Construction of Ulavanoor RWS

Detail of Balance Works to be done as at 05/03/2021

Item Date sc edule to


ask ame ro ress / Status
o Com lete
1 a in of DI/ C i es ittin s and alves
Pipe laying (additional laying) Partially done 95% 28-May-2021
Pressure testing Partially done 90% 3-May-2021
Washout chamber (19nos + 19nos) Completed 100% 28-Feb-2021
Section Valve (6nos) Partially done 60% 28-Apr-2021
Air Valve (1nos) Partially done 50% 28-Apr-2021
Cleaning and Dis-inspection Not done 0% 7-May-2021
Providing household connection Not done 0% 20-May-2021

2 Site orks and andsca in


Planting Trees Not done 0% 30/04/2021
Fence and Gate installation Partially done 50% 10-May-2021
Fixing Solar powered Led lamp (15nos) Not done 0% 20-May-2021
Yard piping Not done 0% 25-May-2021
Turfing Not done 0% 30-May-2021

3 Construction of 0m3 erro Cement o er


Footing Completed 100%
Ground Beam Completed 100%
st
Column - Ground to 1 Level Completed 100%
Ring Beam - Level 1 Completed 100%
st nd
Column – 1 Level to 2 Level Completed 100%
Ring Beam - Level 2 Completed 100%
nd rd
Column – 2 Level to 3 Level Completed 100%
Ring Beam - Level 3 Completed 100%
rd th
Column – 3 Level to 4 Level Completed 100%
Level 4 Beam and Base Slab Completed 100% 5-Mar-2021
Ferro Cement Tank Plastering (Dome & Wall) Not done 0% 20-May-2021
Painting Not done 0% 25-May-2021
Water Proofing Not done 0% 27-May-2021
Fixing GI ladder and Railing Not done 88% 30-Apr-2021
Water Tightness testing Not done 0% 28-May-2021
Valve chamber Not done 0% 22-May-2021

Construction of 20m3 erro Cement tank


Footing Completed 100%
Ground Beam Completed 100%
st
Column - Ground to 1 Level Completed 100%
Ring Beam - Level 1 Completed 100%
st nd
Column – 1 Level to 2 Level Completed 100%
Ring Beam - Level 2 Completed 100%
nd rd
Column – 2 Level to 3 Level Completed 100%
Ring Beam - Level 3 Completed 100%
rd th
Column – 3 Level to 4 Level Partially done 90% 27-Apr-2021
Level 4 Beam and Base Slab Not done 0% 27-Apr-2021
Ferro cement Tank Plastering (Dome & Wall) Not done 0% 10-May-2021
Painting Not done 0% 13-May-2021
Water Proofing Not done 0% 5-May-2021
Fixing GI ladder and Railing Not done 0% 10-May-2021
Water Tightness testing Not done 0% 15-May-2021
Valve chamber Not done 0% 20-May-2021
Construction of Ulavanoor RWS
Detail of Balance Works to be done as at 05/03/2021

Item Date sc edule to


ask ame ro ress / Status
o Com lete

5 Construction of Rou in ilter erator


Base slab Completed 100%
Wall Completed 100%
False slab casting and Placing Completed 100%
Supply and filling of Filter media in proggres 0% 28-Apr-2021
Steel works (Aluminum ladder) Not done 0% 5-May-2021
Washout Valve chamber Partially done 70% 26-Apr-2021
Testing and Inspection Not done 0% 15-May-2021

Construction of 0m3 Clear Water Sum


Base slab Completed 100%
Wall Completed 100%
Roof Slab Completed 100%
Steel work (GI Ladder) and Chequer plate Not done 0% 15-May-2021
Testing and Inspection Partially done 40% 27-Apr-2021

Construction of 20m3 ilter Water Sum


Foundation Completed 100%
Base Slab Completed 100%
Ferro Cement Plastering (Dome & Wall) Completed 100%
Painting Completed 100%
Water Proofing Not done 0% 3-May-2021
Steel works (Aluminum ladder) not done 0% 8-May-2021
Testing and Inspection Completed 100% 28-Mar-2021

