S. DIMENSIONS
QUANTITY
N DESCRIPTION OF ITEM NOS NAME
O L (M) B (M) D (M) OF (m3)
THE
OWNER : MR.K.SEKARAN
1 Earth Work Excavation In All Soils And Sub Soils 14 1.22 1.22 1.83 38.13
Add Extra 0.87
39.00
2 Sand Filling Using River Sand For Foundation
(A) Foundation For Column 14 1.22 1.22 0.15 3.13
Add Extra 0.87
4.00
(B) Basement Filling
Verandaha 1 3.65 2.13 1.2 9.33
Hall 1 3.65 4.57 1.2 20.02
Kitchen 1 3.65 2.13 1.2 9.33
Toilet 1 1.98 1.21 1.2 2.87
Bed Room 1 3.58 3.35 1.2 14.39
Toilet 1 3.65 1.37 1.2 6.00
Bed Room 1 3.65 2.66 1.2 11.65
Add Extra 0.41
74.00
3 P.c.c 1:5:10 Using 40mm Jelly For Foundation
(A) Foundation column 14 1.22 1.22 0.15 3.13
(B) Basement same As Item No2(b) 74.00/1.20x0.10 6.17
Add Extra 0.71
10.00
R.C.C 1:2:4 With 20mm HBG Store Jelly Including
4 Well Curing Etc Complete
(A) Foundation And Basement
For Made Concrete 14 1.22 1.22 0.23 4.79
For Trapezoidal portion 1 x 14 x 0.302 4.23
For Column Raising 14 0.23 0.23 1.83 1.36
For Grade Beam In Main Wall Allround 1 35.36 0.23 0.3 2.44
Cross Wall 1 14.55 0.23 0.3 1.00
Cross Wall 1 1.21 0.115 0.3 0.04
Add Extra 0.14
14.00
(B) Ground Floor Lintel
For Grade Beam In Main Wall Allround 1 35.36 0.23 0.3 2.44
Cross Wall 1 14.55 0.23 0.3 1.00
Cross Wall 1 1.21 0.115 0.3 0.04
Column Raising 14 0.23 0.23 3.05 2.26
W-Window Sunshade 4 1.68 0.6 0.08 0.32
Roof Slab 1 7.92 9.75 0.12 9.27
Add Extra 0.67
16.00
Total 30.00
5 Brick Work In C:M 1:5 In All Floors With 2nd Class
Chamber Burnt Bricks Including Well Curing Etc
Complete
(A) Foundation And Basement
In Main Wall Allround 1 35.36 0.23 1.2 9.76
Cross Wall 1 14.55 0.23 1.2 4.02
Cross Wall 1 1.21 0.115 1.2 0.17
Add Extra 0.06
14.00
(B) Ground Floor
In Main Wall Allround 1 35.36 0.23 3.05 24.81
Cross Wall 1 14.55 0.23 3.05 10.21
Cross Wall 1 1.21 0.115 3.05 0.42
Add Extra 0.56
36.00
Deduction (Ground Floor)
Column 14 0.23 0.23 3.05 2.26
M.D & G.D 2 1.2 0.23 2.1 1.16
Door 3 0.9 0.23 2.1 1.30
Door -1 2 0.76 0.23 2.1 0.73
Window 5 1.22 0.23 1.37 1.92
Ventilator 2 0.61 0.23 0.61 0.17
Add Extra 0.45
8.00
Total 42.00
STAGE WISE SPLIT-UP FOR THE PROPOSED CONSTRUCTION OF GROUND FLOOR RESIDENTIAL
BUILDING IN PATTA NO – 71, SURVEY NO – 113/1, SUBDIVISION PATTA NO – 858, SURVEY NO –
113/1A, PLOT NO – 31, SURVEY NO – 113/1A1A, PATTA NO – 9662, SUBDIVISION SURVEY NO –
113/15A2 AT PERAVOOR VILLAGE & PANCHAYAT, PATTANAMKATHAN GROUP, RAMANATHAPURAM
UNION, RAMANATHAPURAM TALUK & DISTRICT..
FINAL 0.00
TOTAL 0.00