DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
7 Neat Cement
Same As Plaster 1129.50 Sq.M.
8 Shuttering
1.0 753.0 0.525 395.33
2.0 753.0 0.2 301.20
696.53 Sq.M.
9 Concrete : M20
1.0 753.0 0.9 0.110 74.55 Cum
10 Reinforcement 5851.94 Kg
C Fire Tank, 2No-4.0mX7.0mX2.0m(clr)
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
1 Earth Work
Footing Size:- 2.0 4.5 7.5 2.6 175.50 Cum
6 Reinforcement
1.15% Of Concrete Volume 1830.5 Kg
1.83 M.T.
8 Plastering
Outer Face 2.0 28.00 2.15 120.40
Base 2.0 4.0 7.0 56.00
176.40 Sq.M.
5 Plastering
Inside 2.0 140.0 0.5 140.00
Base 1.0 140.0 0.5 70.00
210.00 Sq.M.
6 Neat Cement
Same As Plaster 210.00 Sq.M.
7 Shuttering
1.0 140.0 0.525 73.50
2.0 140.0 0.2 56.00
129.50 Sq.M.
8 Concrete : M20
1.0 140.0 0.9 0.110 13.86 Cum
9 Reinforcement 1088.01 Kg
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
1 Earth Work
Footing Size:-1.05x1.05x1.05 215.0 1.05 1.05 1.05 248.89
Tie Beam 1.0 527.25 0.25 0.3 39.54
288.43 Cum
2 Earth Work in Filling 190.3659 Cum
3 S.B.F.S. 215.0 1.05 1.05 237.04
1.0 527.25 0.25 131.81
368.85 Sq.M.
4 Hire & Labour Charges
Footing 215.0 4.2 0.15 135.45
Pedestal 215.0 1.6 0.525 180.60
Column 215.0 1.0 1.5 322.50
Tie Beam 1.0 753.0 0.3 225.90
864.45 Sq.M.
5 Ordinary Cement Concrete , M-20
Footing 215.0 1.05 1.05 0.175 41.48
Pedestal 215.0 0.40 0.4 0.525 18.06
Column 215.0 0.25 0.25 1.5 20.16
Tie Beam 1.0 753.00 0.25 0.3 56.48
136.17 Cum
6 Reinforcement
1.15% Of Concrete Volume 12293.0 Kg
12.293 M.T.
9 Plastering
Outer Face 1.0 753.00 1.5 1129.50
Inside 1 806.75 1.5 1210.13
Top 1 806.75 0.25 201.69
2541.31 Sq.M.
10 Neat Cement
both side 2.0 753.00 0.6 903.60
11 Primer
Same As Plaster 1637.71 Sq.M.
ROAD WORK
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
Total No Of Pit
1 IP(W) 45
2 IP(S) 40
3 RAIN WATER PIPE 40
Total 125 NoS
Inspection pit
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
1 Earth Work
Footing Size:-1.05x1.05x1.05 2.0 15.5 5.5 2.6 443.30 Cum
6 Reinforcement
1.15% Of Concrete Volume 4623.7 Kg
4.62 M.T.
7 250mm Brick Work
2.0 46.25 0.25 2.15 49.72 Cum
8 Plastering
Outer Face 2.0 50.00 2.15 215.00
Base 2.0 15.0 5.0 150.00
365.00 Sq.M.
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
1 Earth Work
Footing Size: 2.0 3.625 4.5 2.6 84.83 Cum
6 Reinforcement
1.15% Of Concrete Volume 883.6 Kg
0.88 M.T.
8 Plastering
Outer Face 2.0 22.25 2.15 95.68
Base 2.0 3.1 4.0 25.00
120.68 Sq.M.
SL
DESCRIPTION OF ITEM NO. L (m) B (m) H (m) Area(m2) Unit
NO.
1 Earth Work
Footing Size: 1.0 10.5 5.5 2.6 150.15 Cum
2 Sand Filling 1.0 10.5 5.5 0.075 4.33 Cum
3 S.B.F.S. 1.0 10.5 5.5 57.75 Sq.M.
4 Hire & Labour Charges
Footing 2.0 32.0 0.125 8.00
Slab 1.0 32.0 0.175 5.60
1.0 10.5 5.5 57.75
71.35 Sq.M.
5 Ordinary Cement Concrete , M-20
Footing slab 1.0 10.500 5.5 0.125 7.22
Top Slab 1.0 10.500 5.5 0.175 10.11
17.33 Cum
6 Reinforcement
1.15% Of Concrete Volume 1564.0 Kg
1.56 M.T.
7 250mm Brick Work
1.0 36.25 0.25 2.15 19.48 Cum
8 Plastering
Outer Face 1.0 43.00 2.15 92.45
Base 1.0 10.5 5.5 57.75
150.20 Sq.M.
9 Neat Cement 150.20 Sq.M.
10 7 M.T. manhole 3 Nos
SL LENGTH Total
NO. DESCRPTION OF ITEM NO. (m) Length(m) Unit
1 U.G.R. TO Pump
1 22.00 22.0
1 7.00 7.0
1 14.00 14.0
2 3.00 6.0
1 5.00 5.0
54.00 Mtr.