You are on page 1of 2

CONCRETE WORKS

Dimensions (m) Volume


No. of Units
Width Depth Length (m^3)

a. Footing -1 1.5 1.5 0.3 8 5.4


b. Footing -2 1.2 1.2 0.25 2 0.72
c. Footing Tie Beam 0.3 0.25 19.775 1 1.483125
d. Wall Footing 1 0.4 0.15 15.19 1 0.9114
e. Wall Footing 2 0.4 0.15 8.07 1 0.4842

f. Columns:
Column 1 (Foundation - 2nd floor) 0.3 0.3 4.5 8 3.24
Column 2 (Foundation - 2nd floor) 0.3 0.3 4.25 2 0.765
C1 & C2 (2nd Floor - Roof Beam) 0.25 0.25 2.8 10 1.75
Planted Column (2nd Floor - Roof
Beam) 0.25 0.25 2.8 2 0.35

g. Beams:
Girder 1 & Girder 2 0.25 0.4 40.01 1 4.001
Beam 1 & Beam 2 0.2 0.35 19.42 1 1.3594
Cantilever Girder 1 &
Cantilever Girder 2 0.25 0.4 7.24 1 0.724
Roof Beam 1 0.2 0.3 31.26 1 1.8756
Roof Beam 2 0.15 0.3 7 1 0.315
Cantilever Roof Beam 0.2 0.3 4 1 0.24

h. Slab:
Ground Floor 8.67 8.5 0.1 1 7.3695
Second Floor 53.914 0.1 1 5.3914

i. Stair Footing 0.2 0.4 1 1 0.08


0.15 0.4 1 1 0.06

j. Stairs 0.038 1 15 0.57


1 1 0.2 1 0.2

k. Lintel Beam 0.1 0.25 20.2 1 0.505


I. Septic Tank 0.15 1.5 4.2 1 0.945
m. Rainwater Tank 0.15 1.3 1.3 1 0.2535
n. Catch Basin 0.1 0.6 0.6 1 0.036
TOTAL VOLUME OF CONCRETE,
(m^3): 39.02913

WASTE FACTOR: 10% 1.1

TOTAL VOLUME OF CONCRETE WITH


WASTE FACTOR , (m^3): 42.93204

VOLUME OF CONCRETE PER BATCH,


(m^3/batch): 0.1193

NO. OF BATCHES: 359.8662