DETAILED ESTIMATE FOR CONSTRUCTION OF PLATFORM AND COOLING TANK

ANNEXURE-B
S. No. Particulars Unit No L (feet) B (feet) H (feet) Quantity Rate Amount
1 Earth work in bulk excavation by mech means (hydraulic
excavator) over areas (Exceeding 30cm in depth 1.5m in width as
well as 10 sqm on plan) including disposal of excavated earth

cum 1.57 262.7 412.44


lead up to 50m and lift up to 1.5m. in all kinds of soil.

Center Line Length=518.98 Rft 1 37 1 1.5 55.50

2 Providing and laying of broken stone layer under foundation


rafts-150mm thick

cum 14.95 1000 14950.00


in foundation

1 37 1 0.5 18.50
in rooms,filling complete job
1 15 7 3 315.00
1 12 1 3 36.00
filling

1 16.25 3.25 3 158.44

3 providing and laying cement concrete of specified


grade including curing but excluding the cost of centring and
shuttering, finishing and reinforcement in Retaining walls in
–1:3:6(1 cemnt:3 coarse sand: 6 graded stone aggregate 20mm

cum 3.97 5733.6 22762.39


nominal size) - Grade M-10

1 37 1 1.000 37.00
1 16 7 0.500 56.00
Mudmat

1 13 1.75 0.330 7.51


Top of plat form

1 10 4 0.500 20.00
1 6 4 0.330 7.92
2 6 1 1.000 12.00
140.43
Base of Boiler Pedistal above top level of platform

4 Brick work with common burnt clay (non-modular) bricks with


class designation 7.5 in foundation and plinth including curing
complete. (extra for work in super structure above plinth level
up to V-floor level is imposed in the rates) Cement mortar

cum 4.99 8100 40419.00


1:6 (1 cement :6 coarse sand)
S. No. Particulars Unit No L (feet) B (feet) H (feet) Quantity Rate Amount
1 37 0.75 3 83.25
outer

2 11 0.75 4 66.00
Tank walls

2 4.5 0.75 4 27.00


176.25

5 Centering and shuttering including strutting and propingetc and


removal of formwork
sqm 8.78 550 4829.00
Walls and Plinth 2 37 1 74.00
1 7 0.5 3.50
1 13 0.5 6.50
1 17 0.5 8.50
1 4 0.5 2.00
62.00
94.50
6
Sqm 54.33 300.45 16323.45
Cement sand plaster in 1:6 mix complete job

Outer Platform 1 37.00 3.5 129.50

1 7.00 16 112.00

1 10.00 4 40.00

tank 2 9.50 4 76.00

2 4.50 4 36.00

2 11.00 4 88.00

2 6.00 4 48.00

2 11.00 0.75 16.50

2 4.50 0.75 6.75

600.33
S. No. Particulars Unit No L (feet) B (feet) H (feet) Quantity Rate Amount
7

Ltr 15.00 130 1950.00


Suply of Rapidate water based antifreeze mixture used for
concrete work, Plaster and brick work complete job

1 15.00 15.00
Total Annexure-B 101646.28