DIMENSION (M)
NO AREA QTY VOLUME TOTAL UNIT REMARK
Around Length Width Height
1 Excavation
14.44 10.80 0.25 1 38.97 38.97 m3
2 Lean Concrete
14.04 10.40 0.05 1 7.30 7.30 m3
3 Concrete
13.84 10.20 0.50 1 70.56 Foundation
0.35 0.35 3.50 6 2.57 Column C-1
5.75 0.25 0.40 6 3.45 Roof Beam
4.25 0.25 0.40 6 2.55 79.13 m3 Roof Beam
4 Formwork
14.04 0.50 2 14.04 Foundation
10.40 0.50 2 10.40 Foundation
3.50 0.35 24 29.40 Column C-1
5.75 0.25 6 8.63 Roof Beam
5.75 0.40 12 27.60 Roof Beam
4.25 0.25 6 6.38 Roof Beam
4.25 0.40 12 20.40 116.84 m2 Roof Beam
5 Backfill 3.45 m3
Note :
CALCULATION SHEET
RE - BAR
b COLUMN
a 1 19 0.41 3.78 0.41 4.60 2.23 72 736.31 Main bar
a
b b
3 10 0.08 0.25 0.08 1.15 0.62 126 89.33 Ties S1
b
3 10 0.08 0.25 0.08 1.15 0.62 144 102.09 Ties S2
Type no. 3
BEAM RB-1
1 16 0.10 9.15 0.10 9.35 1.58 18 265.62 Main bar RB-1
2 16 9.15 9.15 1.58 12 173.29 Side bar RB-1
4 10 0.08 0.15 0.30 1.05 0.62 44 28.48 Stirrup S1 RB-1
4 10 0.08 0.15 0.30 1.05 0.62 32 20.71 Stirrup S2 RB-1
BEAM RB-2
b
a 1 19 0.12 12.15 0.12 12.39 2.23 18 496.35 Main bar RB-2
a
2 19 12.15 12.15 2.23 12 324.49 Side bar RB-2
c c 4 10 0.08 0.15 0.30 1.05 0.62 44 28.48 Stirrup S1 RB-2
4 10 0.08 0.15 0.30 1.05 0.62 52 33.66 Stirrup S2 RB-2
b
Type no. 4 CHAIR
5 19 0.50 0.30 0.50 2.10 2.23 108 504.76
8344.91 Kg
c
b
a b a
Type no. 5
Note :