You are on page 1of 10

SUMMARY FOR Dire Dawa AIRPORT POLICE RESIDENCE

Item No Description Amount (Birr)


A. Substructure
1 Excavation & Earth Work 102,710.50
2 Masonry Work 210,259.38
3 Concrete Work 317,399.32
Sub Total ………...A 630,369.20
B. Superstructure
1 Concrete Work 274,322.10
2 Block Work 374,998.00
3 Roofing and Carpenter 415,775.34
4 Ceiling Work 189,650.00
5 Finishing Work 611,628.50
6 Painting Work 383,438.40
7 Metal Work 294,300.00
8 Glazing 93,720.00
9 Sanitary Installation 72,260.00
10 Electrical Installation 102,070.00
Sub Total ………...B 2,812,162.34
Total for Dire Dawa Airport …………..(A+B) 3,442,531.54
15% VAT………………… 516,379.73
Grand Total …………… 3,958,911.27
TAKEOFF SHEET FOR AIRPORT POLICE RESIDENCE BUILDING
T LXWXH QTY UNIT DESCRIPTION T LXWXH QTY UNIT DESCRIPTION
A-SUB-STRUCTURE Fill around masonry wall
1. 0 EXCAVATION & EARTH WORK 1 100.3
1.1 Clearing 0.5
1 1 Toilet and Shower 0.2
27.04 10.03 m3
27.04 m2 10.03 m3 Total fill around masonry wall
1 1 Bed, dining, store, office rooms 39.70 m3 Total fill
369.37 1.8 Cart Away
369.37 m2 1 1 From site clearing
396.41 m2 Total Site Clearing 396.41
1.2 Trench Excavation 0.2
1 100.3 79.28 m3
1 79.28 m3 Total cartaway from Site Clearing
0.5
50.15 m3 50.15 m3 Total cartaway from trench excavation
50.15 m3 Total Trench Excvation
1 1 1.3 Bulk Excavation 73.87 m3 Total cartaway from bulk excavation
369.37
0.2 112.49 m3 Total cartaway from ST excavation
73.87 m3
73.87 m3 Total Bulk Excavation 315.79 m3 Total cartaway
1.4 Trench Excavation for ST (1.5m) 1.9 Back Fill
1 1 1 1 Under hardcore
27.04 369.37
1.5 369.37 m2
40.56 m3
40.56 m3 Total Trench excvation for ST (1.5m) 1 9.5 DDT for Beam (L1)
1.5 Trench Excavation for ST (1.5-3m) 0.2
1 1 1.90 m2
27.04 2 9.75 DDT for Beam (L2)
1.5 0.2
40.56 m 3
3.90 m2

40.56 m3 Total Trench excvation for ST (1.5-3m) 1 30.1 DDT for Beam (L3)
1.6 Trench Excavation for ST (3-4.5m) 0.2
1 1 6.02 m2
27.04 2 28.1 DDT for Beam (L4)
1.16 0.2
31.37 m3 11.24 m2
31.37 m3 Total Trench excvation for ST (3-4.5m) 7 9.5 DDT for Beam (L5)
1.7 Back Fill 0.2
1 1 Under hardcore 13.30 m2

