Name of the work- Beautification of Ring road with foot path(one side)with Ghat development from Collector office back side
(new bridge approach) to Marwari para and Balibandha Ghat under , SMC, Sambalpur, W No-32, under Sambalpur
Municipal Corporation
SL
No Items L B H Quantity unit Amount
1- Surface Dressing of the ground in any kind of soil
including removing vegetation inequalities not
exceeding 15 cm depth and disposal of the
rubbish within a lead upto 75 m as directed.
New bridge Aproach. To Marwari para Ghat 1 920.00 21.5 19780.00 sqm
Marwaripara Ghat to Sairendri Nayak Park 1 180.00 21.5 3870.00 sqm
50m Both Side view point 1 100.00 21.5 2150.00 sqm
Total 1200.00 25800.00 sqm
@ Rs 10.60 /sqm Rs 273480.00
2- Dismantling stone masonary in cemetmortar
under 3 M height including stacking the useful old 0.25 920.00 0.5 0.75 86.25 cum
materials for reuse and removing the debris. wall
86.250 cum
@ Rs 976.81 /cum Rs 84249.86
3- Earth work in hard soil within 50 M initial lead
and 1.5 M initial lift including rough dressing and
breaking clods to maximum 5cm to 7cm. And
laying in layers not exceeding 3.0 M in depth and
as per direction of the Engineer-in-charge.
For Kerb Stone Foundation 1 1200.00 0.2 0.20 48.00 cum
Retaining wall Collector Office front -Horizontal 1 52.45 3.00 5.00 786.75 cum
side
Vertical side 2 2.0 3.00 5.00 60.00 cum
(3+7)/2
Column 16 1.50 1.50 1.50 54.00 cum
View Point 1 12.00 8.00 1.50 144.00 cum
Toe Wall infront of Collector office 1 55.00 0.90 1.50 74.25 cum
Toe Wall at view point 1 40.00 0.90 1.50 54.00 cum
1221.00 cum
@ Rs 167.81 /cum Rs 204896.01
4 Filling in foundation or plinth by sand in layers not
exceeding 150mm as directed and consolidating the
same by through saturation with water, ramming
comlete including the cost of supply of sand
For Kerb Stone Foundation 1 1200.00 0.2 0.08 18.00 cum
Retaining wall Collector Office- Horzontal Side 1 52.45 3.0 0.15 23.60
Vertical side 2 2.0 3.0 0.15 1.80
Retaining wall Collector Office front- inside 1 49.85 3.50 6.50 1134.09
(3+8)/2
View point 0.5 14 5.00 9.00 315.00
Toe Wall infront of Collector office 1 55.00 0.90 0.10 4.95 cum
Toe Wall at view point 1 40.00 0.90 0.10 3.60 cum
1501.04
@ Rs 482.47 /cum Rs 724203.46
5 Cement concrete (1:3:6) with 40mm. Size hard
broken CB granite metal including cost,
conveyance & royality of mayerials.
For Kerb Stone Foundation 1 1200.00 0.2 0.08 18.00 cum
Retaining wall 1 52.45 3.0 0.15 23.60 cum
2 2.00 3.0 0.15 1.80 cum
View point 1 14 5.00 0.10 7.00 cum
Fountain 2 0.785 6.25 0.15 1.47 cum
2.5*2.5
Retaining wall Collector Office front- inside 1 49.85 3.50 0.10 17.45 cum
Toe Wall infront of Collector office 1 55.00 0.90 0.10 4.95 cum
Toe Wall at view point 1 40.00 0.90 0.10 3.60 cum
77.87
@ Rs 4113.07 /cum Rs 320292.47
6
Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M-10 grade foundation 150
mm thick, foundation having 50 mm projection beyond
kerb stone, kerb stone laid with kerb laying machine,
foundation concrete laid manually, all complete as per
clause 409 of Specifications for Road & Bridge Works
of MoRT&H (5th Revision). (The rate is inclusive of
cost of all materials, labour, hire and usage charges of
machinery and all incidental charges in this
connection.)
