,160.00
Sand 10cm m3 108.10 64.50 40.20 45.40 66.90 38.60 71.60
Stone Pitching Size 20cm-30cm m3 540.50 322.50 201.00 227.00 334.50 193.00 358.00
Stone Masonry 1:2:3 m3 4,324.00 2,580.00 1,608.00 2,115.64 2,676.00 1,544.00 2,864.00
Wheep Hole Ø 1 1/2" Distance 1,5m titik 1,621.50 967.50 603.00 681.00 1,003.50 579.00 1,074.00
Plestering Finishing Cement 1:3 m2 1,081.00 645.00 402.00 454.00 669.00 386.00 716.00
Concrete K175 (Pagar) m3 108.10 64.50 40.20 22.70 66.90 38.60 71.60
Pagar BRC m1 2,162.00 1,290.00 804.00 454.00 1,338.00 772.00 1,432.00
Jalan Inspeksi Tampungan - - - - - - -
Sand m3 486.45 290.25 180.90 102.15 301.05 173.70 322.20
Stone Pitching Size 20cm-30cm m3 972.90 580.50 361.80 204.30 602.10 347.40 644.40
Base Coarse m3 324.30 193.50 120.60 68.10 200.70 115.80 214.80
REKAPITULASI VOLUME DRAIN INLET

No. Item pekerjaan Sat Inlet 14 Inlet 15 Inlet 16 Inlet 17 Inlet 18


I Drain Inlet
1 Galian Tanah m3 1,323.14 1,084.76 780.54 633.46
2 Cerucuk Bambu titik 108.00 108.00 108.00 108.00
3 Sand Gravel Stone m3 10.80 10.80 10.80 10.80
4 Gabion 2x1x1 m3 96.00 96.00 96.00 96.00
5 Concrete Pile titik 167.12 110.96 136.88 232.32
6 Lean Concrete m3 29.67 21.89 25.45 38.56
7 Concrete K300 m3 43.32 43.14 43.14 43.14
8 Pembesian kg 6,320.58 6,261.18 6,261.18 6,261.18
9 Box Culvert m1 41.78 27.74 34.22 58.08
10 Sluice Gate unit 2.00 2.00 2.00 2.00
11 Valve Gate unit 2.00 2.00 2.00 2.00
II Tampungan
1 Galian Tanah m3 92,036.04 8,331.64 1,137.42 1,137.42 1,137.42
2 Back Fill m3 1,572.31 331.83 80.00 80.00 80.00
3 Timbunan & Pemadatan m3 1,661.17 444.34 80.00 80.00 80.00
4 Sand 10cm m3 145.15 24.73 7.31 7.31 7.31
5 Stone Pitching Size 20cm-30cm m3 725.76 123.63 36.53 36.53 36.53
6 Stone Masonry 1:2:3 m3 5,202.28 886.21 261.84 261.84 261.84
7 Wheep Hole Ø 1 1/2" Distance 1,5m titik 358,041.02 40,760.98 1,006.60 1,006.60 1,006.60
8 Plestering Finishing Cement 1:3 m2 1,402.18 238.86 70.57 70.57 70.57
9 Concrete K175 (Pagar) m3 103.13 35.24 7.09 7.09 7.09
10 Pagar BRC m1 24,884.84 8,502.56 1,711.67 1,711.67 1,711.67
III Jalan Inspeksi Tampungan
1 Sand m3 325.66 111.27
2 Stone Pitching Size 20cm-30cm m3 868.43 296.72
3 Base Coarse m3 108.55 37.09

Kesimpulan
Item pekerjaan Satuan Inlet 14 Inlet 15 Inlet 16 Inlet 17 Inlet 18
Tampungan
Galian Tanah m3 61,184.00
Back Fill m3 838.20
Timbunan & Pemadatan m3 7,620.00
Sand 10cm m3 152.40
Stone Pitching Size 20cm-30cm m3 762.00
Stone Masonry 1:2:3 m3 7,101.84
Wheep Hole Ø 1 1/2" Distance 1,5m titik 2,286.00
Plestering Finishing Cement 1:3 m2 1,524.00
Concrete K175 (Pagar) m3 76.20
Pagar BRC m1 1,524.00
Jalan Inspeksi Tampungan -
Sand m3 342.90
Stone Pitching Size 20cm-30cm m3 685.80
Base Coarse m3 228.60
Drain 3 Kitarung
Elevasi Luas Panjang Volume
18.00 7,206.00 22,803.00
17.00 38,400.00 43,645.50
16.00 48,891.00 24,445.50

90,894.00
Back Fill 1.10 1,834.00 2,017.40
Timbunan 10.00 1,834.00 18,340.00
Sand 10cm 0.10 1,834.00 183.40
Stone Pitching 0.50 1,834.00 917.00
Masonry 4.00 1,834.00 7,336.00
Wheep Hole 1.50 1,834.00 2,751.00
Plestering 1.00 1,834.00 1,834.00
Concrete K175 0.10 1,834.00 183.40
Pagar BRC 2.00 1,834.00 3,668.00

Sand 0.45 1,834.00 825.30


Stone Pitching 0.9 1,834.00 1,650.60
Base Coarse 0.3 1,834.00 550.20

Drain 4 Cilangkap
Elevasi Luas Panjang Volume
21.00 236.00 638.00
20.00 1,040.00 1,486.50
19.00 1,933.00 2,296.50
18.00 2,660.00 3,054.00
17.00 3,448.00 3,866.50
16.00 4,285.00 2,142.50

13,484.00
Back Fill 2.20 422.00 928.40
Timbunan 10.00 422.00 4,220.00
Sand 10cm 0.20 422.00 84.40
Stone Pitching 1.00 422.00 422.00
Masonry 8.82 422.00 3,722.04
Wheep Hole 3.00 422.00 1,266.00
Plestering 2.00 422.00 844.00
Concrete K175 0.10 422.00 42.20
Pagar BRC 2.00 422.00 844.00

Sand 0.45 422.00 189.90


Stone Pitching 0.9 422.00 379.80
Base Coarse 0.3 422.00 126.60

Drain 5 Kaduagung Timur


Elevasi Luas Panjang Volume
21.00 904.00 1,431.00
20.00 1,958.00 2,850.00
19.00 3,742.00 4,519.00
18.00 5,296.00 5,986.50
17.00 6,677.00 7,180.50
16.00 7,684.00 3,842.00

25,809.00
Back Fill 2.20 583.00 1,282.60
Timbunan 10.00 583.00 5,830.00
Sand 10cm 0.20 583.00 116.60
Stone Pitching 1.00 583.00 583.00
Masonry 8.82 583.00 5,142.06
Wheep Hole 3.00 583.00 1,749.00
Plestering 2.00 583.00 1,166.00
Concrete K175 0.10 583.00 58.30
Pagar BRC 2.00 583.00 1,166.00

Sand 0.45 583.00 262.35


Stone Pitching 0.9 583.00 524.70
Base Coarse 0.3 583.00 174.90

Drain 7 Royal Soeta


Elevasi Luas Panjang Volume
17.00 1,463.00 2,249.00
16.00 3,035.00 3,913.00
15.00 4,791.00 6,179.50
14.00 7,568.00 3,784.00

16,125.50
Back Fill 1.10 1,081.00 1,189.10
Timbunan 10.00 1,081.00 10,810.00
Sand 10cm 0.10 1,081.00 108.10
Stone Pitching 0.50 1,081.00 540.50
Masonry 4.00 1,081.00 4,324.00
Wheep Hole 1.50 1,081.00 1,621.50
Plestering 1.00 1,081.00 1,081.00
Concrete K175 0.10 1,081.00 108.10
Pagar BRC 2.00 1,081.00 2,162.00
Sand 0.45 1,081.00 486.45
Stone Pitching 0.9 1,081.00 972.90
Base Coarse 0.3 1,081.00 324.30

Drain 8 Cibadak
Elevasi Luas Panjang Volume
18.00 1,181.00 3,768.00
17.00 6,355.00 13,001.00
16.00 19,647.00 9,823.50

26,592.50
Back Fill 1.10 645.00 709.50
Timbunan 10.00 645.00 6,450.00
Sand 10cm 0.10 645.00 64.50
Stone Pitching 0.50 645.00 322.50
Masonry 4.00 645.00 2,580.00
Wheep Hole 1.50 645.00 967.50
Plestering 1.00 645.00 645.00
Concrete K175 0.10 645.00 64.50
Pagar BRC 2.00 645.00 1,290.00

Sand 0.45 645.00 290.25


Stone Pitching 0.9 645.00 580.50
Base Coarse 0.3 645.00 193.50

Drain 9 Babakan
Elevasi Luas Panjang Volume
17.00 1,619.00 2,161.50
16.00 2,704.00 3,104.00
15.00 3,504.00 1,752.00

7,017.50
Back Fill 1.10 402.00 442.20
Timbunan 10.00 402.00 4,020.00
Sand 10cm 0.10 402.00 40.20
Stone Pitching 0.50 402.00 201.00
Masonry 4.00 402.00 1,608.00
Wheep Hole 1.50 402.00 603.00
Plestering 1.00 402.00 402.00
Concrete K175 0.10 402.00 40.20
Pagar BRC 2.00 402.00 804.00
Sand 0.45 402.00 180.90
Stone Pitching 0.9 402.00 361.80
Base Coarse 0.3 402.00 120.60

Drain 10 Kuncoro Jakti


Elevasi Luas Panjang Volume
20.00 22.00 244.00
19.00 466.00 713.50
18.00 961.00 1,094.00
17.00 1,227.00 1,466.50
16.00 1,706.00 853.00

