CENTER LINE METHOD

S.NO DESCRIPTION OF ITEM NO.s LENGTH (M) WIDTH(M)


1 EARTH WORK IN EXCAVATION 49.7 0.8

2 PCC IN FOUNDATION 49.7 0.8

3 BRICK WORK
IN FOUNDATION AND UPTO PLINTH
FOR STEP 600 52.6 0.6
FOR STEP 500 52.8 0.5
FOR STEP 400 53 0.4
FOR STEP 300 53.2 0.3

UPTO PLINTH 53.5 0.15

IN SUPER STRUCTURE
IN WALLS 53.5 0.15

IN PARAPET WALL 36 0.15

4 DPC WORK 53.5 0.15

5 DEDUCTION
DOOR
D1 4 1 0.15
D2 2 0.8 0.15
WINDOW
W1 6 1.2 0.15
W2 2 0.6 0.15
LINTEL
DOOR
D1 4 1.3 0.15
D2 2 1.1 0.15
WINDOW
W1 6 1.5 0.15
W2 2 0.9 0.15

6 RRC IN LINTEL @ 1% STEEL IN LINTEL


REINFORCEMENT

7 RRC IN ROOF 25.7


REINFORCEMENT
BRICK WORK = 54.4 CU.M
DEDUCTION = 3.57 CU.M
DPC = 8.02 SQ.M
RCC = 4.2 CU.M
PCC = 3.9 CU.M
EXCAVATION = 47.7 CU.M
STEEL = 330 KG
ER LINE METHOD
HEIGHT(M) UNIT QUANTITY CALCULATIONS
1.2 CU.M 47.712 53.8-NO OF JUNCTION (10)X 0.5 XWIDTH (0.8)=49.7

0.1 CU.M 3.976

0.1 CU.M 3.156 53.8-10X0.5X0.6= 52.6


0.1 CU.M 2.64 53.8-10X0.5X0.5= 52.8
0.1 CU.M 2.12 53.8-10X0.5X0.4= 53.0
0.8 CU.M 12.768 53.8-10X0.5X0.3= 53.2

0.6 CU.M 4.815 53.8-10X0.5X0.15= 53.5

3 CU.M 24.075

0.9 CU.M 4.86


TOTAL 54.434
SQ.M 8.025
TOTAL 8.025

2.1 CU.M 1.26


2.1 CU.M 0.504

1.2 CU.M 1.296


0.6 CU.M 0.108
ASSUME BEARING OF 300MM

0.15 CU.M 0.117


0.15 CU.M 0.0495

0.15 CU.M 0.2025


0.15 CU.M 0.0405
TOTAL 3.5775

0.4095
KG 32 1% X QUNATITY OF CONCRETE X DENDITY OF STEEL

0.15 CU.M 3.855


KG 298 1% X QUNATITY OF CONCRETE X DENDITY OF STEEL