1 1200.00 0.15 0.45 81.00 cum
@ Rs 5399.11 /cum Rs 437327.91
7 Supplying & laying interlocking designer paver
block of any shade and of approved quality as per
IS: 1237-1980 laid in pattern as directed in
pavement, footpath, driveway, etc including
necessary underlay complete in all respect with
all labour and material. [Border concrete if
necessary to be paid separately] (a) 40 mm thick
block (over 150 mm medium sand bed including
cost of sand but excluding cost of earthwork in
excavation or dismantling of existing hard
surface if necessary)
New bridge App. To Marwari para Ghat 1 920.00 1.6 1472.00 sqm
Marwaripara Ghat to Sairendri Nayak Park 1 180.00 1.6 288.00 sqm
50m Both Side view point 1 100.00 1.6 160.00 sqm
1920.00
@ Rs 944.49 /sqm Rs 1813416.90
8- Cement concrete (1:2:4) with 12mm. Size hard
broken CB granite chips including cost,
conveyance & royality of mayerials.
For Kerb Stone side filling 1 1200.00 0.05 0.15 9.00 cum
Toe Wall infront of Collector office 1 55.00 0.55 1.50 45.38 cum
Toe Wall at view point 1 40.00 0.55 1.50 33.00 cum
(0.75+0.35)/2 87.38
@ Rs 5399.11 /cum Rs 471747.24
9- (a)Supply , fittings & fixing of baluster of plain
cement concrete with (1:1½:3) with stone Foot
chips(floral or intricate pattern of height not (1200/0.25)+1 4,801 nos
Path
exceeding 1200 mm)
25 Priming one coat with any approved primer path 1200.00 4.30 5160.00 sqm
Pillar 136 1.00 0.75 102.00 sqm
Kerb Stone 1 1200.00 0.4 480.00 sqm
5742.00 sqm
@ Rs 54.63 /sqm Rs 313685.46
ELECTRICAL WORKS
Rs /no
Supply, fixing, testing and commissioning of the
46 double door type Outdoor Street Lighting Switch 3 Each @ 23900.00 Rs 71700.00
Board(IP 55).
Commissioner,
SMC Sambalpur
Name of the work- Beautification of Ring road foot path with foot path (One side ) with Ghat development from New bridge
apporach towards Marwaripara Ghat under Sambalpur Municipal Corporation
A Footpath
Length of road =920 M
Width of footh path = 1.5 M
E Developments
Length of Ghat = M
Detailed Estimate
1- Surface Dressing of the ground in any kind of soil
including removing vegetation inequalities not
exceeding 15 cm depth and disposal of the rubbish Foot
1 920.00 21.5 19780.00 sqm
within a lead upto 75 m as directed. path
1380.00
@ Rs 914.47 /sqm Rs 1261968.60
3 Dismantling brick or stone masonary in
cemetmortar under 3 M height including stacking Side
the useful materials for reuse and removing the 1 920.00 0.5 0.75 345.00
wall
debris.