4,371.00
Back Fill 1.10 227.00 249.70
Timbunan 10.00 227.00 2,270.00
Sand 10cm 0.20 227.00 45.40
Stone Pitching 1.00 227.00 227.00
Masonry 9.32 227.00 2,115.64
Wheep Hole 3.00 227.00 681.00
Plestering 2.00 227.00 454.00
Concrete K175 0.10 227.00 22.70
Pagar BRC 2.00 227.00 454.00

Sand 0.45 227.00 102.15


Stone Pitching 0.9 227.00 204.30
Base Coarse 0.3 227.00 68.10

Drain 11 Bojongcae
Elevasi Luas Panjang Volume
18.00 334.00 675.50
17.00 1,017.00 9,318.00
16.00 17,619.00 8,809.50

18,803.00
Back Fill 1.10 669.00 735.90
Timbunan 10.00 669.00 6,690.00
Sand 10cm 0.10 669.00 66.90
Stone Pitching 0.50 669.00 334.50
Masonry 4.00 669.00 2,676.00
Wheep Hole 1.50 669.00 1,003.50
Plestering 1.00 669.00 669.00
Concrete K175 0.10 669.00 66.90
Pagar BRC 2.00 669.00 1,338.00
Sand 0.45 669.00 301.05
Stone Pitching 0.9 669.00 602.10
Base Coarse 0.3 669.00 200.70

Drain 12 Pabuaran
Elevasi Luas Panjang Volume
15.00 2,123.00 4,488.50
14.00 6,854.00 6,854.00
13.00 6,854.00 3,427.00

14,769.50
Back Fill 1.10 386.00 424.60
Timbunan 10.00 386.00 3,860.00
Sand 10cm 0.10 386.00 38.60
Stone Pitching 0.50 386.00 193.00
Masonry 4.00 386.00 1,544.00
Wheep Hole 1.50 386.00 579.00
Plestering 1.00 386.00 386.00
Concrete K175 0.10 386.00 38.60
Pagar BRC 2.00 386.00 772.00

Sand 0.45 386.00 173.70


Stone Pitching 0.9 386.00 347.40
Base Coarse 0.3 386.00 115.80

Drain 13 Carelang
Elevasi Luas Panjang Volume
15.00 1,858.00 11,927.00
14.00 21,996.00 22,541.50
13.00 23,087.00 11,543.50

46,012.00
Back Fill 1.10 716.00 787.60
Timbunan 10.00 716.00 7,160.00
Sand 10cm 0.10 716.00 71.60
Stone Pitching 0.50 716.00 358.00
Masonry 4.00 716.00 2,864.00
Wheep Hole 1.50 716.00 1,074.00
Plestering 1.00 716.00 716.00
Concrete K175 0.10 716.00 71.60
Pagar BRC 2.00 716.00 1,432.00
Sand 0.45 716.00 322.20
Stone Pitching 0.9 716.00 644.40
Base Coarse 0.3 716.00 214.80

Drain 14 Bojong Pandan


Elevasi Luas Panjang Volume
17.00 288.00 3,486.50
16.00 6,685.00 11,730.00
15.00 16,775.00 17,708.50
14.00 18,642.00 18,790.00
13.00 18,938.00 9,469.00

61,184.00
Back Fill 1.10 762.00 838.20
Timbunan 10.00 762.00 7,620.00
Sand 10cm 0.20 762.00 152.40
Stone Pitching 1.00 762.00 762.00
Masonry 9.32 762.00 7,101.84
Wheep Hole 3.00 762.00 2,286.00
Plestering 2.00 762.00 1,524.00
Concrete K175 0.10 762.00 76.20
Pagar BRC 2.00 762.00 1,524.00

Sand 0.45 762.00 342.90


Stone Pitching 0.9 762.00 685.80
Base Coarse 0.3 762.00 228.60
INLET 1 CIKATAPIS CIBERANG (LEFT STA. 0+000)

DRAIN INLET
Box Culvert m' 107.42
Panjang Jumlah Volume
m' m'
53.71 2.00 107.42

Concrete m³ 44.36
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 0.99 4.90 4.87

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.80 2.00 11.43
dinding tengah 1.24 3.80 4.72
0.60 4.90 2.93

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 4.21 2.00 3.79
dinding tengah 0.81 4.90 3.99

Area Lebar Volume


m² m' m³
Tangga 3.36 1.00 3.36

Lean Concrete m³ 65.92


Area Panjang Volume
m² m' m³
Lantai 1.10 57.96 63.76

Area Panjang Volume


m² m' m³
Tangga 2.16 1.00 2.16
INLET 1 CIKATAPIS CIBERANG (LEFT STA. 0+000)

Concrete Pile m' 429.68


Panjang titik Tinggi Total
m' m' m' m'
53.71 107.42 4.00 429.68

Reinforcement kg/m 5715.62


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 7.62 24.50 186.62 4.90 38.09 186.62 1.58 1179.42

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 19.00 158.38 3.80 41.68 158.38 1.58 1000.99
dinding tengah 7.39 19.00 140.37 3.80 36.94 140.37 1.58 443.58
5.79 24.50 141.76 4.90 28.93 141.76 1.58 447.95

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 21.05 88.41 4.21 21.00 88.41 1.58 558.75
dinding tengah 6.62 24.50 162.29 4.90 33.12 162.29 1.58 512.83

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 37.33 5.00 186.65 1.00 186.64 186.64 1.58 589.80
INLET 1 CIKATAPIS CIBERANG (LEFT STA. 0+000)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 1016.37
Area Panjang Volume
m² m' m³
Box culvert 8.19 53.71 439.88
Sluice gate 4.16 6.00 24.95
Valve Gate 91.92 6.00 551.53

Pintu
Sluice Gate 2
Valve Gate 2
INLET 1 CIKATAPIS CIBERANG (LEFT STA. 0+000)
TAMPUNGAN
Galian m³ 1741.49
Area Panjang Volume
m² m' m³
29.75 25.50 758.57
96.36 10.20 982.91

Back fill m³ 522.45


Area Panjang Volume
m² m' m³
8.92 25.50 227.57
28.91 10.20 294.87

sand m³ 8.77
Area Panjang sisi Volume
m² m' m³
0.10 28.23 2.00 5.65
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 43.87


Area Panjang sisi Volume
m² m' m³
0.50 28.23 2.00 28.23
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 354.45


Area Panjang sisi Volume
m² m' m³
4.04 28.23 2.00 228.13
4.04 15.63 2.00 126.32

Wheep Hole Ø 1 1/2" Distance 1,5m titik 1388.77


Panjang titik sisi Volume
m' titik
28.23 18.82 2.00 1062.88
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 84.75


Panjang Lebar sisi Volume
m' m' m²
28.23 0.97 2.00 54.55
15.63 0.97 2.00 30.20

Concrete K175 (Pagar) m³ 8.05


Area titik sisi Volume
m² m³
0.29 14.12 2.00 8.05
INLET 1 CIKATAPIS CIBERANG (LEFT STA. 0+000)
Pagar BRC m' 1941.71
Panjang titik sisi Volume
m' m³
68.77 14.12 2.00 1941.71
INLET 2 CIUJUNG BARAT (RIGHT STA. 0+300)

DRAIN INLET
Box Culvert m' 33.32
Panjang Jumlah Volume
m' m'
16.66 2.00 33.32

Concrete m³ 36.21
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 0.99 4.90 4.87

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.21

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.40 2.00 2.16

Area Lebar Volume


m² m' m³
Tangga 3.68 1.00 3.68

Lean Concrete m³ 24.93


Area Panjang Volume
m² m' m³
Lantai 1.10 20.61 22.67

Area Panjang Volume


m² m' m³
Tangga 2.26 1.00 2.26
INLET 2 CIUJUNG BARAT (RIGHT STA. 0+300)

Concrete Pile m' 133.28


Panjang titik Tinggi Total
m' m' m' m'
16.66 33.32 4.00 133.28

Reinforcement kg/m 4597.62


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 7.62 24.50 186.62 4.90 38.09 186.62 1.58 1179.42

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.20 24.50 78.40 4.90 16.00 78.40 1.58 247.74

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 12.00 50.40 2.40 21.00 50.40 1.58 318.53

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 38.93 5.00 194.67 1.00 194.67 194.67 1.58 615.14
INLET 2 CIUJUNG BARAT (RIGHT STA. 0+300)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 711.71
Area Panjang Volume
m² m' m³
Box culvert 8.19 16.66 136.45
Sluice gate 6.42 6.00 38.52
Valve Gate 89.46 6.00 536.74

Pintu
Sluice Gate 2
Valve Gate 2
INLET 2 CIUJUNG BARAT (RIGHT STA. 0+300)
TAMPUNGAN
Galian m³ 1103.62
Area Panjang Volume
m² m' m³
5.81 25.50 148.23
63.17 15.13 955.38

Back fill m³ 44.47


Area Panjang Volume
m² m' m³
1.74 25.50 44.47

Timbunan & Pemadatan m³ 197.37


Area Panjang sisi Volume
m² m' m³
3.87 25.50 2.00 197.37

sand m³ 8.77
Area Panjang sisi Volume
m² m' m³
0.10 28.23 2.00 5.65
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 43.87


Area Panjang sisi Volume
m² m' m³
0.50 28.23 2.00 28.23
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 354.45


Area Panjang sisi Volume
m² m' m³
4.04 28.23 2.00 228.13
4.04 15.63 2.00 126.32

Wheep Hole Ø 1 1/2" Distance 1,5m titik 1388.77


Panjang titik sisi Volume
m' titik
28.23 18.82 2.00 1062.88
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 84.75


Panjang Lebar sisi Volume
m' m' m²
28.23 0.97 2.00 54.55
15.63 0.97 2.00 30.20
INLET 2 CIUJUNG BARAT (RIGHT STA. 0+300)
Concrete K175 (Pagar) m³ 8.05
Area titik sisi Volume
m² m³
0.29 14.12 2.00 8.05

