SN Document Early Start Early Finsihed Late Start Late Finished Remarks

A Operations and Maintenance Manuals

1 Swimming Pools & Water Features 12-Dec-2021 26-Dec-2021 11-Jan-2022 25-Jan-2022 Submitted Already

2 Hardlandscape 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

3 Softlandscape 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

4 Irrigation System 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

B Warranties, Guaranties and Certficates

1 Swimming Pools & Water Features 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

2 Hardlandscape 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

3 Softlandscape 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

4 Irrigation System 16-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022

C Test Reports

1 Swimming Pools & Water Features 30-Jan-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

2 Hardlandscape 30-Jan-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

3 Softlandscape 30-Jan-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

4 Irrigation System 30-Jan-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

D As Built Drawings

1 Swimming Pools & Water Features 2-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022

2 Hardlandscape 2-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022

3 Softlandscape 2-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022

4 Irrigation System 2-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022


Tower C of the “Aykon City” Mixed Use
Project:
Development located on

Subject: Schedule of Handing Over Document Submission

SN Document Early Start Early Finsihed Late Start Late Finished Remarks
A Operations and Maintenance Manuals

1 Swimming Pools & Water Features 26-Dec-2021 26-Dec-2021 11-Jan-2022 25-Jan-2022 After approval of Tower B

2 Hardlandscape 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

3 Softlandscape 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

4 Irrigation System 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

B Warranties, Guaranties and Certficates

1 Swimming Pools & Water Features 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

2 Hardlandscape 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

3 Softlandscape 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

4 Irrigation System 30-Dec-2021 30-Dec-2021 15-Jan-2022 29-Jan-2022 After approval of Tower B

C Test Reports

1 Swimming Pools & Water Features 13-Feb-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

2 Hardlandscape 13-Feb-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

3 Softlandscape 13-Feb-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

4 Irrigation System 13-Feb-2021 13-Feb-2021 28-Feb-2021 14-Mar-2021 After Testing & Commissioning

D As Built Drawings

1 Swimming Pools & Water Features 16-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022

2 Hardlandscape 16-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022

3 Softlandscape 16-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022

4 Irrigation System 16-Jan-2022 16-Jan-2022 1-Feb-2022 15-Feb-2022