cum
345.000 cum
@ Rs 744.82 /cum Rs 256962.90
4 Filling in foundation or plinth by silver sand in
layers not exceeding 150mm as directed and
consolidating the same by through saturation with
water, ramming comlete including the cost of 1 60 2.5 0.1 15.00 cum
supply of sand
538.108 cum
@ Rs 3523.76 /cum Rs 1896163.45
9 Supplying all labour, materials ,T&P and providing
Cement concrete M25 grade (1:1½:3) with crusher
broken hard granite chips of 20mm & down grade
size for RCC works including cost of conveyance &
royalty ,sundries , watering ,curing &lifting
&laying concrete at a height of 5mtr contractor
profit & labour cess. Maximum complete etc. all
complete(Excluding cost of reinforcement &
centering & shuttering)
Foot
Path 2 920.00 0.375 0.1 69.000 cum
footing 1 60.00 2.500 0.35 52.500 cum
wall 0.5 1 60.00 2.850 0.3 51.300 cum
beam 1 60.00 0.375 0.25 5.625 cum
Type-2
footing 1 90.00 1.950 0.3 52.650 cum
wall 1 90.00 1.700 0.25 38.250
beam 1 90.00 0.250 0.375 8.438
Top beam 1 90.00 0.200 0.375 6.750
Base 5 0.20 2.000 1.225 2.450
286.963 Cum
@ Rs 4234.75 /cum Rs 1215214.45
10-
Supplying fitting and placing uncoated HYSD bar
reinforcement complete as per drawing and
technical specification. foot path 69.00 0.01 7.85 5.42
222.46 0.015 7.85 26.19
31.61 316.11 qtl
316.11
@ Rs 6869.90 /QTL Rs 2171655.42
11
Rigid & smooth centering & shuttering for RCC
work including false works and dismantling them
after casting including cost of materials complete in
ground floor. foot path 1 920.00 0.55 506.00 Sq.m
1 920.00 0.20 184.00 Sq.m
Type-1Footing 2 60.00 0.45 54.00 Sq.m
wall 2 60.00 2.85 342.00 Sq.m
beam 1 60.00 0.875 52.50 Sq.m
beam 1 60.00 0.775 46.50 Sq.m
Type-2Footing 2 90.00 0.40 72.00 Sq.m
wall 2 90.00 1.70 306.00 Sq.m
beam 1 90.00 0.875 78.75 Sq.m
beam 1 90.00 0.775 69.75 Sq.m
For fountain Base 2 0.20 6.25 2.50 Sq.m
1,714.00 sqm
@ Rs 340.17 /sqm Rs 583050.70
12 Supplying and laying 400 G Polythene Sheet below
flooring. Foot path Same as item shuttering 506.00 Sq.m
506.00 sqm
@ Rs 17.00 /sqm Rs 8602.00
13 16mm thick cement plaster (1:6) over brick or stone
masonary
New Brick Work foot path 920.00 1.5 1380 Sq.m
Top beam 920.00 0.5 460 Sq.m
Pillar 184 2 0.55 202.4 Sq.m
Collector office front 1 60 3.425 205.5 Sq.m
(2*1.15+3*.375)
Collector office front 1 90 3.425 308.25 Sq.m
(2*1.15+3*.375)
2556.15 sqm
@ Rs 135.57 /sqm Rs 346537.26
5
Filling foundation and plinth with excavated Earth
inluding watering and ramming (a) With earth obtained Same as excavation
from excavation of foundation.
435.60 cum
@ Rs 74.60 /cum Rs 32495.76
15 Priming one coat with any approved primer Foot path 920.00 3.70 3404.00 sqm
Pillar 184 2.00 0.55 202.40 sqm
44.4+23.6
same as plaster in front of Collector office 513.75 sqm
4120.15 sqm
@ Rs 40.69 /sqm Rs 167648.90
Trees plantation @3.5 M C/C foot path 920.00 ÷ 3.5 263 nos
Trees Piller 8 6 48 nos
in front of Collector office 13
324
@ Rs 103.00 /nos Rs 33357.29
b) trees with earthen pots 920.00 ÷ 10 92 nos
48
in front of Collector office 13
153 nos
@ Rs 78.00 /nos Rs 11934.00
Foot
path 920.00 0.75 690.00
2 45 1 90.00
1 9.7 1.57 15.23
795.23 Sqm
Rs 20049.00 /100sqm Rs 159435.46
21 Supplying, fitting & fixing granite slabs 15mm to
18 mm. thick with uniform texture & without
decorative veins in columns, wall, facia etc. with 15
mm thick [avg] cement mortar (1:2) including
making suitable arrangements to hold the stones
properly by brass / copper hooks including pointing
in cement mortar (1:2) (1 white cement : 2 marble
dust) with admixture of pigment matching the stone
shades all complete as per direction of the
Engineer-in-charge including cost of all materials,
labours, scaffolding, staging, curing and roughening
of concrete surface complete. [Using cement slurry
at back side of granite @ 4.4 kg/sq.m
& white cement slurry for joint filling @ 1.8
kg/sq.m]