Pagar BRC m' 1941.71


Panjang titik sisi Volume
m' m³
68.77 14.12 2.00 1941.71
INLET 3 KITARUNG (RIGHT STA. 0+800)

DRAIN INLET
Box Culvert m' 44.74
Panjang Jumlah Volume
m' m'
22.37 2.00 44.74

Concrete m³ 36.56
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 0.99 4.90 4.87

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.21

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.90 2.00 2.61

Area Lebar Volume


m² m' m³
Tangga 3.58 1.00 3.58

Lean Concrete m³ 35.45


Area Panjang Volume
m² m' m³
Lantai 1.10 30.22 33.24

Area Panjang Volume


m² m' m³
Tangga 2.21 1.00 2.21
INLET 3 KITARUNG (RIGHT STA. 0+800)

Concrete Pile m' 178.96


Panjang titik Tinggi Total
m' m' m' m'
22.37 44.74 4.00 178.96

Reinforcement kg/m 4631.56


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 7.62 24.50 186.62 4.90 38.09 186.62 1.58 1179.42

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.20 24.50 78.40 4.90 16.00 78.40 1.58 247.74

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 14.50 60.90 2.90 21.00 60.90 1.58 384.89

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 36.88 5.00 184.41 1.00 184.41 184.41 1.58 582.72
INLET 3 KITARUNG (RIGHT STA. 0+800)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 259.13
Area Panjang Volume
m² m' m³
Box culvert 8.19 22.37 183.21
Sluice gate 8.63 2.50 21.57
Valve Gate 9.06 6.00 54.35

Pintu
Sluice Gate 2
Valve Gate 2
INLET 3 KITARUNG (RIGHT STA. 0+800)
TAMPUNGAN
Galian m³ 60649.71
Area Tinggi Volume
m² m' m³
29999.61 2.00 59999.22
108.42 6.00 650.49

Back fill m³ 1962.71


Area Panjang Volume
m² m' m³
1.10 1792.43 1962.71

Timbunan & Pemadatan m³ 11032.38


Area Panjang sisi Volume
m² m' m³
6.16 1792.43 11032.38

sand m³ 182.37
Area Panjang sisi Volume
m² m' m³
0.10 1792.43 179.24
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 911.85


Area Panjang sisi Volume
m² m' m³
0.50 1792.43 896.21
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 7367.72


Area Panjang sisi Volume
m² m' m³
4.04 1792.43 7241.40
4.04 15.63 2.00 126.32

Wheep Hole Ø 1 1/2" Distance 1,5m titik 2142184.15


Panjang titik sisi Volume
m' titik
1792.43 1194.95 2141858.25
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 1761.69


Panjang Lebar sisi Volume
m' m' m²
1792.43 0.97 1731.48
15.63 0.97 2.00 30.20
INLET 3 KITARUNG (RIGHT STA. 0+800)
Concrete K175 (Pagar) m³ 255.42
Area titik sisi Volume
m² m³
0.29 896.21 255.42

Pagar BRC m' 61634.33


Panjang titik sisi Volume
m' m³
68.77 896.21 61634.33
INLET 3 KITARUNG (RIGHT STA. 0+800)
JALAN INSPEKSI TAMPUNGAN
sand m³ 741.84
Area Panjang sisi Volume
m² m' m³
0.45 1648.54 741.84

Stone Pitching Size 20cm-30cm m³ 1978.25


Area Panjang sisi Volume
m² m' m³
1.20 1648.54 1978.25

Base Coarse m³ 247.28


Area Panjang sisi Volume
m² m' m³
0.15 1648.54 247.28
INLET 4 CILANGKAP (RIGHT STA. 0+400)

DRAIN INLET
Box Culvert m' 35.20
Panjang Jumlah Volume
m' m'
17.60 2.00 35.20

Concrete m³ 57.38
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 4.30 2.00 12.93
dinding tengah 1.24 4.30 5.34
0.75 4.90 3.68

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 3.92 2.00 3.53
0.72 4.90 2.00 7.10

Area Lebar Volume


m² m' m³
Tangga 3.31 1.00 3.31

Lean Concrete m³ 26.25


Area Panjang Volume
m² m' m³
Lantai 1.10 21.55 23.71

Area Panjang Volume


m² m' m³
Tangga 2.55 1.00 2.55
INLET 4 CILANGKAP (RIGHT STA. 0+400)

Concrete Pile m' 140.80


Panjang titik Tinggi Total
m' m' m' m'
17.60 35.20 4.00 140.80

Reinforcement kg/m 7858.95


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 21.50 179.22 4.30 41.68 179.22 1.58 1132.70
dinding tengah 7.39 21.50 158.84 4.30 36.94 158.84 1.58 501.94
5.21 24.50 127.57 4.90 26.03 127.57 1.58 403.13

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 19.60 82.32 3.92 21.00 82.32 1.58 520.26
5.03 24.50 123.24 4.90 25.15 123.24 1.58 778.85

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 39.63 5.00 198.15 1.00 198.15 198.15 1.58 626.15
INLET 4 CILANGKAP (RIGHT STA. 0+400)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 372.16
Area Panjang Volume
m² m' m³
Box culvert 8.19 17.60 144.14
Sluice gate 5.50 7.84 43.12
Valve Gate 16.70 11.07 184.89

Pintu
Sluice Gate 2
Valve Gate 2
INLET 4 CILANGKAP (RIGHT STA. 0+400)
TAMPUNGAN
Galian m³ 17240.45
Area Tinggi Volume
m² m' m³
90.75 187.22 16990.76
22.56 11.07 249.69

Back fill m³ 820.01


Area Panjang Volume
m² m' m³
1.10 196.11 214.74
1.10 178.15 195.08
1.10 177.46 194.32
1.10 197.15 215.87

Timbunan & Pemadatan m³ 531.61


Area Panjang sisi Volume
m² m' m³
1.80 196.11 352.40
0.91 197.15 179.21

sand m³ 78.01
Area Panjang Volume
m² m' m³
0.10 196.11 19.61
0.10 178.15 17.82
0.10 177.46 17.75
0.10 197.15 19.71
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 390.07


Area Panjang sisi Volume
m² m' m³
0.50 196.11 98.05
0.50 178.15 89.08
0.50 177.46 88.73
0.50 197.15 98.57
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 3151.76


Area Panjang sisi Volume
m² m' m³
4.04 196.11 792.27
4.04 178.15 719.74
4.04 177.46 716.95
4.04 197.15 796.47
4.04 15.63 2.00 126.32
INLET 4 CILANGKAP (RIGHT STA. 0+400)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 94030.44
Panjang titik sisi Volume
m' titik
196.11 130.74 25638.64
178.15 118.77 21159.23
177.46 118.31 20995.65
197.15 131.43 25911.03
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 753.61


Panjang Lebar sisi Volume
m' m' m²
196.11 0.97 189.44
178.15 0.97 172.10
177.46 0.97 171.43
197.15 0.97 190.44
15.63 0.97 2.00 30.20

Concrete K175 (Pagar) m³ 56.04


Area titik sisi Volume
m² m³
0.29 98.05 27.95
0.29 98.57 28.09

Pagar BRC m' 13522.40


Panjang titik sisi Volume
m' m³
68.77 98.05 6743.34
68.77 98.57 6779.06
INLET 4 CILANGKAP (RIGHT STA. 0+400)
JALAN INSPEKSI TAMPUNGAN
sand m³ 176.96
Area Panjang sisi Volume
m² m' m³
0.45 196.11 88.25
0.45 197.15 88.72

Stone Pitching Size 20cm-30cm m³ 471.90


Area Panjang sisi Volume
m² m' m³
1.20 196.11 235.33
1.20 197.15 236.58

Base Coarse m³ 58.99


Area Panjang sisi Volume
m² m' m³
0.15 196.11 29.42
0.15 197.15 29.57
INLET 5 KADUAGUNG TIMUR (LEFT STA. 1+450)

DRAIN INLET
Box Culvert m' 49.02
Panjang Jumlah Volume
m' m'
24.51 2.00 49.02

Concrete m³ 50.03
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 4.50 2.00 13.54
dinding tengah 1.24 4.50 5.59
0.81 4.90 3.97

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.57 2.00 2.31
0.32 4.90 2.00 3.14

Lean Concrete m³ 35.78


Area Panjang Volume
m² m' m³
Lantai 1.10 32.53 35.78
INLET 5 KADUAGUNG TIMUR (LEFT STA. 1+450)

Concrete Pile m' 196.08


Panjang titik Tinggi Total
m' m' m' m'
24.51 49.02 4.00 196.08

Reinforcement kg/m 6742.94


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 22.50 187.56 4.50 41.68 187.56 1.58 1185.38
dinding tengah 7.39 22.50 166.23 4.50 36.94 166.23 1.58 525.29
5.60 24.50 137.20 4.90 28.00 137.20 1.58 433.55

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 12.85 53.97 2.57 21.00 53.97 1.58 341.09
2.34 24.50 57.23 4.90 11.68 57.23 1.58 361.71
INLET 5 KADUAGUNG TIMUR (LEFT STA. 1+450)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 772.24
Area Panjang Volume
m² m' m³
Box culvert 8.19 24.51 200.74
Sluice gate 37.84 6.00 227.05
Valve Gate 57.41 6.00 344.46

Pintu
Sluice Gate 2
Valve Gate 2
INLET 5 KADUAGUNG TIMUR (LEFT STA. 1+450)
TAMPUNGAN
Galian m³ 46265.24
Area Tinggi Volume
m² m' m³
7710.87 6.00 46265.24

Back fill m³ 1224.77


Area Panjang Volume
m² m' m³
1.10 193.73 212.14
1.10 197.38 216.13
1.10 352.87 386.39
1.10 374.54 410.12