369.37 333.01 m2 Hardcore for Living, dining room


0.1 1 1
36.94 m3 27.04
27.04 m2
1 9.5 DDT for Beam (L1) 27.04 m2 Hardcore for toilet and shower room
0.2 360.05 m2 Total 20cm thick hardcore
0.2 2. Masonry
0.38 m3 2.1 Masonry below ground
2 9.75 DDT for Beam (L2) 1 100.3 Masonry under living, dining room edge beam
0.2 0.5
0.2 0.5
0.78 m3 25.08 m3 Total for living, dining room edge beam
1 30.1 DDT for Beam (L3) 25.08 m3
0.2 1 20.7 Masonry for Septic Tank wall
0.2 0.845
1.20 m3 3.86
2 28.1 DDT for Beam (L4) 67.52 m3 Total for living, dining room
0.2 92.59 m3 Total masonry below ground
0.2 2.2 Masonry above ground
2.25 m3 1 100.3 Masonry above living, dining room edge beam
7 9.5 DDT for Beam (L5) 0.5
0.2 0.25
0.2 12.54 m3
2.66 m3 12.54 m3 Total for living, dining room edge beam
29.67 m3 Total fill under hardcore 3. Concrete Work
3.1 Lean Concrete
1 100.3 Lean Concrete under masonry wall
0.5
50.15 m2
1 20.8 Lean Concrete under septic tank masonry wall
1.04
21.63 m2
TAKEOFF SHEET FOR AIRPORT POLICE RESIDENCE BUILDING
T LXWXH QTY UNIT DESCRIPTION T LXWXH QTY UNIT DESCRIPTION
1 28.1 Beam (L4) 4 9.75 Beam (L2)
0.2 0.3
5.62 m2 11.7 m2
5 9.5 Beam (L5) 2 30.1 Beam (L3)
0.2 0.3
9.50 m2 18.06 m2
86.90 m2 4 28.1 Beam (L4)
3.2 Reinforced Concrete 0.3
a) 100mm thick slab 33.72 m2
1 1 14 9.5 Beam (L5)
369.37 0.3
0.1 39.9 m2
36.937 8 5 Beam (L6)
36.94 m3 0.3
12 m2
1 9.5 DDT for Beam (L1) 30 0.2 DDT for Intersections
0.2 0.3
0.1 1.8 m2
0.19 m3 119.28 m2 Total formwork for grade beam
2 9.75 DDT for Beam (L2) b) 150mm thick slab
0.2 1 4.8
0.1 4.8
0.39 m3 23.04
1 30.1 DDT for Beam (L3) 23.04 m2 Total for 150mm thick RC Slab
0.2 B. Super Structure
0.1 1. Concrete Work
0.602 m3 1.1 Formwork
2 28.1 DDT for Beam (L4) 26 0.8 a) Elevation Column for Living room
0.2 3.6
0.1 74.88 m2
1.124 m3 4 0.8 Elevation Column for toilet room
7 9.5 DDT for Beam (L5) 3.1
0.2 9.92 m2
0.1 84.80 m2 Total formwork for elevation column
1.33 m3 b) Top Tie Beam
33.30 m2 100mm thick RC Slab 2 9.5 Beam (L1)
b) Grade Beam 0.3
1 9.5 Beam (L1) 5.7 m2
0.2 4 9.75 Beam (L2)
0.3 0.3
0.57 m 3
11.7 m2

2 9.75 Beam (L2) 2 30.1 Beam (L3)


0.2 0.3
0.3 18.06 m2
1.17 m3 4 28.1 Beam (L4)
1 30.1 Beam (L3) 0.3
0.2 33.72 m2
0.3 14 9.5 Beam (L5)
1.806 m3 0.3
2 28.1 Beam (L4) 39.9 m2
0.2 8 5 Beam (L6)
0.3 0.3
3.372 m 3
12 m2

