Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
1 Earthwork Excavation qs estimate.dwg

a) for columns 22 1.2 1.2 1.15 36.432 m3 1.15


b) for plinth beam 1 54.7 0.3 0.3 4.923 m3 54.7
TOTAL 41.355 m3
2 Sand Filling 22 1.2 1.2 0.1 3.168 m3
TOTAL 3.168 m3
3 PCC (1:5:10) 22 1.2 1.2 0.15 4.752 m3
TOTAL 4.752 m3
4 RCC Footing (1:1.5:3) 22 1.2 1.2 0.3 9.504 m3
TOTAL 9.504 m3
5 RCC Pedestral (1:1.5:3) 22 0.8 0.8 0.3 4.224 m3
TOTAL 4.224 m3
6 RCC Plinth Beam (1:1.5:3) 1 86.2 0.3 0.3 7.758 m3 86.2
TOTAL 7.758 m3
7 Damp Proof Course 1 86.2 0.3 1 25.86 m2 86.2
TOTAL 25.86 m2

GROUND FLOOR
qs estimate.dwg
3
8 RCC column (1:1.5:3) upto lintel beam 22 2.7 0.3 0.3 5.346 m 2.7
TOTAL 5.346 m3
13 Brickwork upto Basement 1 4.86 0.3 0.60 0.87 m3
TOTAL 0.87 m3
9 Brickwork (CM 1:6) upto lintel beam 1 66.4 0.23 2.7 41.2344 m3 66.4
DEDUCTIONS:
a)Window , W1 5 0.9 0.23 1.2 1.242 m3
b)Window , W2 9 0.6 0.23 1.2 1.4904 m3
c)Door , D 4 1 0.23 2.1 1.932 m3
d)Door , D1 1 0.8 0.23 2.1 0.3864 m3

1
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
3
e)Door , D2 2 0.9 0.23 2.1 0.8694 m
f)Ventilator ,V 2 0.9 0.23 0.6 0.2484 m3
g)Opening ,O1 1 2 0.23 2.1 0.966 m3
h)Arch Opening , AO 1 2.7 0.23 2.7 1.6767 m3
DEDUCTIONS 8.8113 m3
TOTAL 32.4231 m3
10 Fixing of Joineries
a)Window , W 5 0.9 1 1.2 5.4 m2
b)Window , W2 9 0.6 1 1.2 6.48 m2
c)Door , D 4 1 1 2.1 8.4 m2
d)Door , D1 1 0.8 1 2.1 1.68 m2
e)Door , D2 2 0.9 1 2.1 3.78 m2
f)Ventilator ,V 3 0.9 1 0.6 1.62 m2
TOTAL 27.36 m2
11 Fixing of window grill
a)Window , W1 5 0.9 1 1.2 5.4 m2
b)Window , W2 9 0.6 1 1.2 6.48 m2
TOTAL 11.88 m2
12 Lintel concreting (1:1.5:3) 1 86.2 0.3 0.3 7.758 m3 86.2
TOTAL 7.758 m3

2
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
3
13 Sunshade concreting (1:1.5:3) 1 38.5 0.45 0.15 2.59875 m 38.5
TOTAL 2.59875 m3
14 Sand Filling and consolidation
a) Kitchen 1 3 4 0.46 5.52 m3
b) Dining Room 1 2.7 4 0.46 4.968 m3
c) Bedroom 1 3 4 0.46 5.52 m3
d) FRP Toilet 1 3 2 0.46 2.76 m3
e) Living Room 1 3 5 0.46 6.9 m3
f) Toilet cum staircase space 1 2.8 2 0.46 2.576 m3
g) Master Bedroom 1 3 5.2 0.46 7.176 m3
h) Study Room 1 2.8 2.7 0.46 3.4776 m3
i) Sitout 1 3 2.3 0.46 3.174 m3
j) Porch 1 3.13 2.5 0.46 3.5995 m3
TOTAL 45.6711 m3
15 PCC Flooring (1:5:10)
a) Kitchen 1 3 4 0.12 1.44 m3
b) Dining Room 1 2.7 4 0.12 1.296 m3
c) Bedroom 1 3 4 0.12 1.44 m3
d) FRP Toilet 1 3 2 0.12 0.72 m3
e) Living Room 1 3 5 0.12 1.8 m3
f) Toilet cum staircase space 1 2.8 2 0.12 0.672 m3
g) Master Bedroom 1 3 5.2 0.12 1.872 m3
h) Study Room 1 2.8 2.7 0.12 0.9072 m3
i) Sitout 1 3 2.3 0.12 0.828 m3
j) Porch 1 3.13 2.5 0.12 0.939 m3
TOTAL 11.9142 m3