Timbunan & Pemadatan m³ 695.14


Area Panjang sisi Volume
m² m' m³
1.80 197.38 354.69
0.91 374.54 340.45

sand m³ 114.98
Area Panjang Volume
m² m' m³
0.10 193.73 19.37
0.10 197.38 19.74
0.10 352.87 35.29
0.10 374.54 37.45
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 574.89


Area Panjang sisi Volume
m² m' m³
0.50 193.73 96.87
0.50 197.38 98.69
0.50 352.87 176.43
0.50 374.54 187.27
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 4645.11


Area Panjang sisi Volume
m² m' m³
4.04 193.73 782.67
4.04 197.38 797.41
4.04 352.87 1425.58
4.04 374.54 1513.13
4.04 15.63 2.00 126.32
INLET 5 KADUAGUNG TIMUR (LEFT STA. 1+450)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 227847.33
Panjang titik sisi Volume
m' titik
193.73 129.15 25021.13
197.38 131.59 25972.05
352.87 235.24 83009.61
374.54 249.69 93518.64
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 1110.69


Panjang Lebar sisi Volume
m' m' m²
193.73 0.97 187.14
197.38 0.97 190.67
352.87 0.97 340.87
374.54 0.97 361.80
15.63 0.97 2.00 30.20

Concrete K175 (Pagar) m³ 81.50


Area titik sisi Volume
m² m³
0.29 98.69 28.13
0.29 187.27 53.37

Pagar BRC m' 19665.87


Panjang titik sisi Volume
m' m³
68.77 98.69 6787.04
68.77 187.27 12878.83
INLET 5 KADUAGUNG TIMUR (LEFT STA. 1+450)
JALAN INSPEKSI TAMPUNGAN
sand m³ 257.36
Area Panjang sisi Volume
m² m' m³
0.45 197.38 88.82
0.45 374.54 168.54

Stone Pitching Size 20cm-30cm m³ 686.30


Area Panjang sisi Volume
m² m' m³
1.20 197.38 236.85
1.20 374.54 449.44

Base Coarse m³ 85.79


Area Panjang sisi Volume
m² m' m³
0.15 197.38 29.61
0.15 374.54 56.18
INLET 6 JL. SUNAN KALIJAGA (RIGHT STA. 2+600)

DRAIN INLET
Box Culvert m' 41.04
Panjang Jumlah Volume
m' m'
20.52 2.00 41.04

Concrete m³ 35.94
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 0.99 4.90 4.87

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.21

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.68 1.00 3.68

Lean Concrete m³ 29.18


Area Panjang Volume
m² m' m³
Lantai 1.10 24.47 26.92

Area Panjang Volume


m² m' m³
Tangga 2.26 1.00 2.26
INLET 6 JL. SUNAN KALIJAGA (RIGHT STA. 2+600)

Concrete Pile m' 164.16


Panjang titik Tinggi Total
m' m' m' m'
20.52 41.04 4.00 164.16

Reinforcement kg/m 4557.81


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 7.62 24.50 186.62 4.90 38.09 186.62 1.58 1179.42

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.20 24.50 78.40 4.90 16.00 78.40 1.58 247.74

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 38.93 5.00 194.67 1.00 194.67 194.67 1.58 615.14
INLET 6 JL. SUNAN KALIJAGA (RIGHT STA. 2+600)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 756.57
Area Panjang Volume
m² m' m³
Box culvert 8.19 20.52 168.06
Sluice gate 8.63 6.00 51.77
Valve Gate 89.46 6.00 536.74

Pintu
Sluice Gate 2
Valve Gate 2
INLET 6 JL. SUNAN KALIJAGA (RIGHT STA. 2+600)
TAMPUNGAN
Galian m³ 1727.68
Area Panjang Volume
m² m' m³
17.60 25.50 448.77
84.56 15.13 1278.91

Back fill m³ 134.63


Area Panjang Volume
m² m' m³
5.28 25.50 134.63

Timbunan & Pemadatan m³ 365.72


Area Panjang sisi Volume
m² m' m³
7.17 25.50 2.00 365.72

sand m³ 8.77
Area Panjang sisi Volume
m² m' m³
0.10 28.23 2.00 5.65
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 43.87


Area Panjang sisi Volume
m² m' m³
0.50 28.23 2.00 28.23
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 354.45


Area Panjang sisi Volume
m² m' m³
4.04 28.23 2.00 228.13
4.04 15.63 2.00 126.32

Wheep Hole Ø 1 1/2" Distance 1,5m titik 1388.77


Panjang titik sisi Volume
m' titik
28.23 18.82 2.00 1062.88
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 84.75


Panjang Lebar sisi Volume
m' m' m²
28.23 0.97 2.00 54.55
15.63 0.97 2.00 30.20
INLET 6 JL. SUNAN KALIJAGA (RIGHT STA. 2+600)
Concrete K175 (Pagar) m³ 8.05
Area titik sisi Volume
m² m³
0.29 14.12 2.00 8.05

Pagar BRC m' 1941.71


Panjang titik sisi Volume
m' m³
68.77 14.12 2.00 1941.71
INLET 7 ROYAL SOETA (RIGHT STA. 3+500)

DRAIN INLET
Box Culvert m' 39.08
Panjang Jumlah Volume
m' m'
19.54 2.00 39.08

Concrete m³ 50.47
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 4.50 2.00 13.54
dinding tengah 1.24 4.50 5.59
0.81 4.90 3.97

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 4.00 1.00 4.00

Lean Concrete m³ 28.25


Area Panjang Volume
m² m' m³
Lantai 1.10 23.50 25.85

Area Panjang Volume


m² m' m³
Tangga 2.40 1.00 2.40
INLET 7 ROYAL SOETA (RIGHT STA. 3+500)

Concrete Pile m' 156.32


Panjang titik Tinggi Total
m' m' m' m'
19.54 39.08 4.00 156.32

Reinforcement kg/m 7092.21


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 22.50 187.56 4.50 41.68 187.56 1.58 1185.38
dinding tengah 7.39 22.50 166.23 4.50 36.94 166.23 1.58 525.29
5.60 24.50 137.20 4.90 28.00 137.20 1.58 433.55

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 48.95 5.00 244.73 1.00 244.73 244.73 1.58 773.35
INLET 7 ROYAL SOETA (RIGHT STA. 3+500)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 704.17
Area Panjang Volume
m² m' m³
Box culvert 8.19 19.54 160.03
Sluice gate 20.31 6.00 121.84
Valve Gate 70.38 6.00 422.29

Pintu
Sluice Gate 2
Valve Gate 2
INLET 7 ROYAL SOETA (RIGHT STA. 3+500)
TAMPUNGAN
Galian m³ 20855.63
Area Panjang Volume
m² m' m³
20.31 1027.02 20855.63

Back fill m³ 2249.17


Area Panjang Volume
m² m' m³
1.10 515.88 564.88
1.10 508.70 557.02
1.10 519.79 569.17
1.10 509.67 558.09

Timbunan & Pemadatan m³ 1377.42


Area Panjang sisi Volume
m² m' m³
1.80 508.70 914.12
0.91 509.67 463.29

sand m³ 208.53
Area Panjang Volume
m² m' m³
0.10 515.88 51.59
0.10 508.70 50.87
0.10 519.79 51.98
0.10 509.67 50.97
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 1042.65


Area Panjang sisi Volume
m² m' m³
0.50 515.88 257.94
0.50 508.70 254.35
0.50 519.79 259.90
0.50 509.67 254.84
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 7473.72


Area Panjang sisi Volume
m² m' m³
3.58 515.88 1848.90
3.58 508.70 1823.16
3.58 519.79 1862.93
3.58 509.67 1826.67
3.58 15.63 2.00 112.06
INLET 7 ROYAL SOETA (RIGHT STA. 3+500)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 703557.14
Panjang titik sisi Volume
m' titik
515.88 343.92 177418.01
508.70 339.13 172513.74
519.79 346.53 180121.79
509.67 339.78 173177.71
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 2014.40


Panjang Lebar sisi Volume
m' m' m²
515.88 0.97 498.34
508.70 0.97 491.40
519.79 0.97 502.12
509.67 0.97 492.34
15.63 0.97 2.00 30.20

Concrete K175 (Pagar) m³ 145.12


Area titik sisi Volume
m² m³
0.29 254.35 72.49
0.29 254.84 72.63

Pagar BRC m' 35017.60


Panjang titik sisi Volume
m' m³
68.77 254.35 17491.99
68.77 254.84 17525.62
INLET 7 ROYAL SOETA (RIGHT STA. 3+500)
JALAN INSPEKSI TAMPUNGAN
sand m³ 458.27
Area Panjang sisi Volume
m² m' m³
0.45 508.70 228.91
0.45 509.67 229.35

Stone Pitching Size 20cm-30cm m³ 1222.04


Area Panjang sisi Volume
m² m' m³
1.20 508.70 610.43
1.20 509.67 611.61

Base Coarse m³ 152.76


Area Panjang sisi Volume
m² m' m³
0.15 508.70 76.30
0.15 509.67 76.45
INLET 8 CIBADAK (LEFT STA. 4+300)

DRAIN INLET
Box Culvert m' 46.00
Panjang Jumlah Volume
m' m'
23.00 2.00 46.00

Concrete m³ 50.93
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 4.00 2.00 12.03
dinding tengah 1.24 4.00 4.97
0.66 4.90 3.24

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 3.30 2.00 2.97
0.54 4.90 2.64

Area Lebar Volume


m² m' m³
Tangga 3.59 1.00 3.59

Lean Concrete m³ 31.95


Area Panjang Volume
m² m' m³
Lantai 1.10 26.94 29.63

Area Panjang Volume


m² m' m³
Tangga 2.31 1.00 2.31
INLET 8 CIBADAK (LEFT STA. 4+300)

