Ejere - Arambute - Shenkora Yohanness Heavy Maintenance Road Project

ID Text1 Task Name Start Finish October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 20
October November December January February March April May
27 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 02 10 18 26 06 14 22 30 07 15 23 01 09 17 25 02
1 ETHIOPIAN ROADS AUTHORITY 15-10-21 31-05-22

2 Alemgena RNSMD 15-10-21 31-05-22

3 1 Laboratory Building,Equipment and 15-10-21 27-01-22


Supplies as specfied under the Spec.
4 2 Laboratory testing to be carried out in 15-10-21 28-04-22
external laboratory,as ordered by the
5 125 Engineer
Mortared Masonry repair 25-02-22 23-04-22

6 127 Gabion Structure 15-11-21 30-12-21

7 317 Gravel Resurfacing (Selected 03-02-22 31-05-22


Material)
8 319 Road Bed Preparation 15-11-21 04-01-22

9 32.01 Excavation 15-11-21 13-12-21

10 (a) Excavation of soft material 15-11-21 29-11-21


irrespective of depth
11 (b) Excavation of hard material 29-11-21 07-12-21
irrespective of depth
12 (c) Channel excavation 08-12-21 13-12-21

13 32.02 (b) Backfilling using imported material 04-04-22 11-05-22

14 32.03(a) iii. Concrete Pipes (on class "B" bedding 26-11-21 31-03-22
and 48" Diameter
15 34.01 (b) i. Grouted stone pitching at inlet and out 02-03-22 31-03-22
let of structures
16 34.01 (b)iii. Grouted stone pitching for side ditch 31-12-21 09-02-22

17 34.03 (b) Cement-mortared stone walls 09-02-22 27-04-22

18 42.01 Cut and borrow to fill including all 01-01-22 26-03-22


haul
19 (a) Cut/Borrow to fill material in 01-01-22 26-03-22
compacted layer thickness of 200
20 (iii) mm and less to 95% of modified
Compacted 01-01-22 26-03-22
AASHTO density
21 (b) Capping Layer 19-01-22 23-03-22

22 42.03 Cut to Spoil including all haul of any 23-11-21 20-01-22


material type
23 15.01(a) Detour Construction 15-11-21 07-12-21

24

25

26

27