3
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
16 Marble Flooring
a) Kitchen 1 3 4 1 12.00 m2
b) Dining Room 1 2.8 4 1 11.20 m2
c) Bedroom 1 3 4 1 12.00 m2
d) FRP Toilet 1 3 2 1 6.00 m2
e)Living Room 1 3 5 1 15.00 m2
f) Staircase Space 1 2 2 1 4.00 m2
g) Master Bedroom 1 3 5.2 1 15.60 m2
h) Study Room 1 2.8 2.7 1 7.56 m2
i) Sitout 1 3 2.3 1 6.90 m2
j)Staircase Space 1 1.2 2 1 2.40 m2
k) Doors and Openings 1 9.5 0.3 1 2.85 m2
TOTAL 95.51 m2
17 Tile Flooring
a) FRP Toilet 1 3 2 1 6 m2
b) Toilet 1 1.8 2 1 3.6 m2
c) Door 1 1.8 0.3 1.00 0.54 m2
TOTAL 10.14 m2

4
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
18 Tile laying on the wall
a) FRP Toilet 1 9.1 2.1 1 19.11 m2 9.1
b) Toilet 1 6.7 2.1 1 14.07 m2 6.7
c) Sitout 1 2.3 2.1 1 4.83 m2
TOTAL 38.01 m2
19 Clay tile Laying (PORTICO) 1 3.13 2.5 1 7.825 m2
TOTAL 7.825 m2
20 RCC Column (1:1.5:3) from lintel to Roof beam 22 0.3 0.3 0.3 0.594 m3
TOTAL 0.594 m3
21 RCC Roof Beam (1:1.5:3) 1 86.2 0.3 0.3 7.758 m3 86.2
TOTAL 7.758 m3
22 Brickwork (CM 1:6) upto Roof Beam 1 66.4 0.23 0.3 4.5816 m3 66.4
TOTAL 4.5816 m3
23 RCC Slab (1:1.5:3) 1 9.9 12.4 0.12 14.7312 m3
DEDUCTIONS:
a) Staircase space 1 2.2 2 0.12 0.528 m3
TOTAL 14.2032 m3
24 Ceiling Plastering (CM 1:4)
a) Kitchen 1 3 4 1 12 m2
b) Dining Room 1 2.7 4 1 10.8 m2
c) Bedroom 1 3 4 1 12 m2
d) FRP Toilet 1 3 2 1 6 m2

5
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
2
e) Living Room 1 3 5 1 15 m
f) Toilet cum staircase space 1 2.8 2 1 5.6 m2
g) Master Bedroom 1 3 5.2 1 15.6 m2
h) Study Room 1 2.8 2.7 1 7.56 m2
i) Sitout 1 3 2.3 1 6.9 m2
j) Porch 1 3.13 2.5 1 7.825 m2
TOTAL 99.285 m2
25 Inner Plastering ( CM1:5) 1 112.7 1 3 338.1 m2 112.7
a) Doors and Openings (Vertically) 14 0.3 1 2.10 8.82 m2
b)Doors and Openings (Horizontally) 1 6.6 0.3 1.00 1.98 m2
c) Windows and Ventilators (Vertically) 1 36 0.3 1.00 10.80 m2
d) Window and Ventilator (Horizontally) 1 23.4 0.3 1.00 7.02 m2
DEDUCTIONS:
a)Window , W1 5 0.9 1 1.2 5.4 m2
b)Window , W2 9 0.6 1 1.2 6.48 m2
c)Door , D 7 1 1 2.1 14.7 m2
d)Door , D1 2 0.8 1 2.1 3.36 m2
e)Door , D2 4 0.9 1 2.1 7.56 m2
f)Ventilator ,V 2 0.9 1 0.6 1.08 m2
g)Opening ,O1 2 2 1 2.1 8.4 m2
h)Arch Opening , AO 2 2.7 1 2.7 14.58 m2
i)Staircase opening 1 2 1 3 6 m2
DEDUCTIONS 67.56 m2
TOTAL 299.16 m2

