ADM PROJECT : QA

No. Task Name Dur Start Finish


oct

A PREPARATION WORK 110 d 13-Oct-22 31-Jan-23

B CIVIL WORK
1 Earth Work 16 d 17-Oct-22 01-Nov-22
2 Pile & Foundation Work 19 d 25-Oct-22 12-Nov-22
3 Concrete Structure Work 20 d 05-Nov-22 24-Nov-22
4 Steel Structure Work 49 d 20-Oct-22 07-Dec-22
5 Masonry Work 28 d 24-Oct-22 20-Nov-22
6 Waterproffing Work
7 Tile Work 12 d 24-Dec-22 04-Jan-23
8 Roofing & Sidding Work 14 d 12-Dec-22 25-Dec-22
9 Miscellaneous metal work 21 d 14-Dec-22 03-Jan-23
10 Door And Window Work 26 d 24-Nov-22 19-Dec-22
11 Painting Work 10 d 06-Jan-23 15-Jan-23
12 Eksterior & Interior Finishing Work 21 d 23-Dec-22 12-Jan-23
13 Miscellanous Work 6d 19-Jan-23 24-Jan-23
14 Eksternal Work 7d 20-Jan-23 26-Jan-23

C MECHANICAL & ELECTRICAL WORK


1 Air Conditioner 3d 13-Jan-23 15-Jan-23
2 Equipment 10 d 21-Dec-22 30-Dec-22
3 Ducting Works ( SUS ) 17 d 22-Dec-22 07-Jan-23
4 Plumbing Works 16 d 24-Dec-22 08-Jan-23
5 Fire Figghting Works 11 d 24-Dec-22 03-Jan-23
6 Air Compressor system works 11 d 15-Jan-23 25-Jan-23
7 Main feeder system for building Facility 12 d 18-Dec-22 29-Dec-22
8 Power Wiring For Building 11 d 04-Jan-23 14-Jan-23
9 Lighting System 12 d 18-Jan-23 29-Jan-23
10 Socket outlet System 8d 23-Dec-22 30-Dec-22
11 Telephone system 8d 23-Dec-22 30-Dec-22
12 Fire alarm system 7d 23-Dec-22 29-Dec-22
D Final Test & Commissioning 2d 30-Jan-23 31-Jan-23
ADM PROJECT : QA LABORATORY

2022 20
oct nov dec jan
2023
jan feb
2022
NOVEMBER DESEMBER

14-Nov-22 6-Jan-22
21-Nov-22
ok Design Item A
ok Design Item B
ok Design Item C

Persiapan Item A
Persiapan Item B ###
Persiapan Item C ###

Delivery Steel material Item A ### 23 Des 22


Delivery Steel material Item B 23 Des 22
Delivery Steel material Item C 25-Jan-23

Piling Item A ### 14 Des 22


Piling Item B 14 Des 22
Piling Item C 1-Jan-23

Construction A
Construction B
Construction C

A Water Supply
Genset Room
Substation Tosso
Tosso Compressor Room
Receiving Room
Stanchion
Construction A
1.1 Earth Work
1.2 Piling Work
Foundation Work
1.3 Concrete Work
1.4 Steel Structure Work
1.5 Roofing Work
1.6 Fascia Work
1.7 Miscellaneous Work
1.8 Painting Work
1.9 Fence Installation Work
1.10 Finishing Work
1.11 Rain Drainage

B Substation welding
Colling tower welding foundation
Construction B
1.1 Earth Work
1.2 Pile & Foundation Work
1.3 Concrete Work
1.4 Steel Structure Work
1.5 Roofing Work
1.6 Fascia Work
1.7 Miscellaneous Work
1.8 Painting Work
1.9 Fence Installation Work
1.10 Finishing Work
1.11 Rain Drainage

C Gasoline supply foundation


Welding & assembly compressor room
Subtstation assembly
Construction C
1.1 Earth Work
1.2 Pile & Foundation Work
1.3 Concrete Work
1.4 Steel Structure Work
1.5 Roofing Work
1.6 Fascia Work
1.7 Miscellaneous Work
1.8 Painting Work
1.9 Fence Installation Work
1.10 Finishing Work
1.11 Rain Drainage
2023
JANUARY FEBRUARY MARET APRIL JUNY

