ID Outline Number Name Duration

2 1.1 Draw plans 7.00d


10 2.1   -  Review & Finalize Plans 3.00d
13 2.4   -  Print Construction Drawings 1.00d
26 4 Grading & Building Permits 14.00d
27 4.1   -  Schedule lot stake-out 1.00d
28 4.2   -  Stake lot 1.00d

29 4.3   -  File Grading Permit Application 1.00d

30 4.4   -  File Building Permit Application 3.00d

31 4.5   -  Post Lot Identification 1.00d


  -  Install Construction Barracks and
34 4.8 3.00d
Storage
41 4.15   -  Building Permit Issued 0.00d
42 5 Site Work 7.00d
43 5.1   -  Clear Lot 2.00d
44 5.2   -  Strip Topsoil & Stockpile 1.00d
45 5.3   -  Stake Lot for Excavation 1.00d
46 5.4   -  Rough grade lot 1.00d
47 5.5   -  Excavate for foundation 2.00d
48 6 Foundation 38.00d
49 6.1   -  Layout footings 1.00d

50 6.2   -  Dig Footings & Install Reinforcing 5.00d

51 6.3   -  Footing Inspection 0.00d


52 6.4   -  Pour footings 5.00d
53 6.5   -  Pin Footings 1.00d
54 6.6   -  Stock Block, Mortar, Sand 5.00d
55 6.7   -  Build Block Foundation 15.00d
58 6.1   -  Fill Block Cores w/ Concrete 1.00d
59 6.11   -  Steel Delivery 1.00d
60 6.12   -  Set Lintels, Bolts, Cap Block 2.00d
61 6.13   -  Lumber Delivery 1.00d
62 6.14   -  Waterproofing and Drain Tile 1.00d
63 7 Rough Carpentry 20.00d
64 7.1   -  Set Steel 1.00d
65 7.2   -  Floor Deck Framing 4.00d
66 7.3   -  Floor Wall Framing 4.00d
71 7.8   -  Set Roof Beam 7.00d
  -  Install Windows & Doors
74 7.11 4.00d
Provisions
77 8 Concrete Slabs 8.00d
90 10 Plumbing Rough-in 8.00d
91 10.1   -  Plumbing Sub-slab 2.00d
92 10.2   -  Plumbing Layout 1.00d
93 10.3   -  Plumbing rough-in 5.00d
96 13 Electric Rough-in 19.00d
97 13.1   -  Set Electric Boxes 2.00d
98 13.2   -  Install Electric Service Panel 2.00d
99 13.3   -  Electrical Walk-through 1.00d
100 13.4   -  Electrical Rough-wire 14.00d
101 14 Specialty Rough-ins 4.00d
104 14.3 Internet/Cable 2.00d
CCTV provisions 2.00d
110 18 Roofing/ceiling 33.00d
72 7.9   -  Frame Roof 7.00d
  -  Install Sansdtone and steel
73 7.1 roofing (sub-con) 5.00d

Test Roof for Leaks 1.00d


install insulation 3.00d
iinstall ceiling frame 7.00d
install hardiflex 10.0d
115 19 Exterior Finishes 56.00d
116 19.1   -  Siding 3.00d
117 19.2   -  Door Trims 7.00d
118 19.3   -  install window mouldings 16.00d
119 19.4   -  install pvc design for wall 4.00d
install baluster and railings 5.00d
prep wall for paint 14.00d
flat latex painting 7.00d
126 23 Interior Wall rough finishes 21.00d
127 23.1 prep wall/ceiling for paint 14.00d
128 23.2 flat latex painting 7.00d
134 25 Floor/T&B Finishes 21.00d
135 25.1 Install wood grain tiles 15.00d
136 25.2 patio 1.00d
137 25.3 T&B Masters 2days
138 25.4 T&B Common 2 days
139 25.5 T&B Small Room 1.00d
150 28 Carpentry 29.00d
151 28.1   -  Interior Trim/Door Delivery 2.00d
Install Door Jam 3.00d
152 28.2   -  Install Doors 7.00d
153 28.3   -  Install baseboard 5.00d
Install Masters T&B Cabinet 1.00d
154 28.4  Install Kitchen Cabinetry 5.00d
155 28.5 install masters walk-in closet 5.00d
156 28.6 install other room cabinets 5.00d
Install entertainment Cabinet 3.00d
140 26 Paint Finishes 26.00d
141 26.1 Finish Coat Trim Exterior 7.00d
142 26.2 Finish Coat Interior Walls 7.00d
143 26.3 Prep coat Kitchen cabinets 2.00d

