INSPECTION REPORT
Legend:
PROJECT: NEW CONSTRUCTION OF 2-STOREY RESIDENCE WITH BASEMENT
LOCATION: LOT 6, BLOCK 21-A HILLCREST ESTATES, CALAMBA, LAGUNA
Added items not on submitted BOQ but
OWNER: CARMELITA V. CRUZ as per design, and as per actual site
DATE: SEPT 26 2022
Wood Tile Cladding (Exterior Wall at One side of wall not installed as per
WF-03 Balcony) 15,803.63 design, Incomplete grout
Not installed properly, For
WF-06 600mm x 1200mm Porcelain Tiles 59,618.10 replacement
Walls not complete and Not installed
WF-11 T&B Wall Tiles 221,346.95 properly, For replacement
Supply and install estimated cost,
Should be included by Gencon, As per
Jacuzzi Area Wall Tiles (17sqm) 34,776.00 design
Supply and install estimated cost,
Should be included by Gencon, as
Wood Slats Cladding for Altar 7,500.00 discussed
7.00 Floor Finishes
20x120 Porcelain Tiles (Lanai/BBQ Area,
FF-03 Pool surround) 42,069.00 Not supplied & installed
FF-04 60x60 Porcelain Tiles (Service Areas) 57,646.00 Not supplied & installed