Nashik Smart City

Status of Traffic Diversion Permissions for Roads


3/11/2022
Date of
documents Application Diversion permission
Sr.
Road No submitted by submitted by approved by DCP Remark
No.
BGSCTPL to NMSCDCL (Traffic)
NMSCDCL

A Major Road

1 Road No-01 03.02.2021 12.02..2021

2 Road No-02 Ongoing Road


3 Road No-03 20.01.2021 22.01.2021 18.03.2021

4 Road No-04 Ongoing Road


5 Road No-05 25.02.2021 27.02.2021

6 Road No-06 15.03.2021 22.03.2021

7 Road No-07 25.02.2021 27.02..2021 20.05.2021

8 Road No-08 30.07.2021 21.09.2021 04.01.2022

9 Road No-10 16.08.2021 21.09.2021

10 Road No-11 2/2/2022 2/23/2022

11 Road No-12 2/2/2022 2/23/2022

12 Road No-13 25.05.2021 03.06.2021

13 Road No-14 2/3/2022 2/23/2022

14 Road No-15 11.02.2021 12.02.2021

15 Road No-16 04.03.2021 13.03.2021

16 Road No-17 16.08.2021 21.09.2021

17 Road No-18 13.01.2021 21..01.2021 Ongoing Road


18 Road No-19 20.01.2021 22.01..2021 26.02.2021 Ongoing Road
19 Road No-20 06.09.2021 21.09.2021 04.01.2022

20 Road No-21 16.12.2020 28.12.2020 04.01.2022

21 Road No -22 15.03.2021 22.03.2021 20.05.2021 Ongoing Road


22 Road No -23 09.02.2021 01.04.2021 04.01.2022

23 Road No-24 M/s.Sitaram taken permission. Ongoing Road


24 Road No-25 25.05.2021 03.06.2021

25 Road No-26 13.01.2021 21.01.2021 10.03.2021

26 Road No-27 25.05.2021 03.06.2021 04.01.2022

27 Road No-28 25.05.2021 03.06.2021

28 Road No-29 30.07.2021 21.09.2021

29 Road No-30 16.08.2021 21.09.2021

30 Road No-31 11.02.2021 13.02.2021 14.04.2021 Ongoing Road


31 Road No-32 03.02.2021 13.02.2021 20.05.2021 Ongoing Road
32 Road No-33 2/2/2022 2/23/2022

33 Road No-34 2/2/2022 2/23/2022

34 Road No-35 2/2/2022 2/23/2022


Status of Traffic Diversion Permissions for Roads
3/11/2022
Date of
documents Application Diversion permission
Sr.
Road No submitted by submitted by approved by DCP Remark
No.
BGSCTPL to NMSCDCL (Traffic)
NMSCDCL

35 Road No-36 06.09.2021 21.09.2021

36 Road No-37 03.02.2021 13.02.2021 20.05.2021

37 Road No-38 2/2/2022 2/23/2022

38 Road No-39 13.01.2021 21.01.2021 19.03.2021 Ongoing Road


39 Road No-40 07.07.2020 Ongoing Road
40 Road No-41 28.05.2021 03.06.2021

41 Road No-42 25.05.2021 03.06.2021

42 Road No-43 13.01.2021 20.01.2020 18.03.2021 Ongoing Road


43 Road No-44 09.02.2021 12.02.2021

44 Road No-45 2/2/2022 2/23/2022

45 Road No-46 15.03.2021 22.03.2021

46 Road No-47 2/2/2022 2/23/2022

47 Road No-48 2/2/2022 2/23/2022

48 Road No-49 06.09.2021 21.09.2021

49 Road No-50 16.08.2021 21.09.2021

50 Road No-51 16.08.2021 21.09.2021

51 Road No-52 16.08.2021 21.09.2021 04.01.2022

52 Road No-53 09.02.2021 13.02.2021 20.02.2021 Ongoing Road


53 Road No-54 03.06.2021 10.06-2021

54 Road No-55 09.07.2020 Ongoing Road


55 Road No-56 25.05.2021 03.06.2021 04.01.2022

56 Road No-57 13.01.2021 21.01.2021 19.03.2021

57 Road No-58 2/3/2022 2/23/2022

58 Road No-59 15.03.2021 22.03.2021 20.05.2021

59 Road No-61 03.06.2021 10.06.2021

60 Road No-62 25.02.2021 27.02.2021 20.05.2021

61 Road No-63 06.09.2021 21.09.2021

62 Road No-64 06.09.2021 21.09.2021

63 Road No.65 Ongoing Road


64 Road No.66 11/4/2020 23.11.2020 01.12.2020 Ongoing Road
65 Road No.67 Ongoing Road
66 Road No-68 06.09.2021 21.09.2021

67 Road No-69 25.02.2021 27.02.2021 14.04.2021

68 Road No-70 20.01.2021 22.01.2021 15.04.2021 Ongoing Road


69 Road No-71 25.02.2021 13.03.2021 Ongoing Road
70 Road No-72 04.03.2021 13.03.2021 14.04.2021 Ongoing Road
71 Road No.73 Ongoing Road
Status of Traffic Diversion Permissions for Roads
3/11/2022
Date of
documents Application Diversion permission
Sr.
Road No submitted by submitted by approved by DCP Remark
No.
BGSCTPL to NMSCDCL (Traffic)
NMSCDCL

72 Road No-74 26.03.2021 01.04.2021 04.01.2022 Ongoing Road


73 Road No-75 07.02.2020 04.08.2020 Ongoing Road
Total

Minor Road

74 Road No-90 25.05.2021 03.06.2021

75 Road No-91 16.12.2020 28.12.2020 05.02.2021 Ongoing Road


While visit of Commissioner of Police with
76 Road No-88 16.12.2020 CEO of NMSCDCL,CP is not agree to start
of this Road
77 Road No-89 16.12.2020 28.12.2020 05.02.2021 Ongoing Road
78 Road No-41 04.06.2021 10.06.2021