7 9.5 Beam (L5) 30 0.2 DDT for Intersections


0.2 0.3
0.3 1.8 m2
3.99 m3 119.28 m2 Total formwork for top tie beam
4 5 Beam (L6) 1.2 Reinforced Concrete
0.2 26 0.8 a) Elevation Column for Living
0.3 0.2
1.2 m3 3.6
30 0.2 DDT for Intersections 14.976 m3
0.2 4 0.8 Elevation Column for toilet
0.3 0.2
0.36 m3 3.1
11.75 m3 Total for RC Grade Beam 1.984 m3
c) 150mm thick slab 16.96 m2 Total RC for elevation column
1 4.8 b) Grade Beam
4.8 1 9.5 Beam (L1)
0.15 0.2
3.456 0.3
3.46 m3 Total for 150mm thick RC Slab 0.57 m3
3.3 Formwork 2 9.75 Beam (L2)
a) Grade Beam 0.2
2 9.5 Beam (L1) 0.3
0.3 1.17 m3
5.7 m2
TAKEOFF SHEET FOR AIRPORT POLICE RESIDENCE BUILDING
T LXWXH QTY UNIT DESCRIPTION T LXWXH QTY UNIT DESCRIPTION
1 30.1 Beam (L3) 2 0.9 D2
0.2 2.5
0.3 4.5 m2
1.806 m3 1 2 D3
2 28.1 Beam (L4) 2.5
0.2 5 m2
0.3 69.6 m2
3.372 m3 820.42 m2 Total for 200 thick HCB
7 9.5 Beam (L5) b. 15 * 15 * 40 cm
0.2
0.3 1 15.9 Living and Dining room
3.99 m3 3.6
4 5 Beam (L6) 57.24 m2
0.2 1 13.25 Toilet and Shower
0.3 3.1
1.2 m3 41.075 m2
30 0.2 DDT for Intersections 8 0.65 DDT for D4
0.2 2.5
0.3 13 m2
0.36 m3 1 0.9 DDT for D2
11.75 m3 Total for Top Tie Beam 2.5
2. Block Works 2.25
a. 20 * 20 * 40 cm 2 0.7 DDT for D5
1 18.84 Span AB-23 2.5
3.6 3.5
67.824 m2 79.57 m2 Total for 15cm HCB
1 13.84 Span AB-12 C. 10 * 10 * 40 cm
3.6
49.824 m2 1 12.1 Toilet and Shower
1 14.37 Span BC-23 3.1
3.6 37.51 m2
51.732 m2 37.51 m2 Total for Toilet and Shower
1 14.32 Span BC-12 3. Roofing and Carpenter
3.6 3.1 GS28 Roof cover
51.552 m2 1 1 Bed and Dining room
1 9.42 Span BC-23 369.37
3.6 369.37 m2
33.912 m2 1 1 Bed and Dining room
1 14.32 Span CD-12 28.32
3.6 28.32 m2
51.552 m2 397.69 m2 Total for GS28 Roof Cover
1 9.42 Span CD-23 3.2 Wooden roof structure
3.6 11 21.49 a) Upper & Lower Chords
33.912 m2 1
1 14.32 Span DE-12 236.39 m
3.6 236.39 m Total for 12cm dia chord
51.552 m2 11 16.68 b) Vertical & Diagonal Members
1 9.42 Span DE-23 1
3.6 183.48 m
33.912 m 2
183.48 m
1 37.18 Span EG-13 11 9.8 c) 5 X 7 cm Wood Roof Purlin
3.6 1
133.848 m 2
107.80 m
1 27.2 Span EG-34 107.80 m
3.6 4. Ceiling Work
97.92 m2 1 1 Bed and Dining room
3 4.8 Toilet and Shower 369.37
3.1 369.37 m 2

44.64 m2 1 1 Bed and Dining room


4 4.8 Toilet and Shower parapet 28.32
0.75 28.32 m2
14.4 m2 DDT for Beams
1 108.4 Living and Dining parapet 1 9.5 Beam (L1)
1.6 0.2
173.44 m2 1.9 m2
890.02 m2 2 9.75 Beam (L2)
DDT for Window/Door on Toilet Room 0.2
2 1.05 W5 1.95 m2
0.6 1 30.1 Beam (L3)
1.26 m2 0.2
2 1.2 W5 6.02 m2
0.6 2 28.1 Beam (L4)
1.44 m2 0.2
18 1.2 W1 5.62 m2
1.5 7 9.5 Beam (L5)
32.4 m2 0.2
10 1 D1 1.9 m2
2.5 4 5 Beam (L6)
25 m2 0.2
1 m2
379.30 m2 Total for PVC ceiling
TAKEOFF SHEET FOR AIRPORT POLICE RESIDENCE BUILDING
T LXWXH QTY UNIT DESCRIPTION T LXWXH QTY UNIT DESCRIPTION
5. Finishing Works
5.1 Plastering for walls
2 1 Plastering for 20 cm for HCB wall
820.42
1640.84 m2
2 1 Plastering for 15 cm for HCB wall
79.57
159.13 m2
2 1 Plastering for 10 cm for HCB wall
37.51
75.02 m2
1874.99 m2 Total for plastering of walls
5.2 Gypsum plastering for internal walls
2 1 Plastering for 20 cm for HCB wall
820.42
1640.84 m2
2 1 Plastering for 15 cm for HCB wall
79.57
159.13 m2
2 1 Plastering for 10 cm for HCB wall
37.51
75.02 m2
1 1 DDT for External Wall
820.42
820.42 m2
1054.57 m2 Total for Gypsum plastering
5.3 Cement Screed for floor
1 1
369.37
369.37 m2
369.37 m2

