Soil Volume Removed

S. No. Excavation Type Depth (ft) Area (ft2) Volume (ft3)


1 Plot excavation (from RL to BFL) 10.00 1800.00 18000.00
2 Footing Type 1 1.50 866.50 1299.75
3 Footing Type 2 2.00 431.25 862.50
4 RCC Floor 4in 0.33 164.25 54.75
5 Tapered Area 1 (Rft*Trig.Area) 62.00 1.13 69.75
6 Tapered Area 2 23.00 2.00 46.00
7 Tapered Area 3 10.75 0.13 1.34
8 Lift 7.00 195.00 1365.00
9 PCC 0.33 1800.00 600.00
Total Soil Removed (ft3) 22,299.09
Concrete Volume Summary
S. No. Concrete Mix Ratio Vol wet (Ft3) Vol dry (Ft3) Cement (ft3)
1 1.4.8 883 1,359 105
2 1.1.5.3 2,053 3,162 575
3 1.2.4 16,017 24,666 3,524
Sum: 18,953 29,188 4,203

Concrete Volume 1:4:8 883


S. No. PCC (1:4:8) Depth (ft) Area (ft2) Volume (ft3)
1 4" Beneath Raft & Lift 0.33 1800.00 600.00
2 Beneath Lift 1 (CL Rft*Rect.Area) 20.50 3.75 76.88
3 Beneath Lift 2 (CL Rft*Rect.Area) 11.25 5.50 61.88
4 Beneath Lift 3 (CL Rft*Trig.Area) 20.75 4.50 93.38
5 Beneath Lift 4 (CL Rft*Trig.Area) 11.25 4.50 50.63

Total Concrete Volume (1:4:8) 882.75

Concrete Volume 1:1.5:3 2,053


S. No. Concrete (1:1.5:3) Depth (ft) Area (ft2) Volume (ft3)
1 Col 12x18 146.00 1.50 219.00
2 Col 9x18 219.00 1.13 246.38
3 Col 9x36 511.00 2.25 1149.75
4 Col 9x48 146.00 3.00 438.00
0.00
Total Concrete Volume (1:1.5:3) 2,053.13

Concrete Volume 1:2:4 16,017


S. No. Concrete (1:2:4) Depth (ft) Area (ft2) Volume (ft3)
Foundation
1 Lift 2.00 195.00 390.00
2 Strip 18" 1.50 965.50 1448.25
3 Strip 24" 2.00 470.25 940.50
4 Floor 4" 0.33 189.00 63.00
5 Tapered Area 18" (Rft*Trig.Area) 69.00 1.13 77.63
6 Tapered Area 24" (Rft*Trig.Area) 26.50 2.00 53.00
7 Tapered Area 6" (Rft*Trig.Area) 20.75 0.50 10.38

RCC Walls
1 Basement RCC Walls (Rft*Area) 124.50 7.13 887.06
2 Tanks RCC Walls (Rft*Area) 77.00 5.45 419.65

Lift RCC Walls


1 4 Sides 9" Walls (Rft*Area) 79.00 20.25 1599.75
2 Doors Deductions (No.*Vol) -7.00 13.50 -94.50

Basement-Roof Slab
1 8" Slab 0.67 1560.00 1040.00
2 5" Slab 0.42 262.50 109.38
3 Openings -0.67 101.60 -67.73
4 Opening Lift -0.67 36.00 -24.00
5 B-1 28.50 0.88 24.94
6 B-2 22.50 0.88 19.69
7 B-3 41.50 0.88 36.31
8 B-4 20.50 0.38 7.69
9 B-4A 10.25 0.38 3.84
10 B-5 12.50 0.25 3.13
11 CB-1 8.00 0.06 0.48

Ground Floor-Roof Slab


1 8" Slab 0.67 949.00 632.67
2 6" Slab 0.50 98.00 49.00
3 Openings -0.67 10.00 -6.67
4 Opening Lift 0.00 0.00 0.00
5 B-1 104.00 0.81 84.45
6 B-1A 28.50 0.81 23.14
7 B-2 28.50 0.88 25.08
8 B-2A 22.50 0.88 19.80
9 B-3 22.00 0.58 12.76
10 B-4 18.00 0.37 6.66
11 B-5 28.00 0.37 10.36
12 CB-1 15.00 0.06 0.90