79 Road No-42 04.06.2021 10.06.2021 Ongoing Road


80 Road No-43 28.07.2021 21.09.2021

81 Road No-28 04.06.2021 10.06.2021 04.01.2022

82 Road No-80 07.09.2021 21.09.2021

83 Road No-81 07.09.2021 21.09.2021

84 Road No-83 07.09.2021 21.09.2021

85 Road No-92 29.07.2021 21.09.2021 Ongoing Road


86 Road No-93 28.07.2021 21.09.2021 Ongoing Road
87 Road No-94 28.07.2021 21.09.2021 Ongoing Road
88 Road No-95 28.07.2021 21.09.2021 04.01.2022

89 Road No-96 28.07.2021 21.09.2021

90 Road No-01 01.09.2021 21.09.2021

91 Road No-03 01.09.2021 21.09.2021

92 Road No-04 01.09.2021 21.09.2021

93 Road No-08 01.09.2021 21.09.2021

94 Road No-09 01.09.2021 21.09.2021

95 Road No-12 01.09.2021 21.09.2021

96 Road No-14 01.09.2021 21.09.2021

97 Road No-16 01.09.2021 21.09.2021

98 Road No-17 01.09.2021 21.09.2021

99 Road No-18 01.09.2021 21.09.2021

100 Road No-19 01.09.2021 21.09.2021

101 Road No-20 01.09.2021 21.09.2021

Total

C Water Supply

102 Sneh bandhan Park,C.P Office 09.12.2020 17.12.2020

103 Police Vasahat,CP Office 06.11.2020 03.12.2020


Date:-03.03..2022 to 11.03.2022 3/11/2022

Scope Completed upto last week Completed Last Week Completed in this Week % Complete till now

Sr. No. Activity Unit ABSTRACT


Re- Re- Re- Re- Re-
MC constructi SWD Utility MC construct SWD Utility MC constru SWD Utility MC constru SWD Utility MC constru SWD Utility
on ion ction ction ction

1 Excavation Rmt 5460 3527 6167 22312 3441 3527 5663 18434 60 0 30 40 262 0 14 335 68% 100% 92% 84%
2 SWD Rmt 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 Raft Rmt 0 0 4800 0 0 0 4786 0 0 0 0 0 0 0 14 0 100%
4 Wall Rmt 0 0 4800 0 0 0 4785 0 0 0 0 0 0 0 15 0 100%
5 Slab Rmt 0 0 4800 0 0 0 4778 0 0 0 0 0 0 0 12 0 100%

6 RCC Pipe for SWD Rmt 0 0 1392 40 0 0 902 40 0 0 0 0 0 0 0 0 65%

7 Encasing of pipe Rmt 0 0 712 0 0 0 712 0 0 0 0 0 0 0 0 0 100%

8 Sewer line Rmt 0 0 0 3189 0 0 0 2469 0 0 0 0 0 0 0 45 79%

9 DWC 200 mm Rmt 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


HT Rmt 0 0 0 20939 0 0 0 16837 0 0 0 25 0 0 0 315 82%
LT Rmt 0 0 0 20939 0 0 0 16807 0 0 0 25 0 0 0 185 81%
10 DWC 50 mm Rmt 0 0 0 20939 0 0 0 16567 0 0 0 85 0 0 0 230 80%
11 Subgrade Rmt 5460 3527 0 22452 3350 3527 0 18370 35 0 0 65 215 0 0 240 65% 100% 83%
12 GSB Rmt 5460 3527 0 22602 3269.5 3527 0 18410 35 0 0 135 185 0 0 255 63% 100% 83%
13 DLC Rmt 5460 1725 0 19602 3229.5 1725 0 14772 40 0 0 330 140 0 0 235 62% 100% 77%
14 PQC Rmt 5460 1635 0 3186 3039 1635 0 3106 180 0 0 60 85 0 0 50 57% 100% 99%
15 WMM Rmt 90 1802 0 3070 90 1802 0 3070 0 0 0 0 0 0 0 0 100% 100%
16 Paver Block Rmt 0 90 0 17311 0 90 0 11326 0 0 0 130 0 0 0 470 100% 68%
17 DBM Rmt 1552 1802 131 2460 1549 1802 131 2460 0 0 0 0 0 0 0 0 100% 100% 100% 100%
18 BC Rmt 1552 1802 131 2460 1514 1782 96 2205 0 0 0 0 0 0 0 0 98% 99% 73% 90%

19 Pole Foundation Nos 0 0 0 306 0 0 306 0 0 0 0 0 0 0 0 100%

20 Electric Pole Nos 0 0 0 294 0 0 294 0 0 0 0 0 0 0 0 100%


21 Kerb Stone Rmt 530 0 0 4105 530 0 0 3074 0 0 0 0 0 0 0 30 76%
22 RCC Railing Rmt 0 0 0 460 0 0 0 460 0 0 0 0 0 0 0 0 100%

23 Water Supply (ABD) Rmt 0 0 45045 560 0 0 22921.9 210 28.5 51%

24 Testing Rmt 45045 19110 635 0 42%


25 Reconstruction 10883.5 250 210
Water Supply
26 Rmt 0 0 0 37228 0 0 0 10259 47.5 115.5 28%
(Roads)
27 Testing Rmt 0 37228 6698.5 0 60 18%
Date:-03.03..2022 to 11.03.2022 1 2 3 4

last this % till last this % till


Scope Completed upto last week Completed in this Week % Complete till now Scope Scope Scope Completed upto last week Completed in this Week
week Week now week Week now

