SL No Scope of LL Start Date Completion Date Current Status

1 Fire Fighting Works


Work will be done by 27-Aug
Fire Sprinkler piping
a 28th July,2021 25th Aug,2021 completed, Mezzanine by 2nd
work
Sept.
Water Tank Tank will come on 30 August &
b 30th Aug,2021 5th Sep,2021
Installation will be ready by 7 Sept
Pump Room work Pump will come on 10 Sept &
b (Installation of 13th Aug,2021 20-Sep work will be complete by 20
Pumps & Panel) Sept
Completion - 03.09.2021
Partion wall within
2 15th July,2021 20th Aug,2021 (Clearance given on 27.08.2021
the Box
by CARS24)
Sanitary fixtures & Tile work is
3 Toilets 3rd Aug,2021 10th Sep,2021 pending which will be done by
10 Sept.
ETP procured & will be installed
4 ETP 25th Aug,2021 5th Sep,2021
by 5 Sept
5 Ramp 2 Nos 3rd Aug,2021 26th Aug,2021 Complete
Levelling & Laying of Grid slab concreting to be
Gravels at the executed at the Exit, Entry &
6 20th July,2021 20th Aug,2021
parking Area with Front on HT line trench - 1st
Blacktop & Gate Sept 2021.

Electrical Drawing ok go ahead given by


Transformer Shuvendu, Visit of Electrical
7 7th Aug,2021 31st OCT,2021
Installation & inspector to be done for
Cabling approval.5th Oct 2021

Completion of
Boundary wall at the
8 7th Aug,2021 30th Aug,2021 It will be done by 5th Aug
back of the premises
with barbed wire

Flooring on
9 26th July 3rd Aug,2021 Done
Mazzenine-2

Front boundary wall 3rd Aug,2021


10 20th Aug,2021 Done
breaking & remaking

Water tank installation pending-


11 Toilet Water tank 25-Aug 30-Aug
1500 ltr
Front Gate
12 25-Aug 30th Aug,2021 2nd Sept - it will be completed
Installation
Septic tank Cleaning
13 24-Aug 25th Aug,2021 Done
& Covering
External Partion Wall Precast boundary wall - painting
14 Finishing in friont 20thAug,2021 in progress. Finishing on 02nd
side Sept
Concreting in front
15 of Parking Area & 20th Aug,2021 25th Aug,2021 05th Sept
Gate Installation
Concreting Over the
16 Electrical Trench in 20th Aug,2021 25th Aug,2021 05th Sept
the front section
Concreting in the
17 20th Aug,2021 25th Aug,2021 05th Sept
Front Section
DG marking to be done,
18 DG area Leveling 22th Aug,2021 22th Aug,2021 Concreting will by done by -
03.Sept
Step/Stairs
19 dismantling beside 22th Aug,2021 22th Aug,2021 Done
dock
Toilet Drainage Line
20 Connection with 25th Aug,2021 28th Aug,2021 Done
Septic Tank
Toilet Deck Slab & Marking to be given by Colliers
21 18th Aug,2021 19th Aug,2021
Duct Cutout making for cutout for ducting exhaust
Wall above
22 18th Aug,2021 18th Aug,2021 done
Mezzanine
Cleaning Mezzanine 18th Aug,2021
23 18th Aug,2021 done
Floor
24 Parking Lighting Not Given Not Given RE to close the issue
Occupancy
25 Already Provided Already Provided
certificate
26 Fire NOC 27-Sep It is expected on 30 Sept
27 Mazzenine floor - A Railing to be provided
Tentative
Sr. No. Scope of LL Start Date Completion
Date

Power is
Three phase of Electric meter with 400 KW load
applied on
along with proper cabling/termination.
13 Aug
1

Mezzanine area to be developed as per the


19-Aug 19-Sep
requirement.
2

Dock, Ramps & Fire exit 28-Jul 25-Aug


3

Toilets to be developed as per the requirement. 1-Sep 19-Sep


4

  STP (15 KLD). 17-Aug 19-Sep


5

Open Area Lighting 1-Sep 19-Sep


6

Shed internal lighting (150 lux level). 21-Aug 30-Aug


7

External Lighting 30-Aug


8

  Bore well as per requirement.


9

  Fire
NOC(Fire Sprinkler, Fire Hydrant Fixing, Fire
17-Aug 25-Aug
Pump Room)
10

Pollution NOC 18-Aug


11
Providing Boundary Across the open area
5-Sep 25-Sep
Premises
12

Back Side Boundary wall 25-Aug 10-Sep


13

Levelling & Gravelling of low land area beside


15-Sep 30-Sep
water tank
14

Constructuion of culvet 1-Sep 30-Sep


15
16 Providing nets for falling stone
Ground Leveling & Stone placing for parking
22-Jul 30-Aug
17 area
18 Gate Installation at the entry of the site 23-Aug 10-Sep
19 Partition wall of warehouse 11-Aug 2-Sep
20 Fire Noc 17-Aug 25-Aug
21 OC- Occupation Certificate
22 Filling of transformer area 26-Aug 15-Sep
Remarks as on 19-08-2021 Pictures

Due to Mohram Govt holidays it is delayed by authority, LL will


provide final date soon

Contract is given to Konart. As per Konart he will deliver in


months time

Done

This work is parallel to Mezzanine.

STP is ordered on 17 Aug

Layout plan is shared with LL

work will be completed by 30 Aug

Work will be done by 30-Aug

Done

Fire Pump room is ready, Fire Hydrant fixtures is done, Testing is


pending will be done by 5th Sept

It is applied on 18 Aug & noc will come only after completion of


STP & ETP
Work will start in september

Work will start on 25 Aug & will be done by 10 Sept

Starting from 15 sept & will be finish by 30 Sept

Due to rain it is delayed. Will be done by 30-Sep

Due to rain it is delayed.after monsson it will be done


stone dust is yet to be laid. Rest work is done
Gate is ordered on 23-Aug
Partition brick work is done & shed work is pending
It is applied on 17 Aug & will be provided on 25 Aug
OC from Gram panchayat is provided on 12 Aug
It will be done once transformer work is done
S.No Scope of Work Landlord Task Dependency Start Date
1 Boundary wall with barbed wire LL None
2 Roof insulation LL None
3 Fire Sprinkler K160 LL None
4 Fire Hydrants internally LL None
5 Fire pump with pump room LL None
6 Toilets LL None
7 STP LL None
Ramps - 2 Nos LL Details shared on 27-
8 July. Work started.
Dock leveller removing LL Drawing approved on
9 27-July. Work started.
Electrical Transformer and cabling LL SLD details shared with 8/4/2021
LL waiting for there
10 approval (On 30-July).

Paved parkıng with Lights LL Paver sample approved 13/8/2021


11 on 27-July.
12 Mezzanine LL None 9/8/2021
13 Mezzanine plumbing LL TBD
MS fencing for open car parking area LL LL has shared reference 13/8/2021
image with us. We have
14 to approve.

Toilet Fixtures LL LL has agreed for fully 15/9/2021


15 fuctional toilets.
End Date Remarks
Done
Done
Done
Done
Done
Done
Done
Done

Done

28-0821 Done

10/9/2021

10/9/2021
TBD
15/9/2021

20/9/2021 it will take 3-4 days.