SUBJECT :- Estimated Qty's.
Item Brief Description of Item No No L B D Qty
No
Plinth Level
1474.58 Cum
5 PCC 1:3:6 :-
F2 1 24 2.000 2.000 0.1 9.60
6 Footings : M20
1 24 1.800 1.800 0.4 31.10
31.104
28.2240
Plinth Beams
B-1 1 2 56.4 0.2 0.900 20.304
B-2 1 2 15.9 0.2 1.000 6.340
26.64
12065.91 kg
GROUND FLOOR
74.99 Cum
434.19 SQM
OUTER PLASTER
1 2 56.85 3.9 443.43
1 2 15.85 3.9 123.63
567.06 SQM
PROJECT
0
SUBJECT :- Estimated Cost of work
Item Particulars Unit Qty SAND GITTI GSB MURRUM BRICKS CEMENT
No
civil work
1 PCC 1:3:6 below foundation work Cqm 9.6 5.8 8.6 33.6
3 Providing and filling in Murrum for plinth Cqm 1474.6 1622.0
3 M20 grade of concrete cum 220.5 132.3 198.4 1653.6
4 Brick work of 200mm thk below Plinth beams cum 11.6 3.5 5198.4 15.6
6 STEEL WORKS :- kg 12066
7 200mm thick masonry work Cum 75.0 20.2 33744.6 101.2
8 Internal plastering works : Sqm 434.2 8.7 52.1
9 External plastering works : Sqm 567.1 19.8 79.4
10 J.K Primex Sqm 567.1