Road No. 04 (Ramwadi


Sr. No. Activity Unit R-2 (Ashok Stambh to Gharpure Ghat) Road No. 15 Minor Road No. 18
Bridge to Gangawadi)

MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility Utility Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility

1 Excavation Rmt 227 114 454 227 114 454 100% 100% 100% 900 220 24% 150 100 50 100% 240 100 460 200 100 320 20 80

2 SWD Rmt

3 Raft Rmt 114 114 100% 100 100

4 Wall Rmt 114 114 100% 100 100

5 Slab Rmt 114 114 100% 100 100

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt 454 454 100%

9 DWC 200 mm Rmt

HT Rmt 227 227 100% 900 220 24% 150 100 50 100% 460 320 80

LT Rmt 227 227 100% 900 220 24% 150 100 67% 460 320 80

10 DWC 50 mm Rmt 227 227 100% 900 220 24% 150 100 67% 460 320 80

11 Subgrade Rmt 227 454 227 454 100% 900 220 24% 150 100 67% 240 460 200 320 20 80

12 GSB Rmt 227 454 227 454 100% 100% 900 220 24% 150 100 67% 240 460 180 320 20 80

13 DLC Rmt 227 454 227 454 100% 100% 900 220 24% 150 100 67% 240 460 150 320 50 80

14 PQC Rmt 227 227 100% 240 100

15 WMM Rmt

16 Paver Block Rmt 454 454 100% 900 220 24% 150 40 40 53% 480 210

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos 11 11 100% 9 9 100% 4 4

20 Electric Pole Nos 11 11 100% 9 9 100% 4 4

21 Kerb Stone Rmt 150 120

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 5 6 7

Completed upto Completed in this % Complete till


% Complete till now Scope Completed upto last week Completed in this Week % Complete till now Scope Scope last week
last week Week now

Sr. No.Minor Road No. 18


Activity Unit Minor Road No. 19 Major Road No.20 Road No.22 (Katya marut

Reconstr Reconstr Reconstr


MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW Utility MCW Utility MCW Utility Utility SWD Utility SWD Utility
uction uction uction

1 Excavation Rmt 92% 100% 87% 140 145 280 140 145 280 100% 100% 100% 520 700 145 290 25 10 33% 43% 320 320 1060 320 320 960

2 SWD Rmt

3 Raft Rmt 100% 145 145 100% 320 320

4 Wall Rmt 100% 145 145 100% 320 320

5 Slab Rmt 100% 145 145 100% 320 320

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt 120 120 100%

9 DWC 200 mm Rmt

HT Rmt 87% 280 280 100% 700 145 15 23% 1060 960

LT Rmt 87% 280 280 100% 700 145 15 23% 1060 960

10 DWC 50 mm Rmt 87% 280 280 100% 700 145 15 23% 1060 960

11 Subgrade Rmt 92% 87% 140 280 140 280 100% 100% 520 700 145 230 15 70 31% 43% 320 1060 320 960

12 GSB Rmt 83% 87% 140 280 140 280 100% 100% 520 700 145 230 15 70 31% 43% 320 1060 320 960

13 DLC Rmt 83% 87% 140 280 140 280 100% 100% 520 700 145 230 15 70 31% 43% 320 1060 320 960

14 PQC Rmt 140 140 100% 520 115 25 27% 320 320

15 WMM Rmt

16 Paver Block Rmt 44% 280 230 30 93% 700 90 13% 1060 960

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos 100% 21 21

20 Electric Pole Nos 100% 21 21

21 Kerb Stone Rmt 80%

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 8 9 10

Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till Completed upto Completed in this
this Week % till now Scope Scope Scope % Complete ti
last week Week now last week Week now last week Week

Sr. No. Road No.22 (Katya


Activity maruti chowk to Garden)
Unit Major Road No. 24 (Ramkund to Hotel Tuljakrupa) Major Road No. 25 ( Road No27

Reconstr Reconstr
SWD Utility SWD Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW
uction uction

1 Excavation Rmt 100% 100% 91% 240 340 200 340 83% 100% 100 160 100 160 100% 100% 80 80 80 80 100%

2 SWD Rmt

3 Raft Rmt 100%

4 Wall Rmt 100%

5 Slab Rmt 100%

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt

9 DWC 200 mm Rmt

HT Rmt 91% 340 340 100% 160 160 100% 80 80

LT Rmt 91% 340 340 100% 160 160 100% 80 80

10 DWC 50 mm Rmt 91% 340 340 100% 160 160 100% 80 80

11 Subgrade Rmt 100% 91% 240 480 200 400 83% 83% 100 160 100 160 100% 100% 80 80 80 80 100%

12 GSB Rmt 100% 91% 240 480 200 400 83% 83% 100 160 100 160 100% 100% 80 80 80 80 100%

13 DLC Rmt 100% 91% 240 480 200 360 30 83% 81% 100 160 100 160 100% 100% 80 80 80 100%

14 PQC Rmt 100% 240 270 200 220 40 83% 96% 100 100 100% 80 80 100%

15 WMM Rmt

16 Paver Block Rmt 91% 210 130 80 100% 340 205 135 100% 160 35

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos 100% 6 6 100%

20 Electric Pole Nos 100% 5 5 100%

21 Kerb Stone Rmt 30 30

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 11 12 13

Completed upto Completed in this % Complete till last this % till


% Complete till now Scope Scope Completed upto last week Completed in this Week % Complete till now Scope Scope this Wee
last week Week now week Week now

Road No.32 (Ashok


Sr. No. RoadActivity
No27 Unit Major Road No. 28 ) Road No.31(Veterinary hospital to Gharpure Ghat) Road No.39 (Meh
stambh to Nandadeep)

Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility Utility SWD Utility SWD