6
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
26 Opening Plastering (CM 1:5)
a)Opening ,O 1 6.2 0.3 1 1.86 m2 6.2
b)Arch Opening , AO 1 8.1 0.3 1 2.43 m2 8.1
TOTAL 4.29 m2
27 Sunshade Plastering ( CM 1:5) 1 38.5 1.05 1 40.425 m2 38.5
TOTAL 40.425 m2 1.05
28 Outer Plastering (CM 1:5)
a) Wall Plastering 1 44.6 3.72 1 165.912 m2 44.6
b) Column Plastering 9 3.72 0.3 1 10.044 m2 3.72
DEDUCTIONS:
a)Window , W1 5 0.9 1 1.2 5.4 m2
b)Window , W2 9 0.6 1 1.2 6.48 m2
c)Door , D 2 1 1 2.1 4.2 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 0 0.9 1 2.1 0 m2
f)Ventilator ,V 2 0.9 1 0.6 1.08 m2
g)Opening ,O1 0 2 1 2.1 0 m2
h)Arch Opening , AO 0 2.7 1 2.7 0 m2
DEDUCTIONS 17.16 m2
TOTAL 158.796 m2

7
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
29 Inner Staircase
a) Waist slab Concreting (1:1.5:3) 1 5.77 1 0.15 0.87 m3 5.77
b) Landing Concreting (1:1.5:3) 1 2 1 0.15 0.3 m3
c) Steps (Brickwork) (CM1:6) 8 1 0.2 0.3 0.48 m3 nos = 16*0.5
d) Handrail 1 5.77 1 0.75 4.33 m2
e) Plastering at the sides of steps (CM 1:5) 8 0.2 0.3 1 0.48 m2 nos = 16*0.5
f) Plastering below waist slab (CM 1:5) 1 5.77 1 1 5.77 m2
g) plastering below landing slab 1 2 1 1 2 m2
h) Marble Laying on Thread 16 1 1 0.3 4.8 m2
i) Marble Laying on Rise 16 1 1 0.2 3.2 m2
j) Marble Laying on landing 1 2 1 1 2 m2

30 Outer Staircase:
a) Steps (Brickwork) (CM 1:6) 1 1 0.9 0.6 0.54 m3
b) Plastering (CM 1:5) 2 1 0.9 0.6 1.08 m2
c) Handrail 4 1.08 1 0.75 3.24 m2
d) Marble Laying on Thread 6 1 1 0.3 1.8 m2
e) Marble Laying on Rise 6 1 1 0.2 1.2 m2

8
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
31 Painting
a) Inner Wall Painting 1 1 1 299.16 299.16 m2
b) Outer Painting (Wall and Column ) 1 1 1 158.80 158.80 m2
c) sunshade Painting 1 1 1 40.43 40.43 m2
d) Ceiling painting 1 1 1 99.29 99.29 m2
e) Opening painting 1 1 1 4.29 4.29 m2
f) Outet Staircase painting 1 1 1 1.08 1.08 m2
g) Inner Staircase painting 1 1 1 8.25 8.25 m2
h) Enamel Coating 1 1 1 27.36 27.36 m2

