PROPOSED CHLORINATION UNIT

BILLS OF QUANTITIES

ITEM RATE AMOUNT


DESCRIPTION UNIT QTY
NO (LKR) (LKR)

B EXCAVATION AND EARTH WORK


Allow Lump Sum for Clearing site, bushes,
Lum
B01 shrubs under growth hedges and up rooting -
sum
trees
-
Excavating to reduce level average depth of
B02 m2 15.51 200.00 3,102.00
150mm
-
Excavation for Wall and Column foundations
in any material except rock requiring blasting,
B03 m3 9.12 2,150.00 19,612.30
depth not exceeding 1500mm from the
existing Ground level.
-
Supplying and Filling under floors and under
Steps with approved earth in layers not
B04 m3 11.02 5,350.00 58,957.00
exceeding 150mm including watering and
ramming.
-
B - Sub Total Carried to Summary 81,671.30

C CONCRETE WORK

Grade 15 (40) Concrete


Pad Footing
75 mm thick Screed concrete under column
C01 m2 5.88 3,750.00 22,050.00
foundation.
-
Wall foundation -
75 mm thick screed concrete under Wall
C02 m2 8.13 3,750.00 30,487.50
foundation
-
1 :2 1/2 :5 (25mm) Volumed Batched Mass
-
Concrete
100mm thick Floor concreting in ground floor
C03 m3 0.97 53,000.00 51,410.00
and steps
-
Grade 20(20) Concrete -
Pad Footing -
3
C04 Reinforced concrete in Column foundation m 1.33 55,500.00 73,815.00
-
Columns -
Reinforced concrete in Columns upto Ground
C05 m3 1.44 55,500.00 79,920.00
Level
-
Reinforced concrete in Columns from Ground
C06 m3 0.58 55,500.00 32,190.00
Level to Roof level
-
Beams -
C07 Reinforced concrete in Roof Beam. m3 0.10 55,500.00 5,550.00
ITEM RATE AMOUNT
DESCRIPTION UNIT QTY
NO (LKR) (LKR)
-
Formwork -
Pad Footing -
C08 Sides of screed m 24.00 180.00 4,320.00

C09 Sides of Column Staircase foundation m2 4.41 2,600.00 11,466.00


-
Columns -

C10 Sides of Column shafts upto Ground level m2 2.48 2,600.00 6,448.00
-
Sides of Columns from Ground Level to Roof 2
C11 m 10.28 2,600.00 26,728.00
level
-
In sides and Edges of Beam and Slab -
C12 Sides of roof beam m2 2.00 2,600.00 5,200.00
High yield Steel reinforcement & Mild Steel
-
reinforcement
-
Pad footing -

C13 Column foundation kg 152.19 785.00 119,469.15


Columns -

C14 Column shaft upto Ground Level kg 47.29 785.00 37,122.65

C15 Columns from Ground Level upto Roof Level kg 118.63 785.00 93,124.55
Beams -
C16 Beam at Roof kg 20.13 785.00 15,802.05

C - Sub Total Carried to Summary 615,102.90

D MASONRY WORK
Stone Work
Random Rubble Masonry Work
Random Rubble( 225 mm-500 mm) Masonry
D01 work in 1:5 Cement sand mortar in Wall m3 2.90 27,500.00 79,750.00
Foundation of Building
-
Block Work -

150mm Cement Block Work -


100mm thick block work in 1:5 cement sand
D02 m2 10.50 7,450.00 78,225.00
mortar for walls in Building.
-
D - Sub Total Carried to Summary 157,975.00
ITEM RATE AMOUNT
DESCRIPTION UNIT QTY
NO (LKR) (LKR)