1 9.5 DDT for Beam (L1)


0.2
1.90 m2
2 9.75 DDT for Beam (L2)
0.2
3.90 m2
1 30.1 DDT for Beam (L3)
0.2
6.02 m2
2 28.1 DDT for Beam (L4)
0.2
11.24 m2
7 9.5 DDT for Beam (L5)
0.2
13.30 m2
1 4.8 Toilet and Shower
4.8
23.04 m2
356.05 m2 Total for Cement Screed
8. Glazing
Glazing for windows
W1 (1200x1500mm)
18 1.5
1.2
32.40 m2
1 1.5 W2 (1600x1500mm)
1.6
2.40 m2
2 1.5 W3 (1500x3000mm)
3
9.00 m2
2 1.5 W4 (1200x600mm)
0.6
1.80 m2
2 1.05 W5 (1050x600mm)
0.6
1.26 m 2

46.86 m2
BAR SCHEDULE FOR G+1 RESIDENTAIL BUILDING
Reinforcement Diameter
Location Dia C/C Length Size No Member Total length
6 8 10 12 14 16 20 24.00
A-SUB STRUCTURE
Ground Floor Slab

Toilet, Bar in X direction 8 0.16 8.09 4.72 29 1 235 - 234.61 - - - - - -


Shower Bar in Y direction 8 0.16 8.09 4.72 29 1 235 - 234.61 - - - - - -
Grade Beam - - - - - -
Top Reinforcement 12 @180mm 5.65 20x30 2 4 45.20 - - - 45.20 - - - -
GB1 Bottom Reinforcement 12 @180mm 5.15 20x30 2 4 41.20 - - - 41.20 - - - -
Strirrups 8 0.18 0.9 4.7 26 4 94 - 93.60 - - - - - -
Top Reinforcement 12 @180mm 29.51 20x30 2 2 118 - - - 118.04 - - - -
GB2 Bottom Reinforcement 12 @180mm 28.41 20x30 2 2 114 - - - 113.64 - - - -
Strirrups 8 0.18 0.9 28.3 157 2 283 - 282.60 - - - - - -
Top Reinforcement 12 @180mm 22.21 20x30 2 1 44 - - - 44.42 - - - -
GB3 Bottom Reinforcement 12 @180mm 20.94 20x30 2 1 42 - - - 41.88 - - - -
Strirrups 8 0.18 0.9 20.6 114 1 103 - 102.60 - - - - - -
Top Reinforcement 12 @180mm 9.95 20x30 2 7 139.30 - - - 139.30 - - - -
GB4 Bottom Reinforcement 12 @180mm 9.45 20x30 2 7 132.30 - - - 132.30 - - - -
Strirrups 8 0.18 0.9 8.91 49 7 309 - 308.70 - - - - - -
Top Reinforcement 12 @180mm 10.2 20x30 2 2 40.80 - - - 40.80 - - - -
GB5 Bottom Reinforcement 12 @180mm 9.7 20x30 2 2 38.80 - - - 38.80 - - - -
Strirrups 8 0.18 0.9 9.15 51 2 92 - 91.80 - - - - - -
Top Reinforcement 12 @180mm 9.95 20x30 2 2 39.80 - - - 39.80 - - - -
GB6 Bottom Reinforcement 12 @180mm 9.45 20x30 2 2 - - - - - - - -
Strirrups 8 0.18 0.9 8.9 49 2 88.20 - 88.20 - - - - - -
Total Length (m) - 1,436.72 - 795.38 - - - -
Unit Weight (mkg) 0.222 0.395 0.617 0.889 1.210 1.580 2.469 3.556
Total Weight (m) - 573.99 - 707.00 - - - -
BAR SCHEDULE FOR G+1 RESIDENTAIL BUILDING
Reinforcement Diameter
Location Dia C/C Length Size No Member Total length
6 8 10 12 14 16 20 24.00
B-SUBPER STRUCTURE
Ground Floor Column
Main Reinforcement 12 @150mm 5.11 20x20 4 26 531.44 - - - 531.44 - - - -
C1
Strirrups 8 0.15 0.70 3.55 24 26 436.80 - 436.80 - - - - - -
Main Reinforcement 12 @150mm 4.61 20x20 4 4 73.76 - - - 73.76 - - - -
C1
Strirrups 8 0.15 0.70 3.35 22 4 61.60 - 61.60 - - - - - -
Top Tie Beam t op
Top Reinforcement 12 @180mm 5.65 20x30 2 4 45.20 - - - 45.20 - - - -