0.5 2.2 6.245 6.870 sqm
6.87
Rs 2685.00 /sqm Rs 0.00
22 Supplying, fitting and fixing vertified tile in floors
of size 600mm x 600mm of approved make with
application of polymer modified cement based
water resistant adhesive bed of required thickness of
10mm and filling joints with epoxy grout of
approved quality including cost of all materials,
labour T&P etc required for the work
Rs /no
Supply & Fixing Decorative Light Fittings with
2) 40Watt LED Fittings complete connection. (Make- 120 No. @ 14199.00 Rs 1703880.00
Crompton, Model-Maple-LPTO-40-CDL)
Rs /no
Supply & Fixing of Bollarads Light with 10Watt
3) LED complete connection. (Make-Crompton, 65 No. @ 7449.00 Rs 484185.00
Model-Liara-LBLS1-10-CDL)
Rs /no
Supply & Fixing of Pathway Light of LED
4) complete connection. (Make-Crompton, 40 No. @ 6299.00 Rs 251960.00
Model-Trisha-LBLM06WW)
Rs /no
Supply & Fixing of Monument/Bush Light of LED
5) complete connection. (Make-Crompton, Model- 40 No. @ 12699.00 Rs 507960.00
Disha-LFLM18WW)
Rs /no
Supply, fixing, testing and commissioning of the
14) double door type Outdoor Street Lighting Switch 3 Each @ 23900.00 Rs 71700.00
Board(IP 55).
16132179.24
Add 12% GST 1935861.51
18068040.74
Limited to Rs 9900000.00
(Rupees Ninty Nine Lakhs Only)
Commissioner, Administrator,
SMC Sambalpur SMC, Sambalpur
Name of the work- Beautification of Ring road foot path with foot path (One side ) with Ghat development from Marwaripara
Ghat towards Balibandha(Rajghat) under Sambalpur Municipal Corporation
A Footpath
Length of road =500 M
Width of footh path = 1.5 M
E Developments in Marwaripara Ghat
Length of Ghat = 28.775 M
Detailed Estimate
1- Surface Dressing of the ground in any kind of soil
including removing vegetation inequalities not exceeding
15 cm depth and disposal of the rubbish within a lead Foot path 1 500.00 21.5 10750.00 sqm
upto 75 m as directed.
821.76
@ Rs 1022.55 /sqm Rs 840290.69
3 Dismantling brick or stone masonary in clay under 3 M
height including stacking the useful materials for reuse
and removing the debris. Change
2.137 0.3 3.625 3 6.97
room
cum
step 0.5 2.137 3.625 3 11.62 cum
18.592 cum
@ Rs 833.31 /cum Rs 15492.82
4 Filling in foundation or plinth by silver sand in layers not
exceeding 150mm as directed and consolidating the same Change
by through saturation with water, ramming comlete room 0.5 1.5 3.625 3 8.16
including the cost of supply of sand cum
B) Brick work at Marwari Para Ghat 6 28.775 0.375 0.15 9.712 cum
M.P Ghat
48 0.375 0.375 0.55 3.713 cum
3 Change room
Temple
Col out side 4 1 2.1 8.40 sqm
Brick work 2 10 0.85 17.00 sqm
beam 1 0.95 20 19.00 sqm
1738.92037 sqm
@ Rs 151.68 /sqm Rs 263759.44
Stripping off worn out plaster and reking out joints of
walls, ceiling etc after any height and in any floor
14 foot path 500.00 0.6 300 sqm
incliuding removing rubbish with in a lead off 75 M as
directed. (50% of old work)
@ Rs 21.28 /sqm Rs 6384.00
15 Priming one coat with any approved primer Foot path 500.00 3.70 1850.00 sqm
250 0.60 150 sqm
Pillar 100 2.00 0.55 110.00 sqm
Over Plaster MP ghat 101.466
Over Plaster change room 126.36 3 379.08
Over Plaster Temple 68.00
2658.55 sqm
@ Rs 45.52 /sqm Rs 121017.01
Trees plantation @3.5 M C/C foot path 500.00 ÷ 3.5 143 nos
Trees Piller 8 6 48 nos
191
@ Rs 115.36 /nos Rs 22017.28
b) trees with earthen pots 500.00 ÷ 10 50 nos
ghat 48
98 nos
@ Rs 87.36 /nos Rs 8561.28
MP ghat
On steps 88 0.4 101.42 3569.984 sqm
rising 30 0.15 102.42 460.89 sqm
On Landing 1 1.8 101.42 182.556 sqm
On Landing 1 1.5 101.42 152.13 sqm
4365.56
Rs 661.20 /sqm Rs 2886508.27
30 20mm thick cement plaster (1:4) - Inside
Change Room -Inside
4*4*1.500*(2.1+0.250) 16 1.5 2.35 56.4 sqm
4*2*1.500*0.663 8 1.5 0.663 7.956 sqm
64.356
Rs 174.80 /sqm Rs 11249.43
25 6mm thick cement plaster (1:4) to R.C.C. surfaces
finished smooth including closed deep chipping & slurry
treatment.