Concrete Pile m' 184.00


Panjang titik Tinggi Total
m' m' m' m'
23.00 46.00 4.00 184.00

Reinforcement kg/m 7106.61


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 20.00 166.72 4.00 41.68 166.72 1.58 1053.67
dinding tengah 7.39 20.00 147.76 4.00 36.94 147.76 1.58 466.92
4.61 24.50 112.87 4.90 23.04 112.87 1.58 356.67

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 16.50 69.30 3.30 21.00 69.30 1.58 437.98
3.80 24.50 93.03 4.90 18.99 93.03 1.58 293.96

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 38.07 5.00 190.34 1.00 190.34 190.34 1.58 601.47
INLET 8 CIBADAK (LEFT STA. 4+300)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 1094.31
Area Panjang Volume
m² m' m³
Box culvert 8.19 23.00 188.37
Sluice gate 20.31 6.00 121.84
Valve Gate 130.68 6.00 784.10

Pintu
Sluice Gate 2
Valve Gate 2
INLET 8 CIBADAK (LEFT STA. 4+300)
TAMPUNGAN
Galian m³ 27669.66
Area tinggi Volume
m² m' m³
9223.22 3.00 27669.66

Back fill m³ 670.00


Area Panjang Volume
m² m' m³
1.10 358.46 392.51
1.10 253.42 277.49

Timbunan & Pemadatan m³ 874.50


Area Panjang sisi Volume
m² m' m³
1.80 358.46 644.15
0.91 253.42 230.35

sand m³ 64.31
Area Panjang Volume
m² m' m³
0.10 358.46 35.85
0.10 253.42 25.34
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 321.57


Area Panjang sisi Volume
m² m' m³
0.50 358.46 179.23
0.50 253.42 126.71
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 2598.29


Area Panjang sisi Volume
m² m' m³
4.04 358.46 1448.17
4.04 253.42 1023.80
4.04 15.63 2.00 126.32
INLET 8 CIBADAK (LEFT STA. 4+300)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 128800.10
Panjang titik sisi Volume
m' titik
358.46 238.97 85661.43
253.42 168.94 42812.77
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 621.27


Panjang Lebar sisi Volume
m' m' m²
358.46 0.97 346.27
253.42 0.97 244.80
15.63 0.97 2.00 30.20

Concrete K175 (Pagar) m³ 87.19


Area titik sisi Volume
m² m³
0.29 179.23 51.08
0.29 126.71 36.11

Pagar BRC m' 21039.86


Panjang titik sisi Volume
m' m³
68.77 179.23 12325.94
68.77 126.71 8713.93
INLET 8 CIBADAK (LEFT STA. 4+300)
JALAN INSPEKSI TAMPUNGAN
sand m³ 275.34
Area Panjang sisi Volume
m² m' m³
0.45 358.46 161.31
0.45 253.42 114.04

Stone Pitching Size 20cm-30cm m³ 734.25


Area Panjang sisi Volume
m² m' m³
1.20 358.46 430.15
1.20 253.42 304.10

Base Coarse m³ 91.78


Area Panjang sisi Volume
m² m' m³
0.15 358.46 53.77
0.15 253.42 38.01
INLET 9 BABAKAN (LEFT STA. 5+000)

DRAIN INLET
Box Culvert m' 69.28
Panjang Jumlah Volume
m' m'
34.64 2.00 69.28

Concrete m³ 48.86
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.50 2.00 10.53
dinding tengah 1.24 3.50 4.35
0.51 4.90 2.50

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 3.60 2.00 3.24
0.63 4.90 3.09

Area Lebar Volume


m² m' m³
Tangga 3.66 1.00 3.66

Lean Concrete m³ 44.79


Area Panjang Volume
m² m' m³
Lantai 1.10 38.59 42.45

Area Panjang Volume


m² m' m³
Tangga 2.34 1.00 2.34
INLET 9 BABAKAN (LEFT STA. 5+000)

Concrete Pile m' 277.12


Panjang titik Tinggi Total
m' m' m' m'
34.64 69.28 4.00 277.12

Reinforcement kg/m 6980.06


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 17.50 145.88 3.50 41.68 145.88 1.58 921.96
dinding tengah 7.39 17.50 129.29 3.50 36.94 129.29 1.58 408.56
3.61 24.50 88.37 4.90 18.04 88.37 1.58 279.25

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 18.00 75.60 3.60 21.00 75.60 1.58 477.79
4.40 24.50 107.80 4.90 22.00 107.80 1.58 340.65

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 41.51 5.00 207.57 1.00 207.57 207.57 1.58 655.92
INLET 9 BABAKAN (LEFT STA. 5+000)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 1358.30
Area Panjang Volume
m² m' m³
Box culvert 8.19 34.64 283.70
Sluice gate 34.40 6.00 206.38
Valve Gate 144.70 6.00 868.22

Pintu
Sluice Gate 2
Valve Gate 2
INLET 9 BABAKAN (LEFT STA. 5+000)
TAMPUNGAN
Galian m³ 1156.25
Area tinggi Volume
m² m' m³
385.42 3.00 1156.25

Back fill m³ 362.61


Area Panjang Volume
m² m' m³
1.10 128.31 140.50
1.10 126.26 138.26
1.10 76.58 83.86

Timbunan & Pemadatan m³ 345.35


Area Panjang sisi Volume
m² m' m³
1.80 128.31 230.57
0.91 126.26 114.77
1.00 76.58 76.58

sand m³ 36.24
Area Panjang Volume
m² m' m³
0.10 128.31 12.83
0.10 126.26 12.63
0.10 76.58 7.66
0.10 15.63 2.00 3.13

Stone Pitching Size 20cm-30cm m³ 181.21


Area Panjang sisi Volume
m² m' m³
0.50 128.31 64.15
0.50 126.26 63.13
0.50 76.58 38.29
0.50 15.63 2.00 15.63

Stone Masonry 1:2:3 m³ 1464.18


Area Panjang sisi Volume
m² m' m³
4.04 128.31 518.37
4.04 126.26 510.11
4.04 76.58 309.38
4.04 15.63 2.00 126.32
INLET 9 BABAKAN (LEFT STA. 5+000)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 25839.42
Panjang titik sisi Volume
m' titik
128.31 85.54 10975.47
126.26 84.18 10628.40
76.58 51.05 3909.66
15.63 10.42 2.00 325.90

Plestering Finishing Cement 1:3 m² 350.10


Panjang Lebar sisi Volume
m' m' m²
128.31 0.97 123.95
126.26 0.97 121.97
76.58 0.97 73.98
15.63 0.97 2.00 30.20

Concrete K175 (Pagar) m³ 47.19


Area titik sisi Volume
m² m³
0.29 64.15 18.28
0.29 63.13 17.99
0.29 38.29 10.91

Pagar BRC m' 11387.03


Panjang titik sisi Volume
m' m³
68.77 64.15 4412.03
68.77 63.13 4341.71
68.77 38.29 2633.28
INLET 9 BABAKAN (LEFT STA. 5+000)
JALAN INSPEKSI TAMPUNGAN
sand m³ 149.02
Area Panjang sisi Volume
m² m' m³
0.45 128.31 57.74
0.45 126.26 56.82
0.45 76.58 34.46

Stone Pitching Size 20cm-30cm m³ 397.38


Area Panjang sisi Volume
m² m' m³
1.20 128.31 153.97
1.20 126.26 151.52
1.20 76.58 91.90

Base Coarse m³ 49.67


Area Panjang sisi Volume
m² m' m³
0.15 128.31 19.25
0.15 126.26 18.94
0.15 76.58 11.49
INLET 10 KUNCORO JAKTI (RIGHT STA. 6+800)

DRAIN INLET
Box Culvert m' 34.44
Panjang Jumlah Volume
m' m'
17.22 2.00 34.44

Concrete m³ 49.06
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 4.30 2.00 12.93
dinding tengah 1.24 4.30 5.34
0.75 4.90 3.68

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.73 1.00 3.73

Lean Concrete m³ 25.62


Area Panjang Volume
m² m' m³
Lantai 1.10 21.16 23.28

Area Panjang Volume


m² m' m³
Tangga 2.35 1.00 2.35
INLET 10 KUNCORO JAKTI (RIGHT STA. 6+800)

Concrete Pile m' 137.76


Panjang titik Tinggi Total
m' m' m' m'
17.22 34.44 4.00 137.76

Reinforcement kg/m 6856.01


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 21.50 179.22 4.30 41.68 179.22 1.58 1132.70
dinding tengah 7.39 21.50 158.84 4.30 36.94 158.84 1.58 501.94
5.20 24.50 127.40 4.90 26.00 127.40 1.58 402.58

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 40.77 5.00 203.85 1.00 203.84 203.84 1.58 644.15
INLET 10 KUNCORO JAKTI (RIGHT STA. 6+800)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 1194.09
Area Panjang Volume
m² m' m³
Box culvert 8.19 17.22 141.03
Sluice gate 38.47 6.00 230.84
Valve Gate 137.04 6.00 822.22

Pintu
Sluice Gate 2
Valve Gate 2
INLET 10 KUNCORO JAKTI (RIGHT STA. 6+800)
TAMPUNGAN
Galian m³ 10574.23
Area tinggi Volume
m² m' m³
2114.85 5.00 10574.23

Back fill m³ 359.50


Area Panjang Volume
m² m' m³
1.10 64.60 70.73
1.10 62.92 68.90
1.10 99.31 108.74
1.10 101.49 111.13