1 Excavation Rmt 100% 210 420 85 170 15 48% 40% 240 245 480 240 245 480 100% 100% 100% 270 270 100% 1020

2 SWD Rmt

3 Raft Rmt 160 160 100%

4 Wall Rmt 160 160 100%

5 Slab Rmt 160 160 100%

6 RCC Pipe Rmt 85 85 100% 40

7 Encasing of pipe Rmt 85 85 100%

8 Sewer line Rmt 210 85 40% 320 320 100%

9 DWC 200 mm Rmt

HT Rmt 100% 420 170 40% 480 480 100% 270 270 100% 1020

LT Rmt 100% 420 170 40% 480 480 100% 270 270 100% 1020

10 DWC 50 mm Rmt 100% 420 170 40% 480 480 100% 270 270 100% 1020

11 Subgrade Rmt 100% 210 420 85 170 40% 40% 240 480 240 480 100% 100% 270 270 100% 1020

12 GSB Rmt 100% 210 420 85 170 40% 40% 240 480 240 480 100% 100% 270 270 100% 1020

13 DLC Rmt 0% 210 420 85 170 40% 40% 240 480 240 480 100% 100% 270 270 100% 950

14 PQC Rmt 210 60 25 40% 240 240 100% 50

15 WMM Rmt 90 90 100% 140

16 Paver Block Rmt 22% 420 0% 480 480 100% 155 155 100% 950

17 DBM Rmt 90 90 100% 140

18 BC Rmt 90 90 140

19 Pole Foundation Nos

20 Electric Pole Nos

21 Kerb Stone Rmt 410

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 14 15 755 16 17

last this % till last this % till


this Week this Week % till now Scope Completed upto last week Completed in this Week % Complete till now Scope Scope Scope
week Week now week Week now

Road No. 43 (Trimbak Road No. 53 (Pimpal


Sr. No. Activity Road No.39
Unit (Meher Signal to Sudarshan) Road No. 40 (Sudarshan to Gadge Maharaj Bridge)
naka to Ganjmal Signal) Chowk to Main Road)

Utility SWD Utility SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility Utility Utility SWD Utility MC

1 Excavation Rmt 1020 100% 410 270 800 410 270 800 100% 100% 100% 1120 1120 100% 411 411 100% 340 680 340

2 SWD Rmt

3 Raft Rmt

4 Wall Rmt

5 Slab Rmt

6 RCC Pipe Rmt 40 100% 270 270 100% 340

7 Encasing of pipe Rmt 270 270 100%

8 Sewer line Rmt 820 820 100%

9 DWC 200 mm Rmt

HT Rmt 1020 100% 640 640 100% 1120 1120 100% 400 400 100% 680

LT Rmt 1020 100% 640 640 100% 1120 1120 100% 400 400 100% 680

10 DWC 50 mm Rmt 1020 100% 640 640 100% 1120 1120 100% 400 400 100% 680

11 Subgrade Rmt 1020 100% 410 800 410 800 100% 100% 1120 1120 100% 411 411 100% 680 340

12 GSB Rmt 1020 100% 410 800 410 800 100% 100% 1120 1120 100% 411 411 100% 680 340

13 DLC Rmt 950 100% 410 800 410 800 100% 100% 411 411 100% 680 340

14 PQC Rmt 50 100% 410 410 100% 411 411 100% 340

15 WMM Rmt 140 100% 1120 1120 100%

16 Paver Block Rmt 950 100% 720 720 100% 680

17 DBM Rmt 140 100% 510 510 100%

18 BC Rmt 140 100% 510 255 50%

19 Pole Foundation Nos 7 7 100% 21 21 100% 10 10 100%

20 Electric Pole Nos 7 7 100% 11 11 100% 9 9 100%

21 Kerb Stone Rmt 410 100%

22 RCC Railing Rmt

560
Date:-03.03..2022 to 11.03.2022 18 19 20

Completed upto last week Completed in this Week % Complete till now Scope Completed upto last week Completed in this Week % Complete till now Scope Completed upto last week

Sr. No. Activity Unit R-52 Road No. 55 (Annbhau Sathe Chowk to Shivsena Bhavan) R-56

Re- Re- Re- Re-


SWD Utility MC SWD Utility MC SWD Utility MC MC constru SWD Utility MC constru SWD Utility MC construc SWD Utility MC constructi SWD Utility SWD Utility MC SWD Utility MC
ction ction tion on

1 Excavation Rmt 30 30 20 20 0% 7% 15% 602 617 785 602 617 785 100% 100% 100% 240 345 345 90 90 90

2 SWD Rmt

3 Raft Rmt 617 617 100%

4 Wall Rmt 617 617 100%

5 Slab Rmt 617 617 100%

6 RCC Pipe Rmt 0% 240 90

7 Encasing of pipe Rmt

8 Sewer line Rmt

9 DWC 200 mm Rmt

HT Rmt 50 7% 785 785 100% 345 90

LT Rmt 0% 785 785 100% 345 90

10 DWC 50 mm Rmt 0% 785 785 100% 345 90

11 Subgrade Rmt 10 40 0% 15% 602 785 602 785 100% 100% 345 345 90 90

12 GSB Rmt 0% 0% 602 785 602 785 100% 100% 345 345 90 90

13 DLC Rmt 0% 785 785 100% 345 345 85

14 PQC Rmt 20 20 100% 345 45

15 WMM Rmt 602 602 100%

16 Paver Block Rmt 0% 785 780 5 100% 345

17 DBM Rmt 400 602 400 602 100% 100%

18 BC Rmt 400 602 380 582 95% 97%

19 Pole Foundation Nos 8 8 100%

20 Electric Pole Nos 8 8 100%

21 Kerb Stone Rmt 457 457 100%

22 RCC Railing Rmt

410
Date:-03.03..2022 to 11.03.2022 21 22

last this % till


Completed in this Week % Complete till now Scope Completed upto last week Completed in this Week % Complete till now Scope Scope
week Week now