Mezzanine Floor-Roof Slab


1 8" Slab 0.67 1800.00 1200.00
2 8" Cantilever 0.67 7.50 5.03
3 Openings -0.67 101.60 -67.73
4 Opening Lift -0.67 36.00 -24.00
5 B-1 104.00 0.81 84.45
6 B-1A 28.50 0.81 23.14
7 B-2 28.50 0.88 25.08
8 B-2A 22.50 0.88 19.80
9 B-3 41.25 0.88 36.30
10 B-4 18.00 0.75 13.50
11 B-5 28.50 0.81 23.09
12 B-6 28.50 0.62 17.67
13 CB-1 8.00 0.06 0.48

First Floor-Roof Slab


1 8" Slab 0.67 1800.00 1200.00
2 8" Cantilever 0.67 7.50 5.03
3 Openings -0.67 101.60 -67.73
4 Opening Lift -0.67 36.00 -24.00
5 B-1 104.00 0.81 84.45
6 B-1A 28.50 0.81 23.14
7 B-2 51.00 1.08 55.08
8 B-3 41.25 1.08 44.55
9 B-4 18.00 0.75 13.50
10 B-5 28.50 0.81 23.09
11 B-6 28.50 0.81 23.09
12 CB-1 8.00 0.06 0.48

Second Floor-Roof Slab


1 8" Slab 0.67 1800.00 1200.00
2 8" Cantilever 0.67 7.50 5.03
3 Openings -0.67 101.60 -67.73
4 Opening Lift -0.67 36.00 -24.00
5 B-1 104.00 0.81 84.45
6 B-1A 28.50 0.81 23.14
7 B-2 51.00 1.08 55.08
8 B-3 41.25 1.08 44.55
9 B-4 18.00 0.75 13.50
10 B-5 28.50 0.81 23.09
11 B-6 28.50 0.81 23.09
12 CB-1 8.00 0.06 0.48

Third Floor-Roof Slab


1 8" Slab 0.67 1800.00 1200.00
2 8" Cantilever 0.67 7.50 5.03
3 Openings -0.67 101.60 -67.73
4 Opening Lift -0.67 36.00 -24.00
5 B-1 104.00 0.81 84.45
6 B-1A 28.50 0.81 23.14
7 B-2 51.00 1.08 55.08
8 B-3 41.25 1.08 44.55
9 B-4 18.00 0.75 13.50
10 B-5 28.50 0.81 23.09
11 B-6 28.50 0.81 23.09
12 CB-1 8.00 0.06 0.48

Fourth Floor-Roof Slab


1 8" Slab 0.67 1800.00 1200.00
2 8" Cantilever 0.67 7.50 5.03
3 Openings -0.67 101.60 -67.73
4 Opening Lift -0.67 36.00 -24.00
5 B-1 104.00 0.81 84.45
6 B-1A 28.50 0.81 23.14
7 B-2 51.00 1.08 55.08
8 B-3 41.25 1.08 44.55
9 B-4 18.00 0.75 13.50
10 B-5 28.50 0.81 23.09
11 B-6 28.50 0.81 23.09
12 CB-1 8.00 0.06 0.48

Mumty & Lift Top


1 5" Slab 0.42 214.00 89.88
2 6" Lift Top (Double Slab) 5.00 112.50 562.50

RCC Parapet
1 4.5" RCC Parapet (Rft*Area) 180.00 0.56 100.80

OHWT
1 8" Bot Slab 0.67 77.00 51.33
2 6" Top Slab 0.50 77.00 38.50
3 Openings -0.50 1.76 -0.88
4 RCC Walls (Rft*Area) 28.50 2.25 64.13
5 Beam 30.00 0.83 24.90

Stairs
1 6" RCC Stairs-All Floors 0.50 800.00 400.00
y
Sand (ft3) Crush (ft3) Cement Bags
418 837 84
862 1,725 460
7,048 14,095 2820
8,328 16,656 3,364
Volume Summary
S. No. Item Vol wet (Ft3) Vol dry (Ft3) Cement (ft3)
1 C/S Mortar 1:5 9,335 14,376 2,396
2 C/S Plaster (1:5) 7,417 11,422 1,904
3 1:1 Puddlo Plaster 514 791 791
Sum: 17,266 26,589 5,091

Total Number of Bricks: 84,005


Total S.Area for Termite Proofing (sft) 4,005
Total Water Stopper Length (ft) 260