32 RCC Kitchen slab (1:1.5:3) (150mm thk) 1 4.8 0.6 0.15 0.432 m3 4.8
TOTAL 0.432 m3
33 Marble laying on kitchen slab 1 4.8 0.6 1 2.88 m2 4.8
TOTAL 2.88 m2
34 Plastering of Kitchen slab (CM 1:6)
a) Bottom 1 4.8 0.6 1 2.88 m2
b) Sides 1 4.8 0.15 1 0.72 m2
TOTAL 3.6 m2
35 Hand rail for sitout 1 4.86 0.75 1 3.65 m2
TOTAL 3.65 m2

9
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark

FIRST FLOOR
qs estimate.dwg
3
36 RCC column (1:1.5:3) upto lintel beam 17 2.1 0.3 0.3 3.213 m 2.1
TOTAL 3.213 m3
37 Brickwork (CM 1:6) upto lintel beam 1 52.7 0.23 2.1 25.45 m3 52.7
DEDUCTIONS:
a)Window , W1 3 0.9 0.23 1.2 0.7452 m3
b)Window , W2 5 0.6 0.23 1.2 0.828 m3
c)Door , D 4 1 0.23 2.1 1.932 m3
d)Door , D1 0 0.8 0.23 2.1 0 m3
e)Door , D2 1 0.9 0.23 2.1 0.4347 m3
f)Ventilator ,V 1 0.9 0.23 0.6 0.1242 m3
g)Opening ,O 2 1 0.23 2.1 0.966 m3
h)Arch Opening , AO 0 2.7 0.23 2.7 0 m3
DEDUCTIONS 5.0301 m3
TOTAL 20.42 m3
38 Fixing of Joineries
a)Window , W1 3 0.9 1 1.2 3.24 m2
b)Window , W2 5 0.6 1 1.2 3.6 m2
c)Door , D 4 1 1 2.1 8.4 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 1 0.9 1 2.1 1.89 m2
f)Ventilator ,V 1 0.9 1 0.6 0.54 m2
TOTAL 17.67 m2

10
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
39 Fixing of window grill
a)Window , W1 3 0.9 1 1.2 3.24 m2
b)Window , W2 5 0.6 1 1.2 3.6 m2
TOTAL 6.84 m2
40 Lintel concreting (1:1.5:3) 1 53.8 0.3 0.3 4.842 m3 53.8
TOTAL 4.842 m3
41 Sunshade concreting (1:1.5:3) 1 22.5 0.45 0.15 1.51875 m3 22.5
TOTAL 1.51875 m3
42 Marble Flooring
a)Bedroom 1 4.07 2.7 1.00 10.99 m2
b) Store room 1 1.63 2.7 1.00 4.40 m2
c)Passage 1 4.07 2 1.00 8.14 m2
e)Guest room (space :1) 1 3 2 1.00 6.00 m2
f)Guest room (space :2) 1 1 1.7 1.00 1.70 m2
g)Dressing room 1 2 1.7 1.00 3.40 m2
h)Opening 2 0.3 1 1.00 0.60 m2
k) Doors and Openings 1 6 0.3 1 1.80 m2
TOTAL 37.03 m2
43 Tile Flooring
a) Bathroom 1 3 2 1 6 m2
c) Door 1 0.9 0.3 1.00 0.27 m2
TOTAL 6.27 m2
44 Tile laying on the wall
a)Bathroom 1 9.1 2.1 1 19.11 m2 9.1
TOTAL 19.11 m2
45 Clay tile laying (Weathering course)
a)Balcony 1 2.95 6.3 1 18.585 m2 2.95
b)Terrace 1 3 11.8 1 35.4 m2 11.8
TOTAL 53.985 m2

