PHASE DESCRIPTION ACTIVITIES WT% VALUE AMOUNT Actual Work Accomplishment STATUS
SUPERSTRUCTURE-A - Concrete Pouring Of Beams For 2nd Floor Cocrete Pouring Of Beams For 2nd Floor Beams Done
5 - Forms & Scaffolding
15.00% Forms & Scaffolding For 2nd Floor Done
(Ground Floor - 2nd Floor)
- Exterior CHB Laying For All Perimeter On The Ground
Floor
Exterior CHB Laying Ground Floor Done
- Interior CHB Laying @ Ground Floor Interior CHB Laying Ground Floor Done
- This Include All Concrete & Rebar Works Of The
Following: ₱792,353.26
- All Sets Of Columns, Beams @ 2nd Floor
- Suspended Slab @ 2nd, Forms & Scaffolding Suspended Slab @ second Floor
SUPERSTRUCTURE-B - Exterior & Interior CHB Laying 2nd Floor Exterior and Interior CHB Laying on going
6 15.00%
(2nd Floor - Roof Beams) - Slab On fill @ Ground Floor, Forms & Scaffolding Slab On Fill @ Ground Floor Done
- 1m Concrete Pavement & 7m Parking Lot @ Ground
Level Forms and Scaffoldings on going
- Plumbing & Electrical Works ( Rough-Ins) For Ground
Floor
Plumbing & Electrical Works Rough-Ins for Ground Floor Done
- This Include All Concrete & Rebar Works Of The
Following: ₱528,235.50
Steel Truss & Roofing, Canopies
SUPERSTRUCTURE-C - Staircase Interior & Exterior, Septic Tank, Drainage,
7 Sewer & Water Lines 10.00% Septic Tank, Interior Stair Case Done
(ROOF BEAMS - ROOFING)
- Electrical Rough-In Works @ 2nd Floor, & Plastering Exterior Staircase on going
-Installation Of All Wooden Door For Exit, Rooms & Toilet
- Ceiling Installation @ Ground & 2nd Floor
₱528,235.50
8 CONCRETE FENCE ENCLOSURE & STEEL GATE
10.00%