Item # Item Descr iption Unit Factor Length Width Depth Qty Remar ks
Pile cap 1 -
note. Blinding/Mass Concrete 20MPa allow 100mm off set each side
Blinding m3 1. 00 13. 00 3. 30 0. 05 2. 15
Allow deduction of Piles - DN1. 8m -3. 00 2. 54 0. 05 -0. 38
Total Blinding 1. 76
Pilecap No1
note. Structural concrete= 55mpa - C2
m3 1. 00 12. 80 3. 10 2. 50 99. 20
Total Pile cap 1 conc vol m3 100. 96
Pier 5 Pilecap -
Blinding m3 1. 00 13. 30 3. 30 0. 05 2. 19
Allow deduction of Piles - DN1. 8m -3. 00 2. 54 0. 05 -0. 38
Total Blinding 1. 81
Pile cap No 5
m3 1. 00 13. 10 3. 10 2. 50 101. 53
Total Pile cap 5 conc vol m3 103. 34
Total Pile caps conc vol 550. 54
Abutments
Abutment A-
note. Blinding mpa=20
Blinding m3 1. 00 20. 31 5. 00 0. 05 5. 08
Allow deduction of Piles - DN1. 5m -4. 00 1. 77 0. 05 -0. 35
Total blinding 4. 72
note. Structural concrete= 40mpa -B2
Ar ea 1 Base m3 1. 00 20. 11 4. 80 2. 00 193. 06
Wing wall 1. 00 1. 20 0. 75 2. 57 2. 31
1. 00 2. 40 0. 40 3. 09 2. 97
Total wing wall 5. 27
Total Abutment B conc vol 260. 26