Road No. 66 (Gadge


Sr. No. Activity Unit R-56 Road No. 65 (Amardham to Gadge Maharaj Bridge) Maharaj Bridge to Zaveri Road N
Dharmshala)
Re- Re- Re- Re- Re-
SWD Utility MC SWD Utility MC construct SWD Utility MC construct SWD Utility MC construct SWD Utility MC construct SWD Utility MC Utility construct SWD
ion ion ion ion ion

1 Excavation Rmt 10 10 38% 29% 29% 1060 1060 1060 1060 1060 1060 100% 100% 100% 1100 1100 100% 1545 1570

2 SWD Rmt

3 Raft Rmt 1060 1060 100% 1380

4 Wall Rmt 1060 1060 100% 1380

5 Slab Rmt 1060 1060 100% 1380

6 RCC Pipe Rmt 38% 10 10 100% 190

7 Encasing of pipe Rmt 115

8 Sewer line Rmt

9 DWC 200 mm Rmt

HT Rmt 26% 1060 1060 100% 1100 1100 100%

LT Rmt 26% 1060 1060 100% 1100 1100 100%

10 DWC 50 mm Rmt 26% 1060 1060 100% 1100 1100 100%

11 Subgrade Rmt 26% 26% 1060 1060 1060 1060 100% 100% 1100 1100 100% 1545

12 GSB Rmt 26% 26% 1060 1060 1060 1060 100% 100% 1100 1100 100% 1545

13 DLC Rmt 5 0% 26% 1060 1060 100% 1100 1100 100% 1405

14 PQC Rmt 35 23% 920 920 100% 1315

15 WMM Rmt 1060 1060 100% 140

16 Paver Block Rmt 0% 1060 1060 100% 180 180 100% 90

17 DBM Rmt 1060 530 1060 530 100% 100% 140

18 BC Rmt 1060 530 1060 530 100% 100% 140

19 Pole Foundation Nos 24 24 100% 23 23 100%

20 Electric Pole Nos 24 24 100% 23 23 100%

21 Kerb Stone Rmt 630 530 630 530 100% 100%

22 RCC Railing Rmt 460 460 100%

530
Date:-03.03..2022 to 11.03.2022 23 24 25 26

last this % till last this % till


Scope Completed upto last week Completed in this Week % Complete till now Scope Scope Scope Completed upto last week Completed in this Week % Complete till no
week Week now week Week now

Road No. 71
Road No. 70 (Nimani to
Sr. No. Activity Unit Road No. 67 (Amardham to Katya Maruti chowk) (Makhmalabad Naka to Road No. 72 (Ramwadi entrance to Ramwadi Bridge)
Makhmalabad Naka)
Ramwadi entrance)
Re- Re- Re-
Utility construct SWD Utility construct SWD Utility construct SWD Utility Utility Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD
ion ion ion

1 Excavation Rmt 1545 1545 1570 1545 100% 100% 100% 1396 1110 80% 660 660 100% 532 414 1060 410 400 780 14 77% 100%

2 SWD Rmt

3 Raft Rmt 1380 100% 414 400 14 100%

4 Wall Rmt 1380 100% 414 399 15 100%

5 Slab Rmt 1380 100% 414 392 12 98%

6 RCC Pipe Rmt 190 100% 15 15 100%

7 Encasing of pipe Rmt 115 100%

8 Sewer line Rmt

9 DWC 200 mm Rmt

HT Rmt 750 750 100% 1396 1110 80% 660 660 100% 1060 780

LT Rmt 750 750 100% 1396 1110 80% 660 660 100% 1060 780

10 DWC 50 mm Rmt 750 750 100% 1396 1110 80% 660 660 100% 1060 710

11 Subgrade Rmt 1545 1545 1545 100% 100% 1396 1110 80% 660 660 100% 532 1060 403 780 76%

12 GSB Rmt 1545 1545 1545 100% 100% 1396 1110 80% 660 660 100% 532 1060 402.5 710 76%

13 DLC Rmt 1475 1405 1475 100% 100% 1396 1110 80% 660 660 100% 532 1060 397.5 312 75%

14 PQC Rmt 410 1315 410 100% 100% 500 470 10 96% 260 260 100% 532 397 75%

15 WMM Rmt 70 140 70 100% 100%

16 Paver Block Rmt 1065 90 1050 100% 99% 1396 840 75 66% 660 660 100% 1060 292 70

17 DBM Rmt 70 140 70 100% 100%

18 BC Rmt 70 140 70 100% 100%

19 Pole Foundation Nos 59 59 100% 2 2 13 13

20 Electric Pole Nos 59 59 100% 2 2 13 13

21 Kerb Stone Rmt 500 145 29% 310 310 100% 848 232 30

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 27 28 29 30

last this % till last this % till Completed upto Completed in this % Complete
% Complete till now Scope Scope Scope Completed upto last week Completed in this Week % Complete till now Scope
week Week now week Week now last week Week now

Road No. 73 (Ramwadi Road No. 74 (Ashok


adi entrance
Sr. No. to Ramwadi
Activity Bridge) Unit entrance to Ramwadi Stambh to Marathon Road No. 75 (Old Gangapur Naka to Kekan Hospital) Minor Road No. 01
bridge) Chowk)

Utility Utility Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW Utility MCW Utility MCW Utility MCW