11
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
3
46 RCC Column (1:1.5:3) from lintel to roof beam 17 0.3 0.3 0.3 0.459 m
TOTAL 0.459 m3
47 RCC Roof Beam (1:1.5:3) 1 64.8 0.3 0.3 5.832 m3 64.8
TOTAL 5.832 m3
48 Brickwork (CM 1:6) upto Roof Beam 1 52.7 0.23 0.3 3.6363 m3 52.7
TOTAL 3.6363 m3
49 RCC Slab (1:1.5:3) 1 6.6 12.85 0.12 10.1772 m3 12.85
TOTAL 10.1772 m3
50 Ceiling Plastering (CM 1:4)
a)Bedroom 1 4.07 2.7 1 10.989 m2
b) Store room 1 1.63 2.7 1 4.401 m2
c)Passage :1 1 3.2 2 1 6.4 m2
e)Guest room (space :1) 1 3 2 1 6 m2
f)Guest room (space :2) 1 1 1.7 1 1.7 m2
g)Dressing room 1 2 1.7 1 3.4 m2
h) Staircase space 1 4 2 1 8 m2
i) Balcony 1 6.3 2.95 1 18.585 m2
j)Bathroom 1 3 2 1 6 m2
TOTAL 65.475 m2
51 Inner Plastering ( CM1:5) 1 83.67 1 3 251.01 m2 83.67
a) Doors and Openings (Vertically) 10 0.3 1 2.10 6.30 m2
b)Doors and Openings (Horizontally) 1 7.8 0.3 1.00 2.34 m2
c) Windows and Ventilators (Vertically) 1 20.4 0.3 1.00 6.12 m2
d) Window and Ventilator (Horizontally) 1 13.2 0.3 1.00 3.96 m2

12
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
DEDUCTIONS:
a)Window , W1 3 0.9 1 1.2 3.24 m2
b)Window , W2 5 0.6 1 1.2 3.6 m2
c)Door , D 7 1 1 2.1 14.7 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 2 0.9 1 2.1 3.78 m2
f)Ventilator ,V 1 0.9 1 0.6 0.54 m2
g)Opening ,O 4 1 1 2.1 8.4 m2
h) Dress room opening 2 2 1 2.7 10.8 m2
DEDUCTIONS 45.06 m2
TOTAL 205.95 m2
52 Opening Plastering (CM 1:5)
a)Opening ,O1 2 5.2 0.3 1 3.12 m2 5.2
TOTAL 3.12 m2
53 Sunshade Plastering ( CM 1:5) 1 22.5 1.05 1 23.625 m2 22.5
TOTAL 23.625 m2 1.05
54 Outer Plastering (CM 1:5)
a) Wall Plastering 1 28.9 3.72 1 107.508 m2 28.9
b) Column Plastering 7 3.72 0.3 1 7.812 m2 3.72
DEDUCTIONS: n= no of faces
2
a)Window , W1 3 0.9 1 1.2 3.24 m
b)Window , W2 5 0.6 1 1.2 3.6 m2
c)Door , D 1 1 1 2.1 2.1 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 0 0.9 1 2.1 0 m2
f)Ventilator ,V 1 0.9 1 0.6 0.54 m2
g)Opening ,O 0 1 1 2.1 0 m2
h)Arch Opening , AO 0 2.7 1 2.7 0 m2
DEDUCTIONS 9.48 m2

13
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
2
TOTAL 105.84 m
55 Outer Staircase
a) Waist slab Concreting (1:1.5:3) 1 5.41 1.15 0.15 0.93 m3 5.41
b) Landing :1 Concreting (1:1.5:3) 1 1.15 0.6 0.15 0.10 m3
b) Landing :1 Concreting (1:1.5:3) 1 1.15 0.75 0.15 0.13 m3
c) Steps (Brickwork) (CM1:6) 7.5 1 0.2 0.3 0.45 m3 nos = 15*0.5

d) Handrail (Brickwork) (CM 1:6) 1 6.41 1 0.75 4.81 m2


e) Plastering on top of steps (CM 1:5) 15 0.5 1 1 7.5 m2 nos = 15*0.5

f) Plastering below waist slab (CM 1:5) 1 6.41 1.15 1 7.37 m2


g) Plastering above and below landing:1 (CM 1:5) 1 1.15 1 1 1.15 m2
g) Plastering above and below landing:2 (CM 1:5) 1 1.15 0.75 1 0.8625 m2
h) Plastering on Handrail (CM 1:5) 1 0.75 6.41 1 4.81 m2

