Description formula Qnt Unit

Pile length 19+0.15+0.25 19.4 m

Pile 3.14*0.275^2*19.4*16 73.71 m3


Pile Cap 2.678*2.678*0.85*4 24.38 m3
Padestal 1*1*1.75*4 7.00 m3
CC padastal 2.678*2.678*0.075*4 2.15 m3 Planned Actual Dif
Volume for 27m 107.24 m3 Stone (Cft) 3217 3700 483
Sand (Cft) 2145 2467 322
Pile length 23+0.15+0.35 23.50 m Cement (bg) 858 987 129

Pile 3.14*0.325^2*23.5*16 124.71 m3


Pile Cap 2.9*2.9*1.1*4 37.00 m3
Padestal 1*1*1.6*4 6.4 m3
CC padastal 2.9*2.9*0.075*4 2.52 m3 Planned Actual Dif
Volume for 82m 170.63 m3 Stone (Cft) 5119 5500 381
Sand (Cft) 3413 3925 512
Cement (bg) 1365 1570 205

27m 82m Total


Pile work 73.71 124.71 396.83
Pile Cap 24.38 37.00 122.78
Padestal 7.00 6.4 26.80
CC cast 2.15 2.52 9.35
TOTAL PROJECT VOLUME 555.75 m3