Construction of 20m3 Re ected Water Sum


Foundation Completed 100%
Base Slab Completed 100%
Ferron Cement Plastering (Dome & Wall) Completed 100%
Painting Completed 100%
Water Proofing Not done 0% 2-May-2021
Steel works (Aluminum ladder) not done 0% 3-Aug-2021
Testing and Inspection Completed 100% 28-Mar-2021

Construction of Du Well
Base Ring beam Completed 100%
st
1 level Rubble work & concreting Completed 100%
nd
2 level Rubble work and concreting Completed 100%
rd
3 level Rubble work and concreting Completed 100%
th
4 level Rubble work and concreting Completed 100%
th
5 level Rubble work and concreting Completed 100%
th
6 level Rubble work and concreting Not done 0% 10-May-2021
Plastering (Internal & External) Not done 0% 30-May-2021
Construction of Ulavanoor RWS
Detail of Balance Works to be done as at 05/03/2021

Item Date sc edule to


ask ame ro ress / Status
o Com lete
10 Construction of office
Rubble foundation Completed 100%
Plinth Beam Completed 100%
Block masonry for walls Completed 100%
Floor Concrete Completed 100%
Wall plastering Completed 100%
Roof works Completed 100%
Fixing Doors, Windows and fanlight Completed 100%
Roof ceiling Not done 0% 10-May-2021
Electrical works Completed 100%
Floor rendering and Tiling Not done 0% 10-May-2021
Painting Partially done 50% 15-May-2021

11 Construction of um ouse R lant


Rubble foundation Completed 100%
Plinth Beam Completed 100%
Block masonry for walls Completed 100%
Floor Concrete Completed 100%
Wall plastering (External & Internal) Completed 100%
Roof works Completed 100%
Fixing Doors, Windows and fanlight Partially done 70% 10-May-2021
Roof ceiling Completed 100%
Electrical works Completed 100% 10-Feb-2021
Floor rendering Completed 100% 15-Feb-2021
Painting Completed 100% 28-Feb-2021

12 Wetland
Base Slab Completed 100%
Wall completed 100%
Filling metal & Soil Not done 0% 30-May-2021
Planting grass Not done 0% 17-May-2021

13 anel Room at Intake 2

Foundation Completed 100%


Block Masonry for Wall Completed 100%
Roof slab Completed 100%
Floor rendering and Painting Completed 100%
Fixing Door and Fanlight Completed 100%

m3
1 Su l and Installation of 30 Reverse smosis

m3
Supply, Installation and commissioning of 30 RO plant avilabale at 30% 5-May-2021
Reverse Osmosis plant yard
Supply, Installation and commissioning of on process 30-Apr-2021
18.75 W Solar Panel net metering system at
intake 02
Supply, Installation and commissioning of on process 30-Apr-2021
6.25 W Solar Panel net metering system at
intake 01
Construction of Ulavanoor RWS
Detail of Balance Works to be done as at 05/03/2021

Item Date sc edule to


ask ame ro ress / Status
o Com lete
15 Su l and Installation of Bore ole um s
Supply, Installation and borehole type Supply within one 30-Apr-2021
submersible pump set (2nos, 610 l/min) – Intake month
01
Supply, Installation and commissioning of on process 30-Apr-2021
6.25 W Solar Panel net metering system at
intake - 01
Supply, Installation and commissioning of 10 W on process 30-Mar-2021
Solar Panel net metering system at intake - 01

Supply, Installation and commissioning of 2.5 W on process 30-Apr-2021


Solar Panel net metering system at intake - 03

Supply, Installation and commissioning of on process 30-Apr-2021


18.75 W Solar Panel net metering system at
intake - 02
Supply, Installation and borehole type Supply within one 27-Apr-2021
submersible pump set (2nos, 610 l/min) – Intake month
02
Supply, Installation and commissioning of on process 30-Apr-2021
6.25 W Solar Panel net metering system at
intake - 02
Supply, Installation and commissioning of 2.1 W on process 26-Apr-2021
Solar Panel net metering system at intake - 03

Supply, Installation Centrifugal pumps (2, nos, Supply within one 10-May-2021
500l/min) – Intake 3 month
Supply, Installation Centrifugal pumps for 20m3 Supply within one 27-Apr-2021
Tower (2, nos, 78.06l/min) month
Supply, Installation Centrifugal pumps for 80m3 supply within one 30-Apr-2021
Tower (2, nos, 645.21l/min) month