1 Excavation Rmt 74% 340 310 91% 1740 1740 100% 205 652 410 205 652 410 100% 100% 100% 100 100 45 45 5 5 50%

2 SWD Rmt

3 Raft Rmt 410 410 100%

4 Wall Rmt 410 410 100%

5 Slab Rmt 410 410 100%

6 RCC Pipe Rmt 242 242 100%

7 Encasing of pipe Rmt 242 242 100%

8 Sewer line Rmt 320 320 100% 100 45 5

9 DWC 200 mm Rmt

HT Rmt 74% 340 310 91% 1740 1740 100% 410 410 100% 100 45 5

LT Rmt 74% 340 310 91% 1740 1740 100% 410 410 100% 100 45 5

10 DWC 50 mm Rmt 67% 340 310 91% 1740 1740 100% 410 410 100% 100 50

11 Subgrade Rmt 74% 340 310 91% 1740 1740 100% 205 410 205 410 100% 100% 100 100 45 45 5 5 50%

12 GSB Rmt 67% 340 310 91% 1740 1740 100% 205 410 205 410 100% 100% 100 100 30 30 20 20 50%

13 DLC Rmt 29% 340 310 91% 205 410 205 410 100% 100% 100 100 30 30 30%

14 PQC Rmt 70 70 100% 205 205 100% 100 0%

15 WMM Rmt 1740 1740 100%

16 Paver Block Rmt 34% 340 310 91% 410 410 100% 100

17 DBM Rmt 1740 1740 100% 22 131 19 131

18 BC Rmt 1740 1740 100% 22 131 4 96

19 Pole Foundation Nos 100% 22 22 100%

20 Electric Pole Nos 100% 22 22 100%

21 Kerb Stone Rmt 31% 360 330 92% 410 410 100%

22 RCC Railing Rmt

Rework is in progress
Date:-03.03..2022 to 11.03.2022 31 32 33

% Complete till Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till Completed u
Scope Scope Scope Scope
now last week Week now last week Week now last week Week now last week

Sr. No.Minor Road No. 01


Activity Unit Minor Road No. 03 Minor Road No. 04 Minor Road No. 17 Minor

Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW

1 Excavation Rmt 50% 300 300 55 55 18% 18% 130 130 55 30 10 42% 31% 165 165 64 64 7 43% 39% 60 60 60

2 SWD Rmt

3 Raft Rmt

4 Wall Rmt

5 Slab Rmt

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt 50% 300 50 17% 130 10 50 46% 165 45 15 36% 60

9 DWC 200 mm Rmt

HT Rmt 50% 300 55 18% 130 30 10 31% 165 45 27% 60

LT Rmt 50% 300 55 18% 130 30 23% 165 45 27% 60

10 DWC 50 mm Rmt 50% 300 30 10% 130 25 19% 165 45 27% 60

11 Subgrade Rmt 50% 300 300 55 55 18% 18% 130 130 20 10 30 23% 23% 165 165 45 90 27% 55% 60 60 60

12 GSB Rmt 50% 300 300 30 30 10% 10% 130 130 30 25 23% 19% 165 165 45 90 27% 55% 60 60 60

13 DLC Rmt 30% 300 300 30 10% 0% 130 130 30 23% 0% 165 165 45 90 27% 55% 60 60 60

14 PQC Rmt 300 20 7% 130 0% 165 45 27% 60 60

15 WMM Rmt

16 Paver Block Rmt 0% 300 0% 130 0% 165 0% 60

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos

20 Electric Pole Nos

21 Kerb Stone Rmt

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 34 35 36 37

Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till
Scope Scope Scope
last week Week now last week Week now last week Week now last week Week now

Sr. No. Activity UnitMinor Road No. 41 Minor Road No. 42 Minor Road No. 60 Minor Road No. 61

Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility

1 Excavation Rmt 60 100% 100% 100 100 100 100 100% 100% 50 50 40 50 80% 100% 50 50 50 50 100% 100%

2 SWD Rmt

3 Raft Rmt

4 Wall Rmt

5 Slab Rmt

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt 60 100% 100 100 100% 50 40 80%

9 DWC 200 mm Rmt

HT Rmt 60 100% 100 100 100% 50 40 80% 50 15 30%

LT Rmt 60 100% 100 100 100% 50 40 80% 50 15 30%

10 DWC 50 mm Rmt 60 100% 100 0% 50 40 80% 50 15 30%

11 Subgrade Rmt 60 100% 100% 100 100 100 100 100% 100% 50 50 40 40 80% 80% 50 50 25 15 50% 30%

12 GSB Rmt 60 100% 100% 100 100 100 100 100% 100% 50 50 40 40 80% 80% 50 50 15 0% 30%

13 DLC Rmt 60 100% 100% 100 100 100 100 100% 100% 50 50 40 40 80% 80% 50 50 15 0% 30%

14 PQC Rmt 100% 100 100 100% 50 0% 50 0%

15 WMM Rmt

16 Paver Block Rmt 60 100% 100 100 100% 50 0% 50 0%

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos

20 Electric Pole Nos

21 Kerb Stone Rmt

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 38 39 40 41

Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till last this % till last this % till Completed u
Scope Scope Scope Scope Scope
last week Week now last week Week now week Week now week Week now last week

Road No. 89 (Shani


Road No. 91 (Panchwati
Sr. No. Activity Unit Minor Road No. 79 Minor Road No. 80 Chowk to Bansidhar Minor
Rd to Pathrwat Lane)
Tower)

MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility Utility Utility MCW Utility MCW