TTB1 Bottom Reinforcement 12 @180mm 5.15 20x30 2 4 41.20 - - - 41.20 - - - -
Strirrups 8 0.18 0.9 4.7 26 4 93.60 - 93.60 - - - - - -
Top Reinforcement 12 @180mm 29.51 20x30 2 2 118.04 - - - 118.04 - - - -
TTB2 Bottom Reinforcement 12 @180mm 28.41 20x30 2 2 113.64 - - - 113.64 - - - -
Strirrups 8 0.18 0.9 28.3 157 2 282.60 - 282.60 - - - - - -
Top Reinforcement 12 @180mm 22.21 20x30 2 1 44.42 - - - 44.42 - - - -
TTB3 Bottom Reinforcement 12 @180mm 20.94 20x30 2 1 41.88 - - - 41.88 - - - -
Strirrups 8 0.18 0.9 20.6 114 1 102.60 - 102.60 - - - - - -
Top Reinforcement 12 @180mm 9.95 20x30 2 7 139.30 - - - 139.30 - - - -
TTB4 Bottom Reinforcement 12 @180mm 9.45 20x30 2 7 132.30 - - - 132.30 - - - -
Strirrups 8 0.18 0.9 8.91 49 7 308.70 - 308.70 - - - - - -
Top Reinforcement 12 @180mm 10.2 20x30 2 2 40.80 - - - 40.80 - - - -
TTB5 Bottom Reinforcement 12 @180mm 9.7 20x30 2 2 38.80 - - - 38.80 - - - -
Strirrups 8 0.18 0.9 9.15 51 2 91.80 - 91.80 - - - - - -
Top Reinforcement 12 @180mm 9.95 20x30 2 2 39.80 - - - 39.80 - - - -
TTB6 Bottom Reinforcement 12 @180mm 9.45 20x30 2 2 37.80 - - - 37.80 - - - -
Strirrups 8 0.18 0.9 8.9 49 2 88.20 - 88.20 - - - - - -
Total Length (m) - 1,029.10 - 906.94 - - - -
Unit Weight (mkg) 0.222 0.395 0.617 0.889 1.210 1.580 2.469 3.556
Total Weight (m) - 406.56 - 806.17 - - - -
BOQ For Dire Dawa Airport Police Residence
Item
Description Unit Quantity Rate Amount
No
A. Sub Structure
1. Earth Work
1.1 Clear and remove top soil to an average depth of 20 cm. M² 396.41 - -
Trench excavation for masonry foundation depth not exceeding
1.2 60cm starting from the reduced natural ground level & the price M³ 50.15 10.00 501.50
include any earth content (soil type).
1.3 Bulk Excavation to an average depth of 60 cm from NGL. M³ 73.87 10.00 738.74
Trench excavation for septic tank under toilet building with a
1.4 M³ 40.56 100.00 4,056.00
depth not exceeding 150cm
Trench excavation for septic tank under toilet building with a
1.5 M³ 40.56 100.00 4,056.00
depth between 150cm-300 cm.
Trench excavation for septic tank under toilet building with a
1.6 M³ 31.37 50.00 1,568.32
depth between 300cm-450 cm.
Back fill around the foundation and under hardcore with selected
1.7 M³ 39.70 5.00 198.48
material.
Car away surplus materials to a distance not exceeding 5km from
1.8 M³ 315.79 5.00 1,578.96
site
Provide 20cm thick basaltic or equivalent stone hardcore
1.9 surface are well compacted & blinded with crush gravel under M² 360.05 250.00 90,012.50
ground floor slab and septic tank bed concrete.
Sub Total (1)…........................... 102,710.50
2. Masonry
50cm thick basaltic or equivalent stone masonry foundation