Total Wall Volume


S. No. Wall Length (Rft) Height (ft) Wall Th. (ft)
Basement:
1 9" Inner Walls 32.00 9.50 0.75

Ground Floor:
1 9" Inner Walls 20.50 7.75 0.75
2 4.5" Inner Walls 26.00 7.75 0.375
3 9" Outer Walls 105.00 7.75 0.75
4 Minus Lift Wall -7.50 7.75 0.75

Mezzanine Floor
1 9" Inner Walls 20.50 6.75 0.75
2 4.5" Inner Walls 26.00 6.75 0.375
3 9" Outer Walls 105.00 6.75 0.75
4 Minus Lift Wall -7.50 6.75 0.75

First Floor
1 9" Inner Walls 20.50 9.75 0.75
2 4.5" Inner Walls 26.00 9.75 0.375
3 9" Outer Walls 124.00 9.75 0.75
4 Minus Lift Wall -7.50 9.75 0.75

Second Floor
1 9" Inner Walls 20.50 9.75 0.75
2 4.5" Inner Walls 26.00 9.75 0.375
3 9" Outer Walls 124.00 9.75 0.75
4 Minus Lift Wall -7.50 9.75 0.75

Third Floor
1 9" Inner Walls 20.50 9.75 0.75
2 4.5" Inner Walls 26.00 9.75 0.375
3 9" Outer Walls 124.00 9.75 0.75
4 Minus Lift Wall -7.50 9.75 0.75

Fourth Floor
1 9" Inner Walls 20.50 9.75 0.75
2 4.5" Inner Walls 26.00 9.75 0.375
3 9" Outer Walls 124.00 9.75 0.75
4 Minus Lift Wall -7.50 9.75 0.75

Mumty
1 9" Inner Walls 0.00 9.75 0.75
2 4.5" Inner Walls 0.00 9.75 0.375
3 9" Outer Walls 60.50 9.75 0.75
4 Minus Lift Wall 7.50 9.75 0.75

Sum:

Puddlo Plaster: Total Surface Area


S. No. Wall Length (Rft) Height (ft) Faces
Septic Tank
1 9" RCC Walls 29.00 7.25 1
2 Base 7.25 7.25 1

UGWT
1 9" RCC Walls 29.00 7.25 1
2 Base 7.25 7.25 1

OHWT
1 9" RCC Walls 28.50 4.00 1
2 Base 8.25 5.50 1

Sum:

Termite Proofing: Total Surface Area


S. No. Wall Length (Rft) Height (ft) Faces
Basement
1 9" RCC Walls 180.00 12.25 1
2 RCC Floor 30.00 60.00 1

Sum:

Water Stopper 260


S. No. Wall Length (Rft)
1 Basement Walls 190.00
2 Septic Tank Walls 16.00
3 UGWT Walls 16.00
4 OHWT Walls 38.00
Sum: 260.00
Sand (ft3) Cement Bags Puddlo (kg)
11,980 1917 0
9,518 1523 0
0 633 3165
21,498 4,073 3,165

84,005
4,005
260

6,537 Plaster:Total Wall S. Area 18,824


Volume (ft3) Surface Area Faces Area (ft2)

228.00 304.00 2 608.00

119.16 158.88 2 317.75


75.56 201.50 2 403.00 *Bricks:
610.31 813.75 2 1627.50 *Mortar
-43.59 -58.13 2 -116.25

103.78 138.38 2 276.75


65.81 175.50 2 351.00
531.56 708.75 2 1417.50
-37.97 -50.63 2 -101.25

149.91 199.88 2 399.75


95.06 253.50 2 507.00
906.75 1209.00 2 2418.00
-54.84 -73.13 2 -146.25

149.91 199.88 2 399.75


95.06 253.50 2 507.00
906.75 1209.00 2 2418.00
-54.84 -73.13 2 -146.25

149.91 199.88 2 399.75


95.06 253.50 2 507.00
906.75 1209.00 2 2418.00
-54.84 -73.13 2 -146.25
149.91 199.88 2 399.75
95.06 253.50 2 507.00
906.75 1209.00 2 2418.00
-54.84 -73.13 2 -146.25

0.00 0.00 2 0.00


0.00 0.00 2 0.00
442.41 589.88 2 1179.75
54.84 73.13 2 146.25

6,537.38 Sum: 18824.00

685
S.Area (ft2)

210.25
52.56

210.25
52.56

114.00
45.38

685.00

4,005
S.Area (ft2)

2205.00
1800.00

4,005.00
12.85 No. per cft
1.428 cft per cft