You are on page 1of 5

Abstract Of Quantity (I WALL)

Length Breadth Height/Depth


S.no Description Of Item No
(m) (m) (m)

1 Excavation In Foundation 1 3.4 0.7 1.1


2 P.c.c in Foundation 1 3.4 0.7 0.3
3 Brick Work In Foundation Upto plinth
Step no 1 1 3.2 0.5 0.2
Step no 2 1 3.1 0.4 0.6
Step NO 3 1 3 0.3 0.2
Total
4 D.P.C 1 3 0.3
5 Brick Work In S.S 1 3 0.3 3
6 Plaster Work
Front And Back 2 3 3
Sides 2 0.3 3
Total
Abstract Of Cost

Quantity (m³/m²) Remarks Item No Particulars Quantity

1 Excavation In Foundation 2.618


2.618 2 P.c.c in Foundation 0.714
0.714 3 Brick Work In Foundation Upto plinth 1.244
4 D.P.C 0.9
0.32 5 Brick Work In S.S 2.7
0.744 6 Plaster Work 19.8
0.18
1.244
0.9
2.7
Total
18
1.8
19.8
Cost

Unit Rate Amount

m³ $25 $65.45
m³ $50 $35.70
m³ $45 $55.98
m² $40 $36.00
m³ $40 $108.00
m² $2 $40

$340.73
Material Statement
Ratio Cement
S.NO Description Of Item Qty
C : S : C.A (Bags)
1 P.c.c in Foundation 0.714 1 : 4 : 8 2.42

2 Brick Work In Foundation Upto plinth 1.244 1 : 6 1.52

3 D.P.C 0.045 1: 2: 4 0.28

4 Plaster Work 0.297 1: 4 2.16


Coarse
Sand Agg Bricks
(Cu.m) (Cu.m) Nos
0.34 0.68

0.32 622

0.02 0.04

0.30