You are on page 1of 1

Name of Work; 6 Unit One Storey (120'x30'x12') Stuff House Construction

Abstract of Costs

Sr. Quantity Unit Particular Rate Per Total of Each


1 4375.00 sqft Site Clearing 800.00 sqft 3,500,000.00
2 6409.81 cuft Earthwork Excavation for Foundation 320.00 cuft 2,051,140.00
3 1343.08 cuft Hardcore Filling 779.00 cuft 1,046,257.86
4 965.67 cuft 1:2:4 RCC Concrete Work 3,756.52 cuft 3,627,567.39
5 984.77 cuft 1:3:6 Lean Concrete 3,677.50 cuft 3,621,475.59
6 2519.49 cuft 1:3 Brick Work For Retaining Wall 4,247.50 cuft 10,701,545.95
7 1446.75 cuft 6" thick Sand Filling 1,696.00 cuft 2,453,688.00
8 964.50 cuft 4" thick 1:3:6 Cement Concrete Flooring 3,677.50 cuft 3,546,948.75
9 361.69 cuft 1 1/2" thick 1:2:4 Cement Concrete Topping 3,756.52 cuft 1,358,686.96
10 2307.00 sqft Formwork 1,082.50 sqft 2,497,327.50
11 3.05 ton Rebar Work 1,195,807.56 ton 3,646,600.79
12 3207.80 sqft Plastering & Pointing 559.60 sqft 1,795,084.88
13 3207.80 sqft Painting Work (3 Coats) 154.00 sqft 493,995.84
14 1747.25 kg Steel Strcuture Framing 6,934.87 kg 12,116,975.49
15 2589.67 Rft Roof Structure Member 2,676.01 Rft 6,929,970.00
16 3206.64 cuft 1:3 Cement Brick Work For Walling 3,386.65 cuft 10,859,778.51
17 16932.00 sqft 1/2" Plastering Work 559.00 sqft 9,464,988.00
18 16932.00 sqft Painting Work Distemper 3 Coats 226.50 sqft 3,835,098.00
19 3480.00 sqft Oil Paint 3 Coats 519.97 sqft 1,809,506.67
20 193.50 Rft Ridging Work 1,600.00 sqft 309,600.00
21 5133.00 sqft Roofing Work 1,298.00 sqft 6,662,634.00
22 320.00 Rft 8"x1" Eave Board 2,100.00 Rft 672,000.00
23 4579.75 sqft Ceiling Work 1,551.76 sqft 7,106,662.84
24 1902.00 sqft Doors and Windows Work 1,838.74 sqft 3,497,280.00
Total 103,604,813.02