E ROOFER AND ROOF PLUMBING


Zn/Al Sheet roof
Supplying and placing of Zn/Al sheet roofing
laid on timber roof frame work consists of
100×50mm rafters at 600mm spacing
,50x50mm reepers at 900mm spacing and
100x75mm wall plate on beam. Timber shall be
E01 m2 24.00 18,750.00 450,000.00
imported Hard wood, Red/ Yellow balaw or
equvalent approved by the Engineer and
treated well with two coats of approved quality
wood preservatives. Rate shall include for
necessary screws, nails and fittings.
-
Supplying and fixing of Zn/Al sheet paturn
Ridge plate jointed and bedded in 1:1:4 cement
E02 m 4.80 1,300.00 6,240.00
lime and sand mortarcoloured to match tiles
at Roof Level.
-
Supplying and fixing of 20mm thick, 225mm
high Eaves timber valance Board using brass
E03 m 7.65 3,750.00 28,687.50
screws and complete with painting at Roof
Levels
-
Supplying and fixing of Eaves timber Facia
E04 Board using brass screws and complete with m 8.14 4,250.00 34,595.00
painting at Roof Levels
-
Roof Plumbing

Supplying and fixing 0.4 mm thick Zinc


aluminium alloy coated colour bonded box type
E05 eave gutters of size 130 x 160mm of approved m 9.90 2,800.00 27,720.00
pattern and colour including end caps, running
joints with including all necessary fittings.

-
Supplying and fixing 0.4 mm thick Zinc
aluminium alloy coated colour bonded down
pipes of size 100mm x 100mm of approved
E06 m 15.20 2,800.00 42,560.00
pattern and colour with brackets and brass
screws with wooden plugs including all
necessary molded fittings
-

E - Sub Total Carried to Summary 589,802.50


ITEM RATE AMOUNT
DESCRIPTION UNIT QTY
NO (LKR) (LKR)

F FLOOR, WALL & CEILING FINISHES

Floor Finishes
Rendering

20mm thick 1:3 cement sand rendering


F01 including neat coloured cement floating to m2 9.60 2,400.00 23,040.00
ground floor
-
Wall Finishes

Internal Faces

Plastering -

15mm thick 1:3 cement sand plaster finished


F02 m2 13.50 3,000.00 40,500.00
smooth to internal walls.

External Faces
Plastering
15mm thick 1:3 cement sand plaster finished
F03 smooth with approved coloured cement m2 10.70 3,350.00 35,845.00
floating to plinths.

15mm thick 1:3 cement sand plaster finished


F10 semi rough to walls, columns and Sides of m2 17.80 2,950.00 52,510.00
Lintols.

F - Sub Total Carried to Summary 151,895.00


G PAINTER & DECORATOR
PAINTING
External Faces

Prepare & apply Skim Coat or Putty, one


alkaline resisting primer coat and two coats of
G01 weather shield emulsion of approved colour m2 17.80 1,950.00 34,710.00
and quality to semi-rough rendered surfaces
of walls.
-
Internal Faces -
Prepare and apply Skim Coat or Putty, one
primer coat and two coats of emulsion of
G02 approved colour and quality to smooth m2 13.50 2,400.00 32,400.00
plastered surfaces to internal walls, sides of
Lintel and column faces.
-
G - Sub Total Carried to Summary 67,110.00
ITEM RATE AMOUNT
DESCRIPTION UNIT QTY
NO (LKR) (LKR)

H WATER PROOFING
Damp Proofing
Damp proof membrane to horizontal surfaces
H01 of floors ( Builidng ) out of 1000 gauge m2 9.18 400.00 3,672.00
polythene.
20mm thick 1:2 cement : sand DPC and
H02 finished with two coats of hot tar blinded with m2 3.87 2,950.00 11,416.50
coarse sand for Building

H - Sub Total Carried to Summary 15,088.50

J METAL WORKS

Safety Net work

Supplying, fabricating and fixing of 50 x 50mm


PVC Coated Wire mesh fixed with 20 x 20mm
J01 m2 26.70 14,250.00 380,475.00
GI box bar frame work attach chain link fabric
to top rail with tie wire at 600 max centres.

Aluminium Works

Door
Supplying, fabricating and fixing Aluminum
door 1200mm x 2100mm over all size
J02 Nr 1 155,000.00 155,000.00
Aluminium door, Glazed sashes with 75x40mm
size of GI box bar Frame.

J - Sub Total Carried to Summary 535,475.00