You are on page 1of 2

Excavation

WIDTH HEIGHT LENGTH qty


Tie Beam FTB 1 0.2 0.5 40 4 cu.m
Footing 1 1 1.1 12 13.2 cu.m
Total 17.2 cu.m

Backfill 31.68
Footing 1.1 0.819 cu.m 9.828 cu.m
Ftb 4 2.4 1.6 cu.m
Flooring (Area) 73 0.3 21.9 cu.m

Total 33.328 cu.m

Concrete Works qty


Footing 1 1 0.2 12 2.4 cu.m
Column 0.3 0.3 4 12 4.32 cu.m
Ftb 0.2 0.3 40 2.4 cu.m
Flooring (Slab on Fill) GF 73 0.1 7.3 cu.m
Beam 1 0.2 0.3 50 3 cu.m
Slab (2nd Floor) 2F 73 0.15 10.95 cu.m
5.16

Class A (1:2:4)
Cement Gravel(cu.m) Sand (cu.m)
22 bags 2.4 1.2
39 bags 4.32 2.16
22 bags 2.4 1.2
65.7 7.3 3.65
27 3 1.5
98.55 10.95 5.475