As per field Report

Measurement Sheet
Project Name: Bhaluwahi khola River training work
Location: Rajbiraj

S.No. Iteam Description No. Length Breadth Height Quantity Unit Remarks
No.

Ch 1+600 to 2+250

1.1 Earth work in excavation in trenches


Foundation
retaining wall 1 400.00 2.5 1.5 1500.00

Total 1,500.00 Cum


2 Earth work filling
back filling 1 400.00 0.85 3.25 1105.00
Total 1,105.00 Cum
3 PCC 1:3:6
retaining wall 1 400.00 2.5 0.1 100.00
Total 100.00 cum
4 PCC (1:1.5:3) for RCC works

wall verticle portion 1.0 400.00 0.2 3.80 304.00


in tringular portion wall 1.0 200.00 0.1 3.80 76.00
in tringular portion wall 1.0 200.00 0.15 3.80 114.00
for bottom toe nd hell 1.0 400.00 2.4 0.25 240.00
Total 734.00 cum
5 Steel works
for stem portion
16 mmdia @25 c/c 1601.0 4.75 1.57 11939.46
16 mmdia @25 c/c 1601.0 5.45 1.57 13698.96
12 mmdia distribution bar 26.0 400.00 0.88 9152.00
for toe portion
16 mmdia top bar @25 c/c 1601.0 1.97 1.57 4951.73
12 mmdia distribution bar 10.0 400.00 0.88 3520.00
12 mmdia chair bar 1200.0 2.55 0.88 2692.80

Total 45,954.95 cum

2.4 6.00 Wooden Form work


for toe slab 2 350 0.25 175.00
for wall 2 350 2.4 1680.00
Total 1,855.00 m2

Submitted By: Checked By: Re-Checked By: Approved By:


Project Name: Bhaluwahi khola River training work
Location: Rajbiraj

S.No. Iteam
No. Description No. Length Breadth Height Quantity Unit Remarks

Ch 1+600 to 2+250

1.1 Earth work in excavation in trenches


Foundation
retaining wall 1 400.00 2.5 1.5 1500.00
toe slab 1 400.00 0.4 0.8 128.00

Total 1,628.00 Cum


2 Earth work filling
back filling 1 400.00 1 3.25 1300.00
Total 1,300.00 Cum
3 PCC 1:3:6
retaining wall 1 400.00 2.5 0.1 100.00
Total 100.00 cum
4 PCC (1:1.5:3) for RCC works

wall verticle portion 1.0 400.00 0.2 4.20 336.00


in tringular portion wall 1.0 400.00 0.15 4.20 252.00
for bottom toe nd hell 1.0 400.00 2.5 0.30 300.00
for share key 1.0 400.00 0.4 0.80 128.00
Total 1,016.00 cum
5 Steel works
for stem portion
16 mmdia @25 c/c 2001.0 5.68 1.57 17844.12
16 mmdia @25 c/c 2001.0 6.02 1.57 18912.25
12 mmdia distribution bar 30.0 400.00 0.89 10680.00
for toe portion
16 mmdia top bar @25 c/c 2224.0 1.97 1.57 6878.61
12 mmdia distribution bar 20.0 400.00 0.89 7120.00
for share key 1334.0 0.35 1.57 733.03
for share key 8.0 400.00 0.89 2848.00
12 mmdia chair bar 2000.0 2.55 0.89 4539.00

Total 69,555.01 cum

2.4 6.00 Wooden Form work


for toe slab 2 400 0.3 240.00
for wall 2 400 2.95 2360.00
shar key 2 400 0.8 640.00
Total 3,240.00 m2
Comprative chart

Iteam Uni as per final bill As per field Diffrence


Description of work Remarks
No. t Quantity Rate Amount Quantity Amount Quantity Amount
A Ch 1+600 to 2+250
1.0 Earth work in excavation in trenches cum 1,628.00 50.00 81,400.00 1,500.00 75,000.00 128.00 6,400.00
2.0 Earth work filling cum 1,300.00 170.00 221,000.00 1,105.00 187,850.00 195.00 33,150.00
3.0 PCC 1:3:6 cum 100.00 6,900.00 690,000.00 100.00 690,000.00 0.00 -
4.0 PCC (1:1.5:3) for RCC works cum 1,016.00 9,250.00 9,398,000.00 734.00 6,789,500.00 282.00 2,608,500.00
5.0 Steel works kg 69,555.01 85.00 5,912,175.85 45,954.95 3,906,170.33 23600.07 2,006,005.53
6.0 Wooden Form work sqm 3,240.00 220.00 712,800.00 1,855.00 408,100.00 1385.00 304,700.00
17,015,375.85 12,056,620.33 4,958,755.53 -
B General items -
1.0 Insurance ls 1.00 100,000.00 100,000.00 1.00 100,000.00 - -
2.0 commission ls 0.50 25,000.00 12,500.00 0.50 12,500.00 - -
3.0 lab test ls 0.50 25,000.00 12,500.00 0.50 12,500.00 - -
125,000.00
Sub Total For (D) 125,000.00 125,000.00 -
Total A+B) 17,140,375.85 - 12,181,620.33 - 4,958,755.53 -
VAT @ 13 % of Total Amount 2,228,248.86 - 1,583,610.64 - 644,638.22 -
Net Total Amount in Nrs. 19,368,624.71 - - 5,603,393.74