SIMPLEX INFRASTRUCTURES LIMITED

“Construction of Sub-Structure and Super-Structure Civil Works including part Finishing Works for Project ‘Sunshine One’ in ‘Shriram Grand City’,
Uttarpara, Hooghly, near Kolkata.”

Tentative Work Program:

LOCATION
SN DESCRIPTION REMARKS
TOWER 1A TOWER 2A TOWER 2B TOWER 3D TOWER 3E

Date of Commencement 26-02-2021 26-02-2021 26-02-2021 26-02-2021 26-02-2021

A Conventional Work:
1 Total Scope of Pile Cap 54 46 46 52 52
Plan to Complete Date of Conventional Work upto Ground
2 15-05-2021 31-05-2021 18-05-2021 28-05-2021 22-05-2021
Floor Bottom Level

B Mivan Work:
1 Ground Floor Slab (70% Mivan & 30% Conventional) 14-07-2021 30-07-2021 17-07-2021 27-07-2021 21-07-2021

2 Mivan 1st Floor 03-08-2021 19-08-2021 06-08-2021 16-08-2021 10-08-2021


3 Mivan 2nd Floor 15-08-2021 31-08-2021 18-08-2021 28-08-2021 22-08-2021
4 Mivan 3rd Floor 27-08-2021 12-09-2021 30-08-2021 09-09-2021 03-09-2021
5 Mivan 4th Floor 08-09-2021 24-09-2021 11-09-2021 21-09-2021 15-09-2021
6 Mivan 5th Floor 20-09-2021 06-10-2021 23-09-2021 03-10-2021 27-09-2021
7 Mivan 6th Floor 02-10-2021 18-10-2021 05-10-2021 15-10-2021 09-10-2021
8 Mivan 7th Floor 14-10-2021 30-10-2021 17-10-2021 27-10-2021 21-10-2021
9 Mivan 8th Floor 26-10-2021 11-11-2021 29-10-2021 08-11-2021 02-11-2021
10 Mivan 9th Floor 07-11-2021 23-11-2021 10-11-2021 20-11-2021 14-11-2021
11 Mivan 10th Floor 19-11-2021 05-12-2021 22-11-2021 02-12-2021 26-11-2021
12 Mivan 11th Floor 01-12-2021 17-12-2021 04-12-2021 14-12-2021 08-12-2021
13 Mivan 12th Floor 13-12-2021 29-12-2021 16-12-2021 26-12-2021 20-12-2021
14 Mivan 13th Floor 25-12-2021 10-01-2022 28-12-2021 07-01-2022 01-01-2022
15 Mivan 14th Floor 06-01-2022 22-01-2022 09-01-2022 19-01-2022 13-01-2022
16 Mivan 15th Floor 18-01-2022 03-02-2022 21-01-2022 31-01-2022 25-01-2022
17 Mivan 16th Floor 30-01-2022 15-02-2022 02-02-2022 12-02-2022 06-02-2022
18 Miivan 17th Floor 11-02-2022 27-02-2022 14-02-2022 24-02-2022 18-02-2022
19 Mivan 18th Floor 01-03-2022 17-03-2022 04-03-2022 14-03-2022 08-03-2022

20 Above Terrace & Finishing work. 30-05-2022 15-06-2022 02-06-2022 12-06-2022 06-06-2022

Duration in Months 15 16 15 16 15

Note: The above Program is subject to provide all inputs like, Drawings, Free issue materials, approval of front etc in time.