Timbunan & Pemadatan m³ 214.56


Area Panjang sisi Volume
m² m' m³
1.80 62.92 113.07
1.00 101.49 101.49

sand m³ 34.39
Area Panjang Volume
m² m' m³
0.10 64.60 6.46
0.10 62.92 6.29
0.10 99.31 9.93
0.10 101.49 10.15
0.10 15.63 2.00 1.56

Stone Pitching Size 20cm-30cm m³ 171.97


Area Panjang sisi Volume
m² m' m³
0.50 64.60 32.30
0.50 62.92 31.46
0.50 99.31 49.65
0.50 101.49 50.75
0.50 15.63 2.00 7.82

Stone Masonry 1:2:3 m³ 1232.71


Area Panjang sisi Volume
m² m' m³
3.58 64.60 231.51
3.58 62.92 225.50
3.58 99.31 355.92
3.58 101.49 363.75
3.58 15.63 2.00 56.03
INLET 10 KUNCORO JAKTI (RIGHT STA. 6+800)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 19025.58
Panjang titik sisi Volume
m' titik
64.60 43.06 2781.76
62.92 41.95 2639.20
99.31 66.20 6574.59
101.49 67.66 6867.08
15.63 10.42 2.00 162.95

Plestering Finishing Cement 1:3 m² 332.25


Panjang Lebar sisi Volume
m' m' m²
64.60 0.97 62.40
62.92 0.97 60.78
99.31 0.97 95.93
101.49 0.97 98.04
15.63 0.97 2.00 15.10

Concrete K175 (Pagar) m³ 46.78


Area titik sisi Volume
m² m³
0.29 32.30 9.20
0.29 31.46 8.97
0.29 49.65 14.15
0.29 50.75 14.46

Pagar BRC m' 11289.41


Panjang titik sisi Volume
m' m³
68.77 32.30 2221.20
68.77 31.46 2163.53
68.77 49.65 3414.77
68.77 50.75 3489.90
INLET 10 KUNCORO JAKTI (RIGHT STA. 6+800)
JALAN INSPEKSI TAMPUNGAN
sand m³ 73.98
Area Panjang sisi Volume
m² m' m³
0.45 62.92 28.31
0.45 101.49 45.67

Stone Pitching Size 20cm-30cm m³ 197.29


Area Panjang sisi Volume
m² m' m³
1.20 62.92 75.50
1.20 101.49 121.79

Base Coarse m³ 24.66


Area Panjang sisi Volume
m² m' m³
0.15 62.92 9.44
0.15 101.49 15.22
INLET 11 BOJONGCAE (LEFT STA. 7+600)

DRAIN INLET
Box Culvert m' 42.14
Panjang Jumlah Volume
m' m'
21.07 2.00 42.14

Concrete m³ 43.29
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.21

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.68 1.00 3.68

Lean Concrete m³ 29.85


Area Panjang Volume
m² m' m³
Lantai 1.10 25.02 27.52

Area Panjang Volume


m² m' m³
Tangga 2.33 1.00 2.33
INLET 11 BOJONGCAE (LEFT STA. 7+600)

Concrete Pile m' 168.56


Panjang titik Tinggi Total
m' m' m' m'
21.07 42.14 4.00 168.56

Reinforcement kg/m 6306.31


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.20 24.50 78.42 4.90 16.01 78.42 1.58 247.82

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 39.83 5.00 199.17 1.00 199.17 199.17 1.58 629.36
INLET 11 BOJONGCAE (LEFT STA. 7+600)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 916.01
Area Panjang Volume
m² m' m³
Box culvert 8.19 21.07 172.56
Sluice gate 23.85 6.00 143.09
Valve Gate 100.06 6.00 600.36

Pintu
Sluice Gate 2
Valve Gate 2
INLET 11 BOJONGCAE (LEFT STA. 7+600)
TAMPUNGAN
Galian m³ 26789.97
Area tinggi Volume
m² m' m³
8929.99 3.00 26789.97

Back fill m³ 660.07


Area Panjang Volume
m² m' m³
1.10 302.76 331.52
1.10 300.04 328.55

Timbunan & Pemadatan m³ 844.10


Area Panjang sisi Volume
m² m' m³
1.80 302.76 544.06
1.00 300.04 300.04

sand m³ 61.84
Area Panjang Volume
m² m' m³
0.10 302.76 30.28
0.10 300.04 30.00
0.10 15.63 2.00 1.56

Stone Pitching Size 20cm-30cm m³ 309.22


Area Panjang sisi Volume
m² m' m³
0.50 302.76 151.38
0.50 300.04 150.02
0.50 15.63 2.00 7.82

Stone Masonry 1:2:3 m³ 2498.49


Area Panjang sisi Volume
m² m' m³
4.04 302.76 1223.15
4.04 300.04 1212.17
4.04 15.63 2.00 63.16
INLET 11 BOJONGCAE (LEFT STA. 7+600)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 121289.23
Panjang titik sisi Volume
m' titik
302.76 201.84 61109.48
300.04 200.03 60016.80
15.63 10.42 2.00 162.95

Plestering Finishing Cement 1:3 m² 597.41


Panjang Lebar sisi Volume
m' m' m²
302.76 0.97 292.47
300.04 0.97 289.84
15.63 0.97 2.00 15.10

Concrete K175 (Pagar) m³ 85.90


Area titik sisi Volume
m² m³
0.29 151.38 43.14
0.29 150.02 42.76

Pagar BRC m' 20727.98


Panjang titik sisi Volume
m' m³
68.77 151.38 10410.74
68.77 150.02 10317.24
INLET 11 BOJONGCAE (LEFT STA. 7+600)
JALAN INSPEKSI TAMPUNGAN
sand m³ 271.26
Area Panjang sisi Volume
m² m' m³
0.45 302.76 136.24
0.45 300.04 135.02

Stone Pitching Size 20cm-30cm m³ 723.36


Area Panjang sisi Volume
m² m' m³
1.20 302.76 363.31
1.20 300.04 360.05

Base Coarse m³ 90.42


Area Panjang sisi Volume
m² m' m³
0.15 302.76 45.41
0.15 300.04 45.01
INLET 12 PABUARAN (RIGHT STA. 8+100)

DRAIN INLET
Box Culvert m' 39.82
Panjang Jumlah Volume
m' m'
19.91 2.00 39.82

Concrete m³ 43.51
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.21

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.89 1.00 3.89

Lean Concrete m³ 28.63


Area Panjang Volume
m² m' m³
Lantai 1.10 23.86 26.25

Area Panjang Volume


m² m' m³
Tangga 2.38 1.00 2.38
INLET 12 PABUARAN (RIGHT STA. 8+100)

Concrete Pile m' 159.28


Panjang titik Tinggi Total
m' m' m' m'
19.91 39.82 4.00 159.28

Reinforcement kg/m 6364.12


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.20 24.50 78.42 4.90 16.01 78.42 1.58 247.82

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 43.49 5.00 217.46 1.00 217.46 217.46 1.58 687.17
INLET 12 PABUARAN (RIGHT STA. 8+100)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 857.35
Area Panjang Volume
m² m' m³
Box culvert 8.19 19.91 163.06
Sluice gate 23.85 6.00 143.09
Valve Gate 91.87 6.00 551.20

Pintu
Sluice Gate 2
Valve Gate 2
INLET 12 PABUARAN (RIGHT STA. 8+100)
TAMPUNGAN
Galian m³ 19383.05
Area tinggi Volume
m² m' m³
6461.02 3.00 19383.05

Back fill m³ 358.59


Area Panjang Volume
m² m' m³
1.10 165.57 181.30
1.10 161.91 177.29

Timbunan & Pemadatan m³ 459.44


Area Panjang sisi Volume
m² m' m³
1.80 165.57 297.53
1.00 161.91 161.91

sand m³ 34.31
Area Panjang Volume
m² m' m³
0.10 165.57 16.56
0.10 161.91 16.19
0.10 15.63 2.00 1.56

Stone Pitching Size 20cm-30cm m³ 171.56


Area Panjang sisi Volume
m² m' m³
0.50 165.57 82.79
0.50 161.91 80.96
0.50 15.63 2.00 7.82

Stone Masonry 1:2:3 m³ 1386.19


Area Panjang sisi Volume
m² m' m³
4.04 165.57 668.91
4.04 161.91 654.12
4.04 15.63 2.00 63.16
INLET 12 PABUARAN (RIGHT STA. 8+100)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 35915.78
Panjang titik sisi Volume
m' titik
165.57 110.38 18275.84
161.91 107.94 17477.00
15.63 10.42 2.00 162.95

Plestering Finishing Cement 1:3 m² 331.45


Panjang Lebar sisi Volume
m' m' m²
165.57 0.97 159.94
161.91 0.97 156.41
15.63 0.97 2.00 15.10

Concrete K175 (Pagar) m³ 46.67


Area titik sisi Volume
m² m³
0.29 82.79 23.59
0.29 80.96 23.07

Pagar BRC m' 11260.83


Panjang titik sisi Volume
m' m³
68.77 82.79 5693.32
68.77 80.96 5567.51
INLET 12 PABUARAN (RIGHT STA. 8+100)
JALAN INSPEKSI TAMPUNGAN
sand m³ 147.37
Area Panjang sisi Volume
m² m' m³
0.45 165.57 74.51
0.45 161.91 72.86

Stone Pitching Size 20cm-30cm m³ 392.98


Area Panjang sisi Volume
m² m' m³
1.20 165.57 198.69
1.20 161.91 194.29

Base Coarse m³ 49.12


Area Panjang sisi Volume
m² m' m³
0.15 165.57 24.84
0.15 161.91 24.29
INLET 13 KP. CARELANG (RIGHT STA. 9+700)