2.1 wall below NGL bedded in (1:3) cement ratio with full joist under M³ 92.59 2,000.00 185,184.38
grade beam and septic tank slab.
2.2 Ditto but above NGL with proper pointing. M³ 12.54 2,000.00 25,075.00
Sub Total (2)…........................... 210,259.38
3. Concrete Work
5cm lean concrete C-5, 150kg/m3 cement of concrete under
3.1 M² 86.90 10.00 869.02
masonry, grade beam.
3.2 RC quality C-25 , 360kg/m3 cement.
a) 100mm Thick Slab M³ 33.30 2600 86,582.60
b) Grade Beam M³ 11.75 2600 30,544.80
c) 150mm Thick Slab M³ 3.46 2800 9,676.80
Provide, cut and fix in position sawn zigba wood or steel
3.3
formwork which ever appropriate.
a) Grade Beam M² 119.28 100 11,928.00
b) 150mm Thick Slab M² 23.04 240 5,529.60
3.4 Steel reinforcement
a) dia 8 mm deformed bar kg 573.99 140 80,357.93
b) dia 12 mm deformed bar kg 707.00 130 91,910.58
Sub Total (3)…........................... 317,399.32
B. Super Structure
1. Concrete Work
1.1 Provide, cut and fix in position swan Zigba formwork.
a) Elevation Column M² 84.80 220.00 18,656.00
b) Top Tie Beam M² 119.28 220.00 26,241.60
1.2 RC quality C-25 , 360kg/m3 cement.
a) Elevation Column M³ 16.96 2500.00 42,400.00
b) Top Tie Beam M³ 11.75 2500.00 29,370.00
1.3 Steel reinforcement
a) dia 8 mm deformed bar kg 406.56 130.00 52,852.54
b) dia 12 mm deformed bar kg 806.17 130.00 104,801.96
Sub Total (1)…........................... 274,322.10
BOQ For Dire Dawa Airport Police Residence
Item
Description Unit Quantity Rate Amount
No
2. Block Works
Hollow concrete block class B for external & Internal wall bedded in
2.1 cement mortal 1:3 ratio approved by site Engineer.
a. 20 * 20 * 40 cm M² 820.42 400.00 328,168.00
b. 15 * 15 * 40 cm M² 79.57 400.00 31,826.00
c. 10 * 10 * 40 cm M² 37.51 400.00 15,004.00
Sub Total (2)…........................... 374,998.00
3. Roofing and Carpenter
G28 CIS Roofing (without truss and purlin) price includes ridge cover
3.1 and washer
M² 397.69 900.00 357,921.00
3.2 All structural member shall be well seasoned
a) 12 cm. dia. Upper & Lower Chords Eucaliptus Wood ML 236.39 40 9,455.60
b) 10 cm. dia. Vertical & Diagonal Members of a Truss ML 183.48 38 6,972.24
c) 5 X 7 cm Wood Roof Purlin ML 107.80 70 7,546.00
3.3 PVC Down Pipe (Dia 75mm) ML 46.8 110 5,148.00
3.4 Gutter development size 60Cm ML 43.15 550 23,732.50
3.5 Flashing ML 20 250 5,000.00
Sub Total (3)…........................... 415,775.34
4. Ceiling Work
Ceiling covered with PVC material with all frames and required
4.1 acessories including bedding wooden support. The cost include all M² 379.30 500 189,650.00
material used for three coat of product painting
Sub Total (4)…........................... 189,650.00
5. Finishing Works

