9.30 m3
say.9.50 m3 @Rs.4420/- per m3 RS.41,990/-
4) Random rubble in cement mortar 1:8 for foundation &
basement of walls, including cost of all materials,
labour charges, etc complete.
foundation 3 11.00 0.60 0.60 11.88
2 3.50 0.60 0.60 2.52
Crosswall 4 9.00 0.60 0.60 12.96
1 4.00 0.60 0.60 1.44
sitout 2 1.50 0.60 0.60 1.08
1 3.56 0.60 0.60 1.28
Basement
Walls around 1 39.00 0.45 0.30 5.27
36.43 m3
say.36.5 m3 @Rs.2450/- per m3 RS.89,425/-
8)
R.C.C, 1:2:4, using 20mm brocken stone for lintel,
shade, columns,Beams etc, including cost of all
materials, labor charges, etc complete, but excluding
cost of steel re-inforcement & its labor charges
etc………. complete.
a) Ground floor
Lintel Walls around 1 39.00 0.23 0.15 1.35
1 5.70 0.24 0.15 0.21
Columns 2 4.35 0.23 0.23 0.46
Beam 1 7.5 3.00 0.23 5.18
kitchen slab 1 7.08 0.83 0.10 0.59
loftslab 4 3.56 0.83 0.10 1.18
sunshade 1 16.82 0.73 0.08 0.98
level roof slab 1 11.82 5.82 0.10 6.88
slope roof
90m2x 0.1=9.0m3 9.00
25.82 m3
say.26.0 m3 @Rs.7900/- per m3 RS.2,0,5400/-
778.41 m2
(-)less deduct for openings
D1 6 0.90 2.10 11.34
D2 2 0.75 2.10 3.15
W3 6 1.50 1.50 13.50
FW1 2 1.00 1.95 3.90
KW3 1 1.50 1.10 1.65
KW2 1 1.00 1.10 1.10
V2 2 1.10 0.60 0.66
Total less deduction for 35.30 m2
35.30 x 2 70.60 m2
say.710.00 m2 @Rs.260 per m2 RS.1,84,600/-
22.89 m2
say.22.90 m2 @Rs.780/- per m2 RS.17,860/-
say.38.00 m2 @Rs.900/- per m2
18)
Providing & fixing pre- polished granite slab of
approved colour & quality over a plastering with
cement mortar 1:3, 15 mm thick, to kitchen
slab,including bevelling, moulding, etc including
cost of all materials, labor charges, etc.. complete.
3.84 m2
say.3.84m2 @Rs.1950/- per m2 RS.7,500/-
19) Floor finish with approved colour & quality antiskid
ceramic tiles for all toilets, over a plastering with
cement mortar 1:3, 15 mm thick, including cost of all
materials, labor charges, etc complete.
a) Ground floor
Toilets 2 1.75 1.35 4.73
Err:522 m2
say.4.73m2 @Rs.600/- per m2 RS.2,838/-
20)
Floor finish with approved colour & quality
2 x 2 ceramic tiles for all rooms,kitchen,sitout over a
plastering with cement mortar 1:3, 15 mm thick,
including cost of all materials, labor charges, etc
complete.
Sit out 1 3.56 1.50 5.34
hall 1 3.40 8.30 28.22
Bedroom 3 3.30 3.46 11.41
Kitchen 1 3.46 3.30 11.41
56.38 m2
say.57.0m2 @Rs.560/- per m2 RS.31,920/-
21) Painting with two coat of synthetic enamel paint over
a coat of metal primer for all window grills, including
cost of all materials, labor charges, etc…..complete.
window grill
20.00 m2
say.20.00 m2 @Rs. 700/- per 10m2 RS.14,000/-
22) Providing two coat of lacquer polish to all doors,
windows & ventilators, after cleaning the surface &
applying necessary sand papering, sealer, filler, etc.
complete.
D1 6 0.90 2.10 11.34
D2 2 0.75 2.10 3.15
W3 6 1.50 1.50 13.50
FW1 2 1.00 1.95 3.90
KW3 1 1.50 1.10 1.65
KW2 1 1.00 1.10 1.10
V2 2 1.10 0.60 0.66
35.30 m2
say.35.30 m3 @Rs. 510/- per m3 RS.18,000/-
23)
providing & fixing of terra cotta tiles over sloping RCC
roof slab including cost of all materials its labour charges
for fixing and two coat of weather proof painting etc
complet.
ground floor sloppinng roof 93.00 m2
93.00 m2
say.93.0 m2 @R.290/- per m2 RS.26,970/-
24)
Plumbing and electrification
L.S RS.1,10,000/-
S.Tank RS.15,000/-
25) Other unforeseen items RS.487/-
TOTAL RS.12,96,000/-