DRAIN INLET
Box Culvert m' 48.20
Panjang Jumlah Volume
m' m'
24.10 2.00 48.20

Concrete m³ 43.39
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.22

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.76 1.00 3.76

Lean Concrete m³ 33.22


Area Panjang Volume
m² m' m³
Lantai 1.10 28.05 30.86

Area Panjang Volume


m² m' m³
Tangga 2.37 1.00 2.37
INLET 13 KP. CARELANG (RIGHT STA. 9+700)

Concrete Pile m' 192.80


Panjang titik Tinggi Total
m' m' m' m'
24.10 48.20 4.00 192.80

Reinforcement kg/m 6349.36


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.21 24.50 78.52 4.90 16.03 78.52 1.58 248.13

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 42.54 5.00 212.69 1.00 212.69 212.69 1.58 672.10
INLET 13 KP. CARELANG (RIGHT STA. 9+700)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 922.51
Area Panjang Volume
m² m' m³
Box culvert 8.19 24.10 197.38
Sluice gate 31.69 6.00 190.15
Valve Gate 89.16 6.00 534.99

Pintu
Sluice Gate 2
Valve Gate 2
INLET 13 KP. CARELANG (RIGHT STA. 9+700)
TAMPUNGAN
Galian m³ 65627.85
Area tinggi Volume
m² m' m³
21875.95 3.00 65627.85

Back fill m³ 724.15


Area Panjang Volume
m² m' m³
1.10 333.56 365.25
1.10 327.76 358.90

Timbunan & Pemadatan m³ 927.17


Area Panjang sisi Volume
m² m' m³
1.80 333.56 599.40
1.00 327.76 327.76

sand m³ 67.70
Area Panjang Volume
m² m' m³
0.10 333.56 33.36
0.10 327.76 32.78
0.10 15.63 2.00 1.56

Stone Pitching Size 20cm-30cm m³ 338.48


Area Panjang sisi Volume
m² m' m³
0.50 333.56 166.78
0.50 327.76 163.88
0.50 15.63 2.00 7.82

Stone Masonry 1:2:3 m³ 2734.90


Area Panjang sisi Volume
m² m' m³
4.04 333.56 1347.57
4.04 327.76 1324.17
4.04 15.63 2.00 63.16
INLET 13 KP. CARELANG (RIGHT STA. 9+700)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 145956.40
Panjang titik sisi Volume
m' titik
333.56 222.37 74173.96
327.76 218.51 71619.49
15.63 10.42 2.00 162.95

Plestering Finishing Cement 1:3 m² 653.94


Panjang Lebar sisi Volume
m' m' m²
333.56 0.97 322.22
327.76 0.97 316.62
15.63 0.97 2.00 15.10

Concrete K175 (Pagar) m³ 94.24


Area titik sisi Volume
m² m³
0.29 166.78 47.53
0.29 163.88 46.71

Pagar BRC m' 22740.22


Panjang titik sisi Volume
m' m³
68.77 166.78 11469.73
68.77 163.88 11270.49
INLET 13 KP. CARELANG (RIGHT STA. 9+700)
JALAN INSPEKSI TAMPUNGAN
sand m³ 297.59
Area Panjang sisi Volume
m² m' m³
0.45 333.56 150.10
0.45 327.76 147.49

Stone Pitching Size 20cm-30cm m³ 793.59


Area Panjang sisi Volume
m² m' m³
1.20 333.56 400.27
1.20 327.76 393.32

Base Coarse m³ 99.20


Area Panjang sisi Volume
m² m' m³
0.15 333.56 50.03
0.15 327.76 49.16
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)

DRAIN INLET
Box Culvert m' 41.78
Panjang Jumlah Volume
m' m'
20.89 2.00 41.78

Concrete m³ 43.32
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.18

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.73 1.00 3.73

Lean Concrete m³ 29.67


Area Panjang Volume
m² m' m³
Lantai 1.10 24.84 27.32

Area Panjang Volume


m² m' m³
Tangga 2.35 1.00 2.35
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)

Concrete Pile m' 167.12


Panjang titik Tinggi Total
m' m' m' m'
20.89 41.78 4.00 167.12

Reinforcement kg/m 6320.58


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.19 24.50 78.23 4.90 15.97 78.23 1.58 247.20

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 40.78 5.00 203.88 1.00 203.87 203.87 1.58 644.25
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 1323.14
Area Panjang Volume
m² m' m³
Box culvert 8.19 20.89 171.09
Sluice gate 31.69 6.00 190.15
Valve Gate 160.32 6.00 961.91

Pintu
Sluice Gate 2.00
Valve Gate 2.00
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)
TAMPUNGAN
Galian m³ 92036.04
Area tinggi Volume
m² m' m³
18407.21 5.00 92036.04

Back fill m³ 1572.31


Area Panjang Volume
m² m' m³
1.10 282.66 309.51
1.10 289.22 316.70
1.10 429.55 470.35
1.10 434.47 475.74

Timbunan & Pemadatan m³ 1661.17


Area Panjang sisi Volume
m² m' m³
1.80 282.66 507.94
1.00 289.22 289.22
1.00 429.55 429.55
1.00 434.47 434.47

sand m³ 145.15
Area Panjang Volume
m² m' m³
0.10 282.66 28.27
0.10 289.22 28.92
0.10 429.55 42.95
0.10 434.47 43.45
0.10 15.63 2.00 1.56

Stone Pitching Size 20cm-30cm m³ 725.76


Area Panjang sisi Volume
m² m' m³
0.50 282.66 141.33
0.50 289.22 144.61
0.50 429.55 214.77
0.50 434.47 217.23
0.50 15.63 2.00 7.82

Stone Masonry 1:2:3 m³ 5202.28


Area Panjang sisi Volume
m² m' m³
3.58 282.66 1013.05
3.58 289.22 1036.58
3.58 429.55 1539.49
3.58 434.47 1557.13
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)
3.58 15.63 2.00 56.03
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 358041.02
Panjang titik sisi Volume
m' titik
282.66 188.44 53264.07
289.22 192.82 55767.01
429.55 286.36 123005.94
434.47 289.64 125841.05
15.63 10.42 2.00 162.95

Plestering Finishing Cement 1:3 m² 1402.18


Panjang Lebar sisi Volume
m' m' m²
282.66 0.97 273.05
289.22 0.97 279.39
429.55 0.97 414.94
434.47 0.97 419.70
15.63 0.97 2.00 15.10

Concrete K175 (Pagar) m³ 103.13


Area titik sisi Volume
m² m³
0.29 144.61 41.21
0.29 217.23 61.91

Pagar BRC m' 24884.84


Panjang titik sisi Volume
m' m³
68.77 144.61 9945.26
68.77 217.23 14939.58
INLET 14 BOJONG PANDAN (LEFT STA. 10+700)
JALAN INSPEKSI TAMPUNGAN
sand m³ 325.66
Area Panjang sisi Volume
m² m' m³
0.45 289.22 130.15
0.45 434.47 195.51

Stone Pitching Size 20cm-30cm m³ 868.43


Area Panjang sisi Volume
m² m' m³
1.20 289.22 347.07
1.20 434.47 521.36

Base Coarse m³ 108.55


Area Panjang sisi Volume
m² m' m³
0.15 289.22 43.38
0.15 434.47 65.17
INLET 15 DESA WIRANA (RIGHT STA. 12+850)

TAMPUNGAN
Galian m³ 8331.64
Area Panjang Volume
m² m' m³
22.07 377.53 8331.64

Back fill m³ 331.83


Area Panjang Volume
m² m' m³
1.34 247.27 331.83

Timbunan & Pemadatan m³ 444.34


Area Panjang sisi Volume
m² m' m³
1.80 247.27 444.34

sand m³ 24.73
Area Panjang Volume
m² m' m³
0.10 247.27 24.73

Stone Pitching Size 20cm-30cm m³ 123.63


Area Panjang sisi Volume
m² m' m³
0.50 247.27 123.63

Stone Masonry 1:2:3 m³ 886.21


Area Panjang sisi Volume
m² m' m³
3.58 247.27 886.21
INLET 15 DESA WIRANA (RIGHT STA. 12+850)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 40760.98
Panjang titik sisi Volume
m' titik
247.27 164.85 40760.98

Plestering Finishing Cement 1:3 m² 238.86


Panjang Lebar sisi Volume
m' m' m²
247.27 0.97 238.86

Concrete K175 (Pagar) m³ 35.24


Area titik sisi Volume
m² m³
0.29 123.63 35.24

Pagar BRC m' 8502.56


Panjang titik sisi Volume
m' m³
68.77 123.63 8502.56
INLET 15 DESA WIRANA (RIGHT STA. 12+850)

JALAN INSPEKSI TAMPUNGAN


sand m³ 111.27
Area Panjang sisi Volume
m² m' m³
0.45 247.27 111.27

Stone Pitching Size 20cm-30cm m³ 296.72


Area Panjang sisi Volume
m² m' m³
1.20 247.27 296.72

Base Coarse m³ 37.09


Area Panjang sisi Volume
m² m' m³
0.15 247.27 37.09
INLET 16 DESA SANGIANG (RIGHT STA. 16+800)

DRAIN INLET
Box Culvert m' 27.74
Panjang Jumlah Volume
m' m'
13.87 2.00 27.74

Concrete m³ 43.14
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.18

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.55 1.00 3.55

Lean Concrete m³ 21.89


Area Panjang Volume
m² m' m³
Lantai 1.10 17.82 19.60

Area Panjang Volume


m² m' m³
Tangga 2.29 1.00 2.29
INLET 16 DESA SANGIANG (RIGHT STA. 16+800)

Concrete Pile m' 110.96


Panjang titik Tinggi Total
m' m' m' m'
13.87 27.74 4.00 110.96

Reinforcement kg/m 6261.18


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.19 24.50 78.23 4.90 15.97 78.23 1.58 247.20

