PROJECT :-

Shed ( 19.8X29 )
SUBJECT :- Estimated Qty's.
Item Brief Description of Item No No L B D Qty
No

Plinth Level

1 P/filling in Plinth by murrum


1 1 15.9 56.4 1.800 1609.09 1609.09

Deductions RCC -134.51

1474.58 Cum

2 Brick work of 200mm wide for Plinth Beam bottoms :-


Below Plinth Beam 1 2 15.80 0.2 0.4 2.53
1 2 56.40 0.2 0.4 9.02

Total Qty of 200mm thk Brick work for BELOW PLINTH


11.55 cum

5 PCC 1:3:6 :-
F2 1 24 2.000 2.000 0.1 9.60

Total Qty. of PCC 9.60 Cum

6 Footings : M20
1 24 1.800 1.800 0.4 31.10

31.104

Column Below Plinth


C2 1 24 0.4 0.7 4.2 28.22

28.2240

Plinth Beams
B-1 1 2 56.4 0.2 0.900 20.304
B-2 1 2 15.9 0.2 1.000 6.340
26.64

Plinth Slab 1 1 56.40 15.90 0.150 134.514


134.514

Total Qty. of R.C.C 220.49


8 Steel Work 12065.91

12065.91 kg

GROUND FLOOR

Column 46 1 0.2 0.3 3.8 10.5

Lintel 2 1 15.9 0.2 0.3 1.9


2 1 56.4 0.2 0.3 6.8

Total Qty. of Grd floor columns in M 20 gr 19.16 Cum

12 Brick masonry work :-

200mm 2 1 15.85 0.200 2.700 17.12


2 1 56.4 0.200 2.700 60.91
Deductions
RS -1 1 0.2 3.900 3.900 -3.04

74.99 Cum

13 Internal plaster works :-


a) At Grd floor :-
2 1 56.85 3.3 375.21
2 1 15.85 3.3 104.61
Deduction
rs -3 1 3.9 3.9 -45.63

434.19 SQM

OUTER PLASTER
1 2 56.85 3.9 443.43
1 2 15.85 3.9 123.63

567.06 SQM
PROJECT
0
SUBJECT :- Estimated Cost of work
Item Particulars Unit Qty SAND GITTI GSB MURRUM BRICKS CEMENT
No
civil work
1 PCC 1:3:6 below foundation work Cqm 9.6 5.8 8.6 33.6
3 Providing and filling in Murrum for plinth Cqm 1474.6 1622.0
3 M20 grade of concrete cum 220.5 132.3 198.4 1653.6
4 Brick work of 200mm thk below Plinth beams cum 11.6 3.5 5198.4 15.6
6 STEEL WORKS :- kg 12066
7 200mm thick masonry work Cum 75.0 20.2 33744.6 101.2
8 Internal plastering works : Sqm 434.2 8.7 52.1
9 External plastering works : Sqm 567.1 19.8 79.4
10 J.K Primex Sqm 567.1

190.3 207.1 0.0 1622.0 38943.0 1935.6

CIVIL BOM UNIT QTY RATE AMOUNT

1 STEEL MT 12.1 43500 524867


2 CEMENT BAGS 1935.6 300 580670
COST OF CEMENT & STEEL(A) 1105536
COST PER SQ FT 115

3 MURRUM CUM 1622.0 180 291966


4 SAND CUM 190.3 1750 333016
6 AGGREGATE CUM 207.1 700 144954
7 BRICKS NOS 38943.0 5 194715
8 20 micron black sheet sqm 893.9 4 3576
9 polyshulphide chemical rm 447.50 70 31325
10 Floor hardner kg 1787.88 12.5 22349
11 GP2 material sqm 4.80 1800 8640
13 Rooling shutters sqm 21.00 4000 84000
TOTAL 1639541
AREA IN SQ FT 9622
MATERIAL COST PER SQ FT(A) 170
Wastage 3% 5

LABOR CHARGES( B) INCLUDING CARTING AWAY OF SOIL & DISPOSAL OF SOI 80


TOTAL A+B 256
COST OF CEMENT-STEEL PER SQ. FT. 115
TOTAL PER SQ FT COST 370