6-Jan-22 30-Jan-22 6-Feb-23 27-Feb-22

23 Des 22
25-Jan-23
25-Jan-23 27-Feb-23

1-Jan-23
30-Jan-23

6-Feb-23 5-Apr-23
5-Apr-23

2-Jun-23
2023
JUNY JULY AGUSTUS SEPTEMBER OKTOBER

26-Jun-23 31-Jul 7-Aug 25-Sep


7-Aug-23 23-Aug-23

2-Jun-23

23-Aug-23 8-Sep-23

31-Jul-23

8-Sep-23 25-Sep-23
OKTOBER
SEPTEMBER OKTOBER

9-Sep-22

ok Design Item A 8 Okt 22


ok Design Item B 6 Okt 22
ok Design Item C 10 Okt 22

Persiapan Item A 17-Oct-22


Persiapan Item B 26-Oct-22
Persiapan Item C 4-Nov-22

Delivery Steel material Item A


Delivery Steel material Item B
Delivery Steel material Item C

Piling Item A
Piling Item B
Piling Item C

Construction A
Construction B
Construction C

A Water Supply
Genset Room
Substation Tosso
Tosso Compressor Room
Receiving Room
Stanchion
Construction A
1.1 Earth Work
1.2 Piling Work
Foundation Work
1.3 Concrete Work
1.4 Steel Structure Work
1.5 Roofing Work
1.6 Fascia Work
1.7 Miscellaneous Work
1.8 Painting Work
1.9 Fence Installation Work
1.10 Finishing Work
1.11 Rain Drainage

B Substation welding
Colling tower welding foundation
Construction B
1.1 Earth Work
1.2 Piling Work
Foundation Work
1.3 Concrete Work
1.4 Steel Structure Work
1.5 Roofing Work
1.6 Fascia Work
1.7 Miscellaneous Work
1.8 Painting Work
1.9 Fence Installation Work
1.10 Finishing Work
1.11 Rain Drainage

C Gasoline supply foundation


Welding & assembly compressor room
Subtstation assembly
Construction C
1.1 Earth Work
1.2 Piling Work
Foundation Work
1.3 Concrete Work
1.4 Steel Structure Work
1.5 Roofing Work
1.6 Fascia Work
1.7 Miscellaneous Work
1.8 Painting Work
1.9 Fence Installation Work
1.10 Finishing Work
1.11 Rain Drainage
2022
OKTOBER NOVEMBER DESEMBER JANUARY FEBRUARY

17 Okt 14-Nov-22 6-Jan-22 30-Jan-22


21-Nov-22
17 Okt 22
12 Okt 22
17 Okt 22

26-Oct-22
26-Oct-22 4-Nov-22
4-Nov-22 11-Nov-22

21-Nov-22 23 Des 22
23 Des 22 25-Jan-23
25-Jan-23

21-Nov-22 14 Des 22
14 Des 22 1-Jan-23
1-Jan-23 30-Jan-23

6-Feb-23
8-Feb-23
19-Apr-23
2023
FEBRUARY MARET APRIL MAY JUNY

6-Feb-23 27-Feb-22

25-Jan-23
27-Feb-23

30-Jan-23

5-Apr-23
20-Feb-23
19-Apr-23 10-Mar-23
23-Feb-23 31-Mar-23
9-Mar-23 10-May-23
1-Apr-23 5-Jun-23
25-May-23
12-Jun-23
9-Apr-23
9-Jun-23
26-May-23
5-Apr-23 2-Jun-23
7-Apr-23 19-Apr-23
18-Apr-23 8-May-23
26-Apr-23 23-May-23
10-May-23
8-Jun-23
25-Jun-23

2-Jun-23
3-Jun-23 7-Jun-23
4-Jun-23
12-Jun-23
18-Jun-23
3
JUNY JULY AGUSTUS SEPTEMBER OKTOBER

26-Jun-23 31-Jul 7-Aug 25-Sep

5-Jun-23
13-Jun-23
23-Jun-23
10-Jun-23
8-Jul-23
3-Jul-23
7-Aug-23 23-Aug-23
4-Jul-23 6-Aug-23

2-Jun-23

21-Jun-23
26-Jun-23
25-Jun-23 7-Jul-23
25-Jul-23 30-Jul-23
9-Jul-23 25-Apr-23
1-Aug-23 10-Aug-23
15-Jul-23 7-Aug-23
23-Aug-23 8-Sep-23
11-Aug-23 22-Aug-23

31-Jul-23
7-Jun-23
13-Jun-23
19-Jun-23
24-Jul-23
13-Jul-23 28-Jul-23
27-Jul-23 6-Aug-23
7-Aug-23 11-Aug-23
5-Aug-23 22-Aug-23
21-Aug-23 7-Sep-23
14-Jul-23 8-Aug-23
8-Sep-23 25-Sep-23
23-Aug-23 30-Aug-23
OKTOBER
WORK PLAN : QA Laboratory Building

OKTOBER NOPEMBER
NO ITEM PEKERJAAN
MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4

1 Setting out
2 Temporary Protection
3 Pemindahan pohon
4 Mob of pile equipment
5 Pile driving
6 Demob of pile equipment
7 Pile head cutting
8 Rebar fabrication
9 Concrete Work