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 37.02 5.00 185.08 1.00 185.08 185.08 1.58 584.85
INLET 16 DESA SANGIANG (RIGHT STA. 16+800)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 1084.76
Area Panjang Volume
m² m' m³
Box culvert 8.19 13.87 113.60
Sluice gate 22.28 6.00 133.67
Valve Gate 139.58 6.00 837.49

Pintu
Sluice Gate 2.00
Valve Gate 2.00
INLET 16 DESA SANGIANG (RIGHT STA. 16+800)
TAMPUNGAN
Galian m³ 1137.42
Area tinggi Volume
m² m' m³
379.14 3.00 1137.42

Back fill m³ 80.00


Area Panjang Volume
m² m' m³
1.10 24.89 2.00 54.51
1.10 11.64 2.00 25.49

Timbunan & Pemadatan m³ 80.00


Area Panjang Volume
m² m' m³
1.10 24.89 2.00 54.51
1.10 11.64 2.00 25.49

sand m³ 7.31
Area Panjang Volume
m² m' m³
0.10 24.89 2.00 4.98
0.10 11.64 2.00 2.33

Stone Pitching Size 20cm-30cm m³ 36.53


Area Panjang sisi Volume
m² m' m³
0.50 24.89 2.00 24.89
0.50 11.64 2.00 11.64

Stone Masonry 1:2:3 m³ 261.84


Area Panjang sisi Volume
m² m' m³
3.58 24.89 2.00 178.40
3.58 11.64 2.00 83.44
INLET 16 DESA SANGIANG (RIGHT STA. 16+800)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 1006.60
Panjang titik sisi Volume
m' titik
24.89 16.59 2.00 825.95
11.64 7.76 2.00 180.65

Plestering Finishing Cement 1:3 m² 70.57


Panjang Lebar sisi Volume
m' m' m²
24.89 0.97 2.00 48.09
11.64 0.97 2.00 22.49

Concrete K175 (Pagar) m³ 7.09


Area titik sisi Volume
m² m³
0.29 12.44 2.00 7.09

Pagar BRC m' 1711.67


Panjang titik sisi Volume
m' m³
68.77 12.44 2.00 1711.67
INLET 17 PAMARAYAN 1 (RIGHT STA. 18+500)

DRAIN INLET
Box Culvert m' 34.22
Panjang Jumlah Volume
m' m'
17.11 2.00 34.22

Concrete m³ 43.14
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.18

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.55 1.00 3.55

Lean Concrete m³ 25.45


Area Panjang Volume
m² m' m³
Lantai 1.10 21.06 23.17

Area Panjang Volume


m² m' m³
Tangga 2.29 1.00 2.29
INLET 17 PAMARAYAN 1 (RIGHT STA. 18+500)

Concrete Pile m' 136.88


Panjang titik Tinggi Total
m' m' m' m'
17.11 34.22 4.00 136.88

Reinforcement kg/m 6261.18


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.19 24.50 78.23 4.90 15.97 78.23 1.58 247.20

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 37.02 5.00 185.08 1.00 185.08 185.08 1.58 584.85
INLET 17 PAMARAYAN 1 (RIGHT STA. 18+500)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 780.54
Area Panjang Volume
m² m' m³
Box culvert 8.19 17.11 140.13
Sluice gate 22.28 6.00 133.67
Valve Gate 84.46 6.00 506.73

Pintu
Sluice Gate 2.00
Valve Gate 2.00
INLET 17 PAMARAYAN 1 (RIGHT STA. 18+500)
TAMPUNGAN
Galian m³ 1137.42
Area tinggi Volume
m² m' m³
379.14 3.00 1137.42

Back fill m³ 80.00


Area Panjang Volume
m² m' m³
1.10 24.89 2.00 54.51
1.10 11.64 2.00 25.49

Timbunan & Pemadatan m³ 80.00


Area Panjang Volume
m² m' m³
1.10 24.89 2.00 54.51
1.10 11.64 2.00 25.49

sand m³ 7.31
Area Panjang Volume
m² m' m³
0.10 24.89 2.00 4.98
0.10 11.64 2.00 2.33

Stone Pitching Size 20cm-30cm m³ 36.53


Area Panjang sisi Volume
m² m' m³
0.50 24.89 2.00 24.89
0.50 11.64 2.00 11.64

Stone Masonry 1:2:3 m³ 261.84


Area Panjang sisi Volume
m² m' m³
3.58 24.89 2.00 178.40
3.58 11.64 2.00 83.44
INLET 17 PAMARAYAN 1 (RIGHT STA. 18+500)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 1006.60
Panjang titik sisi Volume
m' titik
24.89 16.59 2.00 825.95
11.64 7.76 2.00 180.65

Plestering Finishing Cement 1:3 m² 70.57


Panjang Lebar sisi Volume
m' m' m²
24.89 0.97 2.00 48.09
11.64 0.97 2.00 22.49

Concrete K175 (Pagar) m³ 7.09


Area titik sisi Volume
m² m³
0.29 12.44 2.00 7.09

Pagar BRC m' 1711.67


Panjang titik sisi Volume
m' m³
68.77 12.44 2.00 1711.67
INLET 18 PAMARAYAN 2 (RIGHT STA. 18+600)

DRAIN INLET
Box Culvert m' 58.08
Panjang Jumlah Volume
m' m'
29.04 2.00 58.08

Concrete m³ 43.14
Sluice gate
Area Panjang Volume
m² m' m³
Lantai 2.49 4.90 12.22

Area Tinggi Volume


m² m' m³
dinding samping 1.50 3.30 2.00 9.93
dinding tengah 1.24 3.30 4.10
0.45 4.90 2.18

Valve gate
Area Panjang Volume
m² m' m³
Lantai 1.89 4.90 9.28

Area Tinggi sisi Volume


m² m' m³
dinding samping 0.45 2.10 2.00 1.89

Area Lebar Volume


m² m' m³
Tangga 3.55 1.00 3.55

Lean Concrete m³ 38.56


Area Panjang Volume
m² m' m³
Lantai 1.10 32.98 36.28

Area Panjang Volume


m² m' m³
Tangga 2.29 1.00 2.29
INLET 18 PAMARAYAN 2 (RIGHT STA. 18+600)

Concrete Pile m' 232.32


Panjang titik Tinggi Total
m' m' m' m'
29.04 58.08 4.00 232.32

Reinforcement kg/m 6261.18


Sluice Gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 18.82 24.50 461.02 4.90 94.09 461.02 1.58 2913.62

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 8.34 16.50 137.54 3.30 41.68 137.54 1.58 869.28
dinding tengah 7.39 16.50 121.90 3.30 36.94 121.90 1.58 385.21
3.19 24.50 78.23 4.90 15.97 78.23 1.58 247.20

Valve gate
Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume
m' m' m' m' m' m' kg kg/m
Lantai 12.69 24.50 310.86 4.90 63.44 310.86 1.58 982.30

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
dinding samping 4.20 10.50 44.10 2.10 21.00 44.10 1.58 278.71

Panjang titik Panjang 1 Lebar titik Lebar 1 Berat Volume


m' m' m' m' m' m' kg kg/m
Tangga 37.02 5.00 185.08 1.00 185.08 185.08 1.58 584.85
INLET 18 PAMARAYAN 2 (RIGHT STA. 18+600)
Beronjong m³ 96.00
Panjang 8 Lebar 6
panjang lebar lapisan Volume
Bronjong 2 * 1 * 1 buah buah buah buah m³
2 4.00 6.00 2.00 48.00 96.00

Sand gravel m³ 10.80


Area Panjang Volume
m² m' m³
1.80 6.00 10.80

Bamboo Ø12 titik 108.00


Panjang bamboo Volume
m' titik titik
Horizontal 9.00 6.00 54.00
Vertikal 6.00 9.00 54.00

Galian m³ 633.46
Area Panjang Volume
m² m' m³
Box culvert 8.19 29.04 237.84
Sluice gate 22.28 6.00 133.67
Valve Gate 43.66 6.00 261.94

Pintu
Sluice Gate 2.00
Valve Gate 2.00
INLET 18 PAMARAYAN 2 (RIGHT STA. 18+600)
TAMPUNGAN
Galian m³ 1137.42
Area tinggi Volume
m² m' m³
379.14 3.00 1137.42

Back fill m³ 80.00


Area Panjang Volume
m² m' m³
1.10 24.89 2.00 54.51
1.10 11.64 2.00 25.49

Timbunan & Pemadatan m³ 80.00


Area Panjang Volume
m² m' m³
1.10 24.89 2.00 54.51
1.10 11.64 2.00 25.49

sand m³ 7.31
Area Panjang Volume
m² m' m³
0.10 24.89 2.00 4.98
0.10 11.64 2.00 2.33

Stone Pitching Size 20cm-30cm m³ 36.53


Area Panjang sisi Volume
m² m' m³
0.50 24.89 2.00 24.89
0.50 11.64 2.00 11.64

Stone Masonry 1:2:3 m³ 261.84


Area Panjang sisi Volume
m² m' m³
3.58 24.89 2.00 178.40
3.58 11.64 2.00 83.44
INLET 18 PAMARAYAN 2 (RIGHT STA. 18+600)
Wheep Hole Ø 1 1/2" Distance 1,5m titik 1006.60
Panjang titik sisi Volume
m' titik
24.89 16.59 2.00 825.95
11.64 7.76 2.00 180.65

Plestering Finishing Cement 1:3 m² 70.57


Panjang Lebar sisi Volume
m' m' m²
24.89 0.97 2.00 48.09
11.64 0.97 2.00 22.49

Concrete K175 (Pagar) m³ 7.09


Area titik sisi Volume
m² m³
0.29 12.44 2.00 7.09

Pagar BRC m' 1711.67


Panjang titik sisi Volume
m' m³
68.77 12.44 2.00 1711.67

You might also like