1 Excavation Rmt 70 70 30 30 43% 43% 106 106 70 60 66% 57% 185 185 100% 90 90 100% 180 360 180

2 SWD Rmt

3 Raft Rmt

4 Wall Rmt

5 Slab Rmt

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt

9 DWC 200 mm Rmt

HT Rmt 70 30 43% 106 30 28% 185 185 100% 90 90 100% 180

LT Rmt 70 30 43% 106 0% 185 185 100% 90 90 100% 180

10 DWC 50 mm Rmt 70 30 43% 106 0% 185 185 100% 90 90 100% 180

11 Subgrade Rmt 70 70 30 30 43% 43% 106 106 30 28% 0% 185 185 100% 90 90 100% 180 360 180

12 GSB Rmt 70 70 30 30 43% 43% 106 106 30 28% 0% 185 185 100% 90 90 100% 180 360 180

13 DLC Rmt 70 70 0% 0% 106 106 0% 0% 185 185 100% 90 90 100% 180 360 180

14 PQC Rmt 70 0% 106 0% 185 185 100% 90 90 100% 180 180

15 WMM Rmt

16 Paver Block Rmt 70 0% 106 0% 180

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos 9 9 100% 5 5 100% 5

20 Electric Pole Nos 9 9 100% 5 5 100% 5

21 Kerb Stone Rmt

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 42 43 44

Completed upto Completed in this % Complete till Completed upto Completed in this % Complete till Completed upto
Scope Completed upto last week Completed in this Week % Complete till now Scope Scope
last week Week now last week Week now last week

Sr. No. Activity UnitMinor Road No. 92 Minor Road No. 93 Minor Road No. 94 Minor Road N

Utility MCW Utility MCW Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW SWD Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility MCW Utility

1 Excavation Rmt 360 100% 100% 80 80 80 80 80 80 100% 100% 100% 150 150 150 150 100% 100% 90 90 90 90

2 SWD Rmt

3 Raft Rmt 80 80 100%

4 Wall Rmt 80 80 100%

5 Slab Rmt 80 80 100%

6 RCC Pipe Rmt

7 Encasing of pipe Rmt

8 Sewer line Rmt 40 40

9 DWC 200 mm Rmt

HT Rmt 180 100% 80 80 100% 150 150 100% 90 90

LT Rmt 180 100% 80 80 100% 150 150 100% 90 90

10 DWC 50 mm Rmt 180 100% 80 80 100% 150 150 100% 90 90

11 Subgrade Rmt 360 100% 100% 80 80 80 80 100% 100% 150 150 150 150 100% 100% 90 90 90 90

12 GSB Rmt 360 100% 100% 80 80 80 80 100% 100% 150 300 150 300 100% 100% 90 90 90 90

13 DLC Rmt 360 100% 100% 80 80 80 80 100% 100% 150 300 150 300 100% 100% 90 90 90 90

14 PQC Rmt 100% 80 80 100% 150 145 97% 90 90

15 WMM Rmt

16 Paver Block Rmt 180 100% 80 80 100% 300 300 100% 180 180

17 DBM Rmt

18 BC Rmt

19 Pole Foundation Nos 5 100% 5 5 100%

20 Electric Pole Nos 5 5 5

21 Kerb Stone Rmt

22 RCC Railing Rmt


Date:-03.03..2022 to 11.03.2022 45

Completed in this % Complete till Completed in this


DMA Scope (mtr) Completed upto last week Completed in this week % till now DMA Scope (mtr) Completed upto last week % till now
Week now week

Sr. No. Activity Minor Road No. 95


Unit ABD Area

MCW Utility MCW Utility Water Supply (Other than Road) Water Supply ( Roads)

Reconstr Reconstruc Reconstruc


1 Excavation Rmt 100% 100% Laying Testing Laying Testing Laying Testing Laying Testing Laying Testing Laying Testing
uction tion tion

2 SWD Rmt DMA 1 5345 4050.5 3354 2737 60 76% 63% 52% DMA 1 0

3 Raft Rmt DMA 2 6648 6440.9 5800 3543 75 97% 87% 54% DMA 2 3400 1600 960 47% 28%

4 Wall Rmt DMA 3 2666 0 0 DMA 3 6271 1440 1440 23% 23%

5 Slab Rmt DMA 4 6933 3063.5 2379 1228 44% 34% 18% DMA 4 771 33 4% 0%

6 RCC Pipe Rmt DMA 5 2794 0 0 DMA 5 6198 649 414 10% 7%

7 Encasing of pipe Rmt DMA 6 3753 0 0 DMA 6 1800 0% 0%

8 Sewer line Rmt 100% DMA 8 953 0 0 DMA 8 5285 402.5 155 8% 3%

9 DWC 200 mm Rmt DMA 9 6014 2290 1769 981.5 38% 29% 16% DMA 9 2863 2595 1867.5 22.5 91% 65%

HT Rmt 100% DMA 10 5117 3849.5 3208 1466 28.5 75 76% 63% 30% DMA 10 7778 2270.5 660 60 60 30% 9%

LT Rmt 100% DMA 11 4822 3227.5 2600 928 67% 54% 19% DMA 11 2862 1302 1202 45% 42%

10 DWC 50 mm Rmt 100% TOTAL 45045 22921.9 19110 10883.5 28.5 0 210 51% 42% 25% TOTAL 37228 10259 6698.5 115.5 60 28% 18%

11 Subgrade Rmt 100% 100%

12 GSB Rmt 100% 100%

13 DLC Rmt 100% 100%

14 PQC Rmt 100%

15 WMM Rmt

16 Paver Block Rmt 100%

17 DBM Rmt
Electrical Pole & Foundation other than
18 BC Rmt
ABD
19 Pole Foundation Nos 42 42

20 Electric Pole Nos 42 42

21 Kerb Stone Rmt

22 RCC Railing Rmt


Date;- 3/11/2022
RECONSTRUCTION
TOTAL
CONCR DBM & REMAR
SR.NO DMA SOIL QUANTIT
ETE BC K
Y
1 DMA 1 1603.5 1193.5 2797
2 DMA 2 1868 1750 3618
3 DMA 3 0
4 DMA 4 580 558 90 1228
5 DMA 5 0
6 DMA 6 0
7 DMA 8 0
8 DMA 9 71.5 910 981.5
9 DMA 10 926 615 1541
10 DMA 11 685 243 928
11 TOTAL 2262.5 4029.5 4801.5 11093.5
Nashik Smart City

