SERIBUMI DEVELOPMENT SDN. BHD.

DATE : 8.2.2020
PREPARED BY : CONTRACTOR (ROZNAN/NABIL)
PROJECT : Cadangan meroboh dan membina semula
sebuah rumah berkembar satu tingkat sediada di lot 166 (PT.89)
No. 14, Jalan 3/67, Seksyen 3, 46100 Petaling Jaya, Selangor Darul Ehsan.

WORK SCHEDULE
NO TASK NAME DURATION START FINISH
PRELIMINARIES
1 ORDER BAHAN BINAAN 2 DAYS 16.2.2020 18.2.2020
2 SUSUN ATUR TAPAK 2 DAYS 16.2.2020 17.2.2020
3 MOHON BEKALAN AIR & ELEKTRIK SEMENTARA 2 DAYS 16.2.2020 17.2.2020
4 SETTING OUT 2 DAYS 17.2.2020 19.2.2020

FABRICATING WORKS
5 Formwork 14 DAYS 19.2.2020 4.3.2020
6 Re bar 14 DAYS 19.2.2020 4.3.2020

SUB STRUCTURE
1.1 EXCAVATION / INSTALLATION / CONCRETING
7 Menggali Tapak Asas (JCB) 5 DAYS 19.2.2020 24.2.2020
8 Grid Line Arrangement 3 DAYS 24.2.2020 27.2.2020
9 Memasang Formwork 3 DAYS 24.2.2020 27.2.2020
10 Lean Concrete 2" 3 DAYS 27.2.2020 29.2.2020
11 Memasang besi / re bar 3 DAYS 29.2.2020 2.3.2020
12 Kerja-kerja konkrit tapak asas 5 DAYS 3.3.2020 7.3.2020

1.2 DISMANTLING WORKS/RE-FILL EARTH


13 Membuka papan formwork 2 DAYS 8.3.2020 9.3.2020
14 Kerja menimbus kembali tanah 4 DAYS 9.3.2020 12.3.2020

1.3 MEMBINA GROUND BEAM


15 Grid Line Allignment / Levelling 4 DAYS 13.3.2020 16.3.2020
16 Pasang formwork 4 DAYS 13.3.2020 16.3.2020
17 Pasang besi / re bar 3 DAYS 17.3.2020 19.3.2020
18 Tie up / support formwork 3 DAYS 20.3.2020 22.3.2020
19 Kerja-kerja concreting to Ground Beam 3 DAYS 23.3.2020 25.3.2020

1.4 GROUND FLOOR SLAB


20 Mengisi tanah/pasir/hardcore 3 DAYS 26.3.2020 28.3.2020
21 Menghampar Plastic sheet 3 DAYS 26.3.2020 28.3.2020
22 Menghampar BRC 3 DAYS 26.3.2020 28.3.2020
23 Concrete Pouring to Slab 2 DAYS 29.3.2020 1.4.2020
SERIBUMI DEVELOPMENT SDN. BHD.
DATE : 8.2.2020
PREPARED BY : CONTRACTOR (ROZNAN/NABIL)
PROJECT : Cadangan meroboh dan membina semula
sebuah rumah berkembar satu tingkat sediada di lot 166 (PT.89)
No. 14, Jalan 3/67, Seksyen 3, 46100 Petaling Jaya, Selangor Darul Ehsan.

WORK SCHEDULE
NO TASK NAME DURATION START FINISH
SUPER STRUCTURE
2.1 MEMBINA TIANG
24 - Grid line allignment / levelling 3 DAYS 2.4.2020 4.4.2020
25 - Pasang besi / re bar 3 DAYS 5.4.2020 7.4.2020
26 - Pasang formwork 3 DAYS 8.4.2020 10.4.2020
27 - Checking verticallity and tie up formwork 3 DAYS 10.4.2020 12.4.2020
28 - Concrete Pouring to column 3 DAYS 13.4.2020 15.4.2020

2.2 MEMBINA ROOF BEAM


29 - Menyediakan / Menaikkan T-support/ staging 3 DAYS 15.4.2020 17.4.2020
30 - Pasang roof beam bottom formwork 3 DAYS 15.4.2020 17.4.2020
31 - Pasang roof beam side formwork 3 DAYS 15.4.2020 17.4.2020
32 - Masukkan tetulang besi / re bar 3 DAYS 18.4.2020 20.4.2020
33 - Tie up roof beam formwork 3 DAYS 21.4.2020 23.4.2020
34 - Concrete Pouring to roof beam 3 DAYS 21.4.2020 23.4.2020

2.3 KERJA KERJA BUMBUNG


35 - Pasang wall plate dan kekuda 3 DAYS 24.4.2020 26.4.2020
36 - Laying aluminium foil/timber battern 3 DAYS 24.4.2020 26.4.2020
37 - Pasang atap genting 4 DAYS 27.4.2020 31.4.2020

2.4 KERJA BATA, PLASTER, FRAME PINTU/TINGKAP DAN


SILING
38 - Pasang frame pintu 2 DAYS 1.5.2020 2.5.2020
39 - Kerja mengikat dinding bata 3 DAYS 1.5.2020 3.5.2020
40 - Pasang frame tingkap 2 DAYS 1.5.2020 3.5.2020
41 - Kerja-kerja plaster 3 DAYS 2.5.2020 4.5.2020
42 - Kerja-kerja siling 5 DAYS 4.5.2020 7.5.2020

COLD WATER PLUMBING/SANITARY/SEWERAGE


43 - Under ground paip 3 DAYS 8.5.2020 10.5.2020
44 - Piping and Sanitary fitting 3 DAYS 8.5.2020 10.5.2020
45 - Sewer pipe and septic tank 3 DAYS 8.5.2020 10.5.2020

KERJA-KERJA ELEKTRIK
43 - Cable Laying 2 DAYS 11.5.2020 12.5.2020
44 - Electric Appliance 2 DAYS 11.5.2020 12.5.2020
SERIBUMI DEVELOPMENT SDN. BHD.
DATE : 8.2.2020
PREPARED BY : CONTRACTOR (ROZNAN/NABIL)
PROJECT : Cadangan meroboh dan membina semula
sebuah rumah berkembar satu tingkat sediada di lot 166 (PT.89)
No. 14, Jalan 3/67, Seksyen 3, 46100 Petaling Jaya, Selangor Darul Ehsan.

WORK SCHEDULE
NO TASK NAME DURATION START FINISH
FINISHING WORKS
43 - Floor and Wall tiles 5 DAYS 13.5.2020 17.5.2020
44 - Painting 5 DAYS 13.5.2020 17.5.2020
45 - Fixing door / Window leaf 5 DAYS 13.5.2020 17.5.2020

EXTERNAL WORKS
46 - Perimeter drain and turfing/landscaping 5 DAYS 18.5.2020 22.5.2020

16.2.2020 - 22.5.2020
*DAYS ARE SUBJECTED TO CHANGE ACCORDING TO
CONRTRACTOR SUPERVISION