CIVIL DU TELECOM NETWORK DEVELOPMENT IN ABUDHABI

PROGRAM OF WORKS

2021
ACTIVITY ID ACTIVITY NAME ORIGINAL START FINISH JULY AUGUST
DURATION
CIVIL DU TELECOM NETWORK DEVELOPMENT 31 Days 01-July-2021 30-July-2021
PROJECT MILESTONE 31 Days 01- July -2021 31 July-2021
SURVEY & GENERAL REQUIREMENTS 3 Days 01- July-2021 03- July -2021
MATERIAL AND EQUIPMENT MOBILIZATION 2 Days 04- July -2021 05- July -2021
TRIAL PIT & DEMARCATION 2 Days 06- July -2021 07- July -2021
CIVIL WORK 20 Days 08- July -2021 27- July -2021
DUCTING
 Excavation Down to the required Level 8 Days 08- July -2021 15- July -2021
 Duct Works including Crossing 6 Days 11- July -2021 16- July -2021
 Backfilling 5 Days 12- July -2021 16- July -2021
 Mandrill Test 2 Days 17- July -2021 18- July -2021
MANHOLES
 Excavation Works 6 Days 11- July -2021 16- July -2021
 Installation of Manholes 5 Days 16- July -2021 20- July -2021
 Waterproofing 3 Days 20- July -2021 22- July -2021
 Backfilling 4 Days 23- July -2021 26- July -2021
 Fixing of Frame and Cover 2 Days 26- July -2021 27- July- 2021
TESTING & COMMISIONIONG 02 Days 28- July -2021 29- July -2021
DEMOBILIZATION 01 Days 29- July -2021 29- July -2021
HANDING OVER AND CLOSEOUT 01 Days 30- July -2021 30- July -2021

Actual Work CONSULTANT


Remaining Work
Critical Remaining Work EITC (du) Program of Works