Project: RCC Building Construction Date: 2075/12/9

Place: Code: BLDG 01/075/76


Details of Measurment and Calculation of Quantities
S.N. Description of Work No. Length (m) Breadth (m)Height (m) QuantityRemarks

the area of clearnace is


Initial Site clearance work (shrubs made 3 times to cater the
cutting undulated earth dressing and requirement of staking of
1 lead up to 10m) 3.00 8.25 8.00 198.00 materials
Total 198.00 sqm
Earthwork in excavtion in foundation
2 in hard soil
Column Footing F1 2 1.75 1.75 2.00 12.25
Column Footing F2 6 1.50 1.50 2.00 27.00
Plinth wall foundation
Wall 1 2 2.50 0.60 0.60 1.80
Wall 2 1 2.25 0.60 0.60 0.81
Wall 3 1 1.13 0.60 0.60 0.41
Wall 4 1 1.25 0.60 0.60 0.45
Wall 5 2 1.38 0.60 0.60 0.99
Wall 6 2 1.88 0.60 0.60 1.35
Wall 7 1 2.00 0.60 0.60 0.72
Total 45.78 cum
One layer Flat brick soling on
3 foundation
Column Footing F1 2 1.75 1.75 6.13
Column Footing F2 6 1.50 1.50 13.50
Plinth wall foundation
Wall 1 2 3.70 0.60 4.44
Wall 2 1 3.70 0.60 2.22
Wall 3 1 2.45 0.60 1.47
Wall 4 1 2.45 0.60 1.47
Wall 5 2 2.70 0.60 3.24
Wall 6 2 3.20 0.60 3.84
Wall 7 1 3.20 0.60 1.92
Total 38.23 sqm
4 PCC (1:2:4) on foundation
Column Footing F1 2 1.75 1.75 0.075 0.46
Column Footing F2 6 1.50 1.50 0.075 1.01
Plinth wall foundation 0.00
Wall 1 2 3.70 0.60 0.100 0.44
Wall 2 1 3.70 0.60 0.100 0.22
Wall 3 1 2.45 0.60 0.100 0.15
Wall 4 1 2.45 0.60 0.100 0.15
Wall 5 2 2.70 0.60 0.100 0.32
Wall 6 2 3.20 0.60 0.100 0.38
Wall 7 1 3.20 0.60 0.100 0.19
Total 3.33 cum
Brick work in (1;4) cement sand
4 mortar on plinth wall
Plinth wall foundation
Total plinth walls 1st footing 1 31.00 0.47 0.150 2.19
Total plinth walls 2nd footing 1 31.00 0.35 0.150 1.63
Total plinth walls 3rd footing 1 31.00 0.23 0.295 2.10
Total 5.92 cum
5 RCC Work
Wooden formwork from setting to
i removal
Column Footing F1 2 7.00 0.15 2.10
Column Footing F2 6 6.00 0.15 5.40
Column c1 above footing top and
below tie beam 2 1.20 1.62 3.89
Column c1 above tiebeam and below
ceiling beam 2 1.20 2.65 6.36
Column c2 above footing top and
below tie beam 6 1.20 1.72 12.38
Column c2 above above tiebeam and
below ceiling beam 6 1.20 2.65 19.08
Tiebeam 2 34.0 0.30 20.40
web of ceiling beam 1 34.0 0.73 24.82
Total 94.43 sqm
Reinforcement bars of different dia
cutting bending and tying as per map
ii or instruction
Column Footing F1 mat 16dia bars @
120 mm c/c 60 1.82 @ kg/m 1.58 172.54 No.=(1.75-2*0.04)/0.12+1

Column Footing F2 12dia bars @ of 150


mm c-c 132 1.57 @ kg/m 0.89 184.44 No.=(1.50-2*0.04)/0.15+1
Column c1 up to ceiling beam
20mm dia bars 8 5.58 @ kg/m 2.46 109.81
16mm dia bars 8 5.58 @ kg/m 1.58 70.53

8mm dia ties @ 110 mm cc exterior 392 1.04 @ kg/m 0.39 159.00
4*(0.11^2+0.11^2)^0.5+2*0.
8mm dia ties @ 110 mm cc interior 392 0.78 @ kg/m 0.39 119.59 08