Sr. No. Particulars Upto Jan 2021 Upto 28/2/2022 Total Remarks

1 Major Road No.02 123.67 123.67

2 Major Road No.04 9.72 9.72

Major Road No.15 5.70 5.70

3 Major Road No.18 57.82 12.20 70.02


4 Minor Road No 19 64.68 9.95 74.63

5 Minor Road No 20 23.24 16.44 39.68

6 Major Road No.22 160.81 160.81

7 Major Road No.24 87.91 17.74 105.65

8 Major Road No.25 27.41 8.80 36.21

9 Major Road No.27 2.07 17.11 19.18

10 Major Road No.28 19.82 18.91 38.73

11 Major Road No.31 208.80 6.43 215.23

12 Major Road No.32 24.20 24.20

13 Major Road No.39 119.07 3.84 122.91

14 Major Road No.40 337.36 15.84 353.20

15 Major Road No.43 96.71 96.71

Major Road No.52 2.64

16 Major Road No.53 27.83 27.83

17 Major Road No.55 212.12 2.10 214.22

18 Major Road No.56 2.01 11.24 13.25

19 Major Road No.65 353.21 353.21

20 Major Road No.66 71.53 71.53

21 Major Road No.67 367.72 367.72

22 Major Road No.70 93.54 21.85 115.38

23 Major Road No.71 82.60 2.57 85.17

24 Major Road No.72 343.82 40.64 384.47

25 Major Road No.73 102.86 5.67 108.54

26 Major Road No.74 204.00 204.00

27 Major Road No.75 225.10 225.10

Minor Road No.01 5.68

28 Minor Road No.03 3.24 7.22 10.46

Minor Road No.04 2.26

29 Minor Road No.17 5.02 7.30 12.32

30 Minor Road No.89 13.30 13.30

31 Minor Road No.91 5.25 5.25

32 Minor Road No 41 7.91 7.91


33 Minor Road No 42 25.53 25.53

34 Minor Road No 93 32.18 32.18

35 Minor Road No 92 50.67 50.67

36 Minor Road No 94 52.46 4.50 56.96

37 Minor Road No 95 6.62 8.09 14.71

38 Water Supply 976.29 63.31 1,039.60

39 Electrical 17.04 7.00 24.04

Total 4,645.15 325.05 4,959.62


Decisions/Drawing of Road
3/11/2022
Agenda Points for meeting

1)    Major Road No.04:


We were progressing on the part work of said in the months of Feb 2021. However, the local corporator approached to the site and stopped the work on 27.02.2021 fo

2)    Major Road No. 55:


The work is completed substantially by us and handed over for its intended use in the month of Dec. 2021. However, the main carriageway and footpath on RHS side f

3)    Major Road No. 43:


The work of said road is substantially completed by us and handed over for its intended use on 15.12.2022. However, on LHS side from Ch 0+000 to 0+520, the work

4)    FRP Cabin:


We are following up for details of FRP cabins to be installed at site since Feb 2021. The details are yet to be received to us.

5)    Bus stop:


The drawing for Bus stop is yet awaited.

6)    Major Road No. 24:


We are trying our best to complete the said road by 20.03.2022, however following points needs to sorted out on priority.

i)     The work at Ch 0+210 to 0+250 is pending from M/s SIPL, hence, we could not progress at said location.

7)    Electrical Work:


You are well aware that we have procured 400 nos. of electrical poles of 7m height in the month of April 2021. Out of 400 nos. poles, 282 nos. are erected at site, whe

8)    Major Road No. 71:


We are progressing on the work of Road No. 71 by deploying required resources at site. However, the work at Ch 0+225 to 0+250 is held up due to the movement of v

9)    Major Road R-72:


We are progressing on the work of Road No. 72 in the right earnest to complete the same by 15.03.2022. However, the work at Ch 0+000 to Ch 0+130 RHS is stopped

10) Major Road R-52:


Permission for traffic diversion is received to us on 04.01.2022. However, the work is held up only for laying of transmission line by M/s Sahyadri Constructions. Furthe
i)     Decision for laying of RCC pipe instead of RCC SWD
ii)    Details of FRL as per site is awaited.

11) Major Road R-74:


The work of utility is completed by us; however, the overlaying is withheld for laying of transmission line at Ch 0+040 to Ch 0+140 by M/s Sahyadri Construction.

12) Major Road R-08


Permission for traffic diversion is received to us on 04.01.2022. Accordingly, we have approached site to commence the work, however local corporator stopped the wo

13) Minor Road R-60


We are progressing on the work of Road No. 60 since 01.03.2022 by preparing drawing However, Layout of PQC Panel is yet awaited. On 03.03.2022 the locals have

14) Minor Road R-61


We are progressing on the work of Road No. 61 since 01.03.2022 by preparing drawing However, layout of PQC Panel is yet awaited.

15) DMA Work;


Work of DMA-4 is stopped by local corporator since 01.12. 2021.also we could not start at DMA-3, DMA-5, DMA-6 and DMA-8 due to strongly oppose by local corpora

16) Minor Roads:


We are consistently following up with the PMC for the co-ordinates of minor roads required for execution of the work. The said data is yet to be furnished to us in spite

D Additional Scope of work


1 Road No.40 1) Incasing of 600mm dia pipe
2) Shifting of 300mm dia water supply line.
3) Catch pit
4) RCC Pipe 900mm dia for SWD
5) Raft and retaining wall from CH 160 to 260.
2 Road No.65 1) RCC Fins at RHS
3 Road No.75 1) SWD road to river 250 Rmt
2) Architectual work
4 Road No.72 1) New D.I.Line work CH 0-300
5 Road No.31 1) New D.I.line work.
2) DWC pipe arranged for BSNL Cables