144 26.4 Prep coat Masters walk in cabinets 3.00d

Prep Coat other room cabinets 2.00d


Prep coat baseboard 1.0d
Finish Coat other room cabinets 2.00d
Finish coat baseboard 2.00d
160 30 Plumbing Trim 5.00d
161 30.1 Acquisition/delivery fixtures 2.00d
161 30.1   -  Set Fixtures 4.00d
162 30.2   -  Connect Appliances 1.00d
172 33 Electrical Final Trim 4.00d
173 33.1   -  Switch & Plug 2.00d
174 33.2   -  Install Fixtures 1.00d
175 33.3   -  Connect Appliances 1.00d
176 34 Hardware 9.00d
177 34.1   -  Door Hardware 2.00d
178 34.2   -  Bath Hardware 2.00d
180 34.4   -  Shower Doors 5.00d
184 38 Final Building Inspection 0.00d
185 39 Use & Occupancy Certificate 0.00d
186 40 First Walk-thru 0.00d
188 42 Final Punch-out 9.00d
189 42.1   -  Punch Out Walk-thru List 4.00d
190 42.2   -  Trim and Adjust Doors 2.00d
191 42.3   -  Paint Touch-up 3.00d
192 43 Cleaning 7.00d
193 43.1   -  Windows 3.00d
194 43.2   -  Rough Clean 3.00d
195 43.3   -  Final Clean 2.00d
196 44 Final Walk-through 0.00d
197 45 Move-in 0.00d

338 days
Day Count Finish

. Thu 6/5/14
4 Wed 6/25/14
10,11,12 Wed 7/9/14
. Fri 8/1/14
13 Thu 7/10/14
27FS+3d Wed 7/16/14

16 Thu 7/10/14

14,15,16 Mon 7/14/14

28,29,30 Thu 7/17/14

32,33 Tue 7/22/14

40 Fri 8/1/14
. Tue 8/5/14
37 Wed 7/30/14
43 Thu 7/31/14
43 Thu 7/31/14
43,45 Fri 8/1/14
39,45,43,46 Tue 8/5/14
. Mon 9/8/14
47 Wed 8/6/14

49 Thu 8/7/14

50 Thu 8/7/14
51 Fri 8/8/14
52 Mon 8/11/14
53 Tue 8/12/14
53,54 Tue 9/2/14
55 Wed 9/3/14
58 Thu 9/4/14
59 Mon 9/8/14
58 Thu 9/4/14
61 Fri 9/5/14
. Fri 11/7/14
60 Tue 9/9/14
64 Mon 9/15/14
65 Fri 9/19/14
70 Tue 9/30/14

73,111 Thu 10/23/14

. Mon 9/29/14
. Wed 11/5/14
65 Wed 9/17/14
91,87 Wed 10/29/14
92 Wed 11/5/14
. Wed 11/19/14
74 Mon 10/27/14
97 Wed 10/29/14
98 Thu 10/30/14
99 Wed 11/19/14
. Wed 11/26/14
100 Wed 11/26/14

. Tue 1/20/15
71 Thu 10/9/14

72 Thu 10/16/14

. Fri 1/9/15
74 Tue 10/28/14
116 Thu 11/6/14
117 Fri 11/7/14
118 Fri 1/9/15

. Fri 1/9/15
124 Fri 12/5/14
127 Fri 12/12/14
. Tue 4/28/15
142 Mon 2/2/15
146 Wed 4/1/15
196 Wed 4/22/15
137 Tue 4/28/15
196 Fri 4/17/15
. Fri 2/20/15
142 Tue 1/13/15

151 Tue 1/20/15


152 Tue 2/10/15

153 Tue 2/17/15


154 Wed 2/18/15
155,144 Fri 2/20/15

. Mon 3/30/15
131 Thu 1/8/15
141 Mon 1/12/15
142,152 Thu 1/22/15

143 Mon 1/26/15

. Wed 4/8/15
135,136,146,154 Tue 4/7/15
135,136,146,154 Tue 4/7/15
161 Wed 4/8/15
. Wed 1/14/15
142,100 Wed 1/14/15
146 Thu 3/27/15
155,162 Thu 4/10/15
. Mon 4/13/15
145,146 Mon 3/30/15
145,146 Mon 3/30/15
178 Mon 4/13/15
183 Thu 3/26/15
184FS+3d Tue 3/31/15
185 Tue 3/31/15
. Mon 4/13/15
186 Mon 4/6/15
184,189 Wed 4/8/15
190 Mon 4/13/15
. Wed 4/15/15
145,146 Tue 3/31/15
193 Fri 4/3/15
176,188 Wed 4/15/15
187,188,192 Wed 4/15/15
196FS+1d Thu 4/16/15