Celling of Change room 1 1.288 1.288 3.00 4.98 sqm
Slope Slab=4*0.5*(4.51+1.288)*1.611 2 5.798 1.611 3.00 56.04 sqm
33 Estimate for Land scape Light and Area Light As per Estmimate attached 1781466.71
9703952.27
Limited to Rs 9900000.00
(Rupees Ninty Nine Lakhs Only)
Commissioner, Administrator,
SMC Sambalpur SMC, Sambalpur
Name of the work- Beautification of Ring road foot path with Ghat development from Samlei mandir to Rajghat
A Footpath
Length of road =773 M
Width of footh path = 1.5 M
3,093 nos
@ Rs 383.04 /no Rs 1184742.72
8
Brick work with Fly ash Brick 25cm x 12cm x 8cm size
having crushing strength not less than 75 Kg./Cm2 with
dimentional tolerance + 8% in cement mortar (1:6) in
foundation & plinth. Foot Path 1 773.00 0.375 0.15 43.481 cum
A) Nos of brick Pillar: 773/5.0 = 100 154.6 0.5 0.38 0.55 16.156 cum
Continuation of Existing Brick Work 50% 773.00 0.5 0.3 57.975 cum
117.612 cum
@ Rs 3938.46 /cum Rs 463209.96
9 RCC (1:1.5:3) work with 12mm black hard granite
(crusher broken) stone chips including hoisting & laying.
15 Priming one coat with any approved primer Foot path 773.00 3.70 2860.10 sqm
386.5 0.60 231.9 sqm
3092.00 sqm
@ Rs 45.52 /sqm Rs 140747.84
Trees plantation @3.5 M C/C foot path 773.00 ÷ 3.5 221 nos
221
@ Rs 115.36 /nos Rs 25478.08
b) trees with earthen pots 773.00 ÷ 10 77.3 nos
77 nos
@ Rs 87.36 /nos Rs 6752.93
34- Estimate for Land scape Light and Area Light As per Estmimate attached 432023.00
5465514.92
Limited to Rs 9900000.00
(Rupees Ninty Nine Lakhs Only)
#REF!
Commissioner, Administrator,
SMC Sambalpur SMC, Sambalpur
ABSTRACT
Beautification of Ring road with foot path(one side)with Ghat development from Collector
office back side (new bridge approach) to Marwari para and Balibandha Ghat under , SMC,
Sambalpur, W No-32, under 14th FC 2018-19
Sl No Description Amount
1 Civil Work-
Land scaping and One side Foot path for 1100 mtr , One view
point & Development infront Collector Office (New gate side) 20092688.05
2
Electrical work-
Cable Laying , wiring to all Points and Fixing light , as per 2158836.00
estimate.
Total 22321524.05
Add GST 12% 2678582.89
25000106.94
Limited to Rs 25000000.00
Commissioner,
SMC Sambalpur