Name of Work; Apron & Drain Construction

Detail of Measurement
Measurement Total of
Sr. Particular No No Deduction Content Unit
L (ft) B (ft) H (ft) Each
1 Earthwork Excavation 1 2 128.00 2.75 0.83 584.32 cuft
1 2 38.00 2.75 0.83 173.47 757.79 cuft

2 4" thick 1:3:6 Lean Concrete 1 2 128.00 2.75 0.33 234.67 cuft
1 2 38.00 2.75 0.33 68.97 cuft
1 2 128.00 2.67 0.33 225.28 cuft
1 2 30.00 2.67 0.33 52.87 581.78 cuft

3 1:3 Cement Motar Brick Work 2 2 128.00 0.38 1.00 192.00 cuft
2 2 38.00 0.38 1.00 57.76 249.76 cuft

4 1/2" thick Plastering Work 2 2 128.00 1.00 512.00 sqft


2 2 38.00 1.00 152.00 664.00 sqft