56 Parapet wall:
a) Brickwork (CM 1:6) 1 18.4 0.23 0.75 3.174 m2 18.4
b) Plastering (CM 1:5) 1 12.4 0.75 1 9.3 m2 12.4

57 Painting
a) Inner Wall Painting 1 1 1 205.95 205.95 m2
b) Outer Painting (Wall and Column ) 1 1 1 105.84 105.84 m2
c) sunshade Painting 1 1 1 23.625 23.625 m2
d) Ceiling painting 1 1 1 65.475 65.475 m2
e) Opening painting 1 1 1 3.12 3.12 m2
f) Outer Staircase painting 1 1 1 20.83 20.83 m2
g) Parapet painting 1 1 1 9.3 9.3 m2
h) Enamel Coating 1 1 1 17.67 17.67 m2

14
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
58 Steel Grill
a) Balcony 1 9.25 1 0.75 6.9375 m2 9.25
b) Near Passage 1 2 1 0.75 1.5 m2
TOTAL 8.4375 m2

SECOND FLOOR
qs estimate.dwg
3
59 RCC column (1:1.5:3) upto lintel beam 6 2.1 0.3 0.3 1.134 m 2.1
TOTAL 1.134 m3
60 Brickwork (CM 1:6) upto lintel beam 1 57.1 0.23 2.1 27.58 m3 57.1
DEDUCTIONS:
a)Window , W1 1 0.9 0.23 1.2 0.2484 m3
b)Window , W2 2 0.6 0.23 1.2 0.3312 m3
c)Door , D 2 1 0.23 2.1 0.966 m3
d)Door , D1 0 0.8 0.23 2.1 0 m3
e)Door , D2 1 0.9 0.23 2.1 0.4347 m3
f)Ventilator ,V 1 0.9 0.23 0.6 0.1242 m3
g)Opening ,O 2 1 0.23 2.1 0.966 m3
h)Arch Opening , AO 0 2.7 0.23 2.7 0 m3
i)Columns 6 2.7 0.3 0.3 1.458 m3
DEDUCTIONS 4.5285 m3
TOTAL 23.05 m3

15
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
61 Fixing of Joineries
a)Window , W1 1 0.9 1 1.2 1.08 m2
b)Window , W2 2 0.6 1 1.2 1.44 m2
c)Door , D 2 1 1 2.1 4.2 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 1 0.9 1 2.1 1.89 m2
f)Ventilator ,V 1 0.9 1 0.6 0.54 m2
TOTAL 9.15 m2
62 Fixing of window grill
a)Window , W1 1 0.9 1 1.2 1.08 m2
b)Window , W2 2 0.6 1 1.2 1.44 m2
TOTAL 2.52 m2
63 Lintel concreting (1:1.5:3) 1 27.7 0.3 0.3 2.493 m3 27.7
TOTAL 2.493 m3
64 Sunshade concreting (1:1.5:3) 1 18.8 0.45 0.15 1.269 m3 18.8
TOTAL 1.269 m3
65 Marble Flooring
a)Bedroom 1 4.07 2.7 1 10.989 m2
b) Game room 1 1.63 2.7 1 4.401 m2
c) Doors and Openings 1 3 0.3 1 0.90 m2
TOTAL 16.29 m2