5.1 Apply three coat of cement sand plaster to internal and external surface. M² 1874.99 220 412,497.80
5.2 Gypsum plastering to all internal plastered surface. M² 1054.57 110 116,002.70
3cm thick cement screed ratio 1:3 applied on floor with proper well
5.3 smoothed finish.
M² 356.05 160 56,968.00
5.4 Half concrete pipe open side Ditch diameter of 30 cm ML 65.4 400 26,160.00
Sub Total (5)…........................... 611,628.50
6. Painting Work
Apply three coats of product plastic emulsion paint to all internal wall
6.1 and structural members.
M² 1054.57 110 116,002.70
Apply three coats of oil paint to all toilet and shower rooms internal
6.2 wall and structural members.
M² 138.11 180 24,858.90
6.3 Apply Quartiz paint to all external wall and structural members. M² 820.42 290 237,921.80
6.4 Oil piant skirting to wall with 10cm thickness. ML 186.20 25 4,655.00
Sub Total (6)…........................... 383,438.40
7. Metal Work
Supply, produce and fix doors & windows fully metal 38 LTZ with all
acessories such as hing, lock. Doors are with ribbed sheet metal. Price
7.1 include cost for door ribbed sheet and all accessories. Cost for Glazing
is seprate.
W1 (1200x1500mm) No 8 6480 51,840.00
W2 (1600x1500mm) No 1 8640 8,640.00
W3 (1500x3000mm) No 2 16200 32,400.00
W4 (1200x600mm) No 2 2592 5,184.00
W5 (1050x600mm) No 2 2268 4,536.00
D1 (1000x2500mm) No 10 9000 90,000.00
D2 (900x2500mm) No 3 8100 24,300.00
D3 (2000x2500mm) No 1 18000 18,000.00
D4 (650x2500mm) No 8 5850 46,800.00
D5 (700x2500mm) No 2 6300 12,600.00
Sub Total (7)…........................... 294,300.00
8. Glazing
4 mm thick tinted sheet glass glazed with beads & rubber gasket and
8.1 sealant to LTZ profile frames of windows and window-doors
M² 46.86 2000 93,720.00
Sub Total (8)…........................... 93,720.00
BOQ For Dire Dawa Airport Police Residence
Item
Description Unit Quantity Rate Amount
No
9. Sanitary Installation
Water Supply Pipes & fittings
Supply and install PPR pipes to water distribution to all sanitary
9.1
fixtures as shown on the drawing
Diameter 20 mm ml 32.00 130.00 4,160.00
Supply and install gate valves made of brass complete with rubber
9.2 gaskets, hand wheels and connecting pieces such as unions etc., for all
fixtures
Diameter 20 mm No 3.00 600.00 1,800.00
Sanitary Fixtures -
Supply and fix wash down WC with Low level Flush Cistern,
9.3 Complete with all necessary accessories.
No 4.00 4,000.00 16,000.00
9.4 750x750mm shower tray with all necessary fixtures. No 4.00 2,500.00 10,000.00
Supply and install hand wash basins made of white vitreous China
9.5 with two tap holes complete with all the necessary accessories No 1.00 4,500.00 4,500.00
Size 1200 x 600 mm
Supply and mount 5m³ plastic water tank on the ground with 20cm
9.6 thick concrete slab. Price include all the necessary accessories and No 1.00 30,000.00 30,000.00
required base foundation for plastic tanker.
Waste water & Ventilation Pipe
Supply and install , waste and vent pipe in horizontal branches and
vertical stacks made of PVC including the necessary fittings such as
9.7 bends, branches tees, elbow etc. All horizontal branches should be laid
at a slope of 2% .
Diameter 110 mm ml 24.00 200.00 4,800.00
Supply and install vent caps made of PVC at vent pipes fitted with
9.8 PVC pipe roof weathering slate at roof level.
Diameter 110 mm pcs 2.00 500.00 1,000.00
Sub Total (9)…........................... 72,260.00
10. Electrical Installation
10.1 Two way switch No 9 350.00 3,150.00
10.2 Single switch No 12 300.00 3,600.00
10.3 Surface mounted 1x60W Incandnscent Fitting type No2 No 22 1,400.00 30,800.00
10.4 Surface mounted 2x36W Fluorescent fitting type No 1 No 21 1,800.00 37,800.00
10.5 Surface mounted twin-socket 16A/1P+N+E No 28 350.00 9,800.00
10.6 Electric Cable installation with 2.5mm thick wire ML 282 60.00 16,920.00
Sub Total (10)…........................... 102,070.00

You might also like