16
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
66 Tile Flooring
a) Toilet 1 1.8 2 1 3.6 m2
b) Door 1 0.9 0.3 1.00 0.27 m2
TOTAL 3.87 m2
67 Tile laying on the wall
a)Bathroom 1 6.7 2.1 1 14.07 m2 6.7
TOTAL 14.07 m2
68 Clay tile laying
a) Terrace Garden 1 6 1.2 1 7.2 m2 6
b) Terrace :1 1 6 3.45 1 20.7 m2 3.45
c) Terrace :2 1 3.9 2.3 1 8.97 3.9
TOTAL 36.87 m2
69 RCC Column (1:1.5:3) from lintel to roof beam 6 0.3 0.3 0.3 0.162 m3
TOTAL 0.162 m3
70 RCC Roof Beam (1:1.5:3) 1 27.7 0.3 0.3 2.493 m3 27.7
TOTAL 2.493 m3
71 Brickwork (CM 1:6) upto Roof Beam 1 57.1 0.23 0.3 3.9399 m3 57.1
TOTAL 3.9399 m3
72 RCC Slab (1:1.5:3) 1 6.6 12.85 0.12 10.1772 m3 12.85
TOTAL 10.1772 m3
73 Weathering Course (PCC 1:5:10) 1 6.6 12.85 1 84.81 m3
TOTAL 84.81 m3

17
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
74 Ceiling Plastering (CM 1:4)
a)Bedroom 1 4.07 2.7 1 10.989 m2
b) Game room 1 1.63 2.7 1 4.401 m2
c) Toilet 1 1.8 2 1 3.6 m2
TOTAL 174.11 m2
75 Inner Plastering ( CM1:5) 1 29.8 1 3 89.4 m2 29.8
a) Doors and Openings (Vertically) 6 0.3 1 2.10 3.78 m2
b)Doors and Openings (Horizontally) 1 2.9 0.3 1.00 0.87 m2
c) Windows and Ventilators (Vertically) 1 8.4 0.3 1.00 2.52 m2
d) Window and Ventilator (Horizontally) 1 6 0.3 1.00 1.80 m2
DEDUCTIONS:
a)Window , W1 1 0.9 1 1.2 1.08 m2
b)Window , W2 2 0.6 1 1.2 1.44 m2
c)Door , D 2 1 1 2.1 4.2 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 1 0.9 1 2.1 1.89 m2
f)Ventilator ,V 1 0.9 1 0.6 0.54 m2
g)Opening ,O 2 1 1 2.1 4.2 m2
h)Arch Opening , AO 0 2 1 2.7 0 m2
DEDUCTIONS 13.35 m2
TOTAL 85.02 m2
76 Opening Plastering (CM 1:5)
a)Opening ,O 1 5.2 0.3 1 1.56 m2 5.2

18
Name: Jayapratha DETAILED ESTIMATE 24-03-2023

Sl.No. Description Nos Length (m) Width (m) Depth (m) Quantity Units Remark
2
TOTAL 1.56 m
77 Sunshade Plastering ( CM 1:5) 1 18.8 1.05 1 19.74 m2 18.8
TOTAL 19.74 m2 1.05
78 Outer Plastering (CM 1:5)
a) Wall Plastering 1 23.37 3.72 1 86.9364 m2 23.37
DEDUCTIONS: n= no of faces

a)Window , W1 1 0.9 1 1.2 1.08 m2


b)Window , W2 2 0.6 1 1.2 1.44 m2
c)Door , D 2 1 1 2.1 4.2 m2
d)Door , D1 0 0.8 1 2.1 0 m2
e)Door , D2 1 0.9 1 2.1 1.89 m2
f)Ventilator ,V 1 0.9 1 0.6 0.54 m2
g)Opening ,O 0 2 1 2.7 0 m2
h)Arch Opening , AO 0 2.7 1 2.7 0 m2
DEDUCTIONS 9.15 m2
TOTAL 77.7864 m2
79 Parapet wall:
a) Brickwork (CM 1:6) 1 27 0.23 0.75 4.6575 m2 27
b) Plastering (CM 1:5) 1 54 0.75 1 40.5 m2 54

80 Painting
a) Inner Wall Painting 1 1 1 85.02 85.02 m2
b) Outer Wall Painting 1 1 1 77.79 77.79 m2
c) sunshade Painting 1 1 1 19.74 19.74 m2
d) Ceiling painting 1 1 1 174.11 174.11 m2
e) Opening painting 1 1 1 1.56 1.56 m2
g) Parapet painting 1 1 1 40.5 40.5 m2
h) Enamel Coating 1 1 1 9.15 9.15 m2

19