Calendar:
Procurement
6 Vendors selection 4w 5
7 Procurement of M/c 20d 6
8 Procurement of structural steel 15d 6
9 Procurement of fabrication 10d 6
materials
10 Procurement of C,S,A,R-bar 12d 6
Execution
Preliminary works
11 Site clearance 5d 6
12 Setting-up site office 10d 11
13 Setting up storage spaces 10d 11
14 Setting-up fabrication unit 12d 11, 7FF+3d
Fabrication:
15 Fabrication of steel columns 20d 8,9,12,13,14
16 Fabrication of trusses 24d 15
17 Fabrication of Door & window 12d 16
shutters and frames
Construction
18 Excavation 12d 12,13
19 PCC bed 6d 10,18
20 RCC footings 20d 19
21 RCC columns upto plinth 18d 20
22 RCC plinth beams 10d 21
23 Plinth filling 10d 22
24 Erection of steel columns 20d 15,22FS+7d
25 Erection of trusses 20d 16,24
26 Roofing 15d 25
27 Side walls 12d 23,25
28 Fixing doors & windows 6d 17,26,27
29 Flooring 10d 26,27
30 Painting 12d 28,29
31 Electrification 12d 30
Resources:
Sr. No. Name of resource Unit Rate (Rs/unit) Max. available units
1 Surveyor hr 120 1
2 (from 01 Apr, 2021)
2 Mason hr 70 (Rate A); 80 (Rate B) 1
3 Welder hr 120 2
4 Fitter hr 100 2
5 Painter hr 75 2
6 Electrician hr 100 1
7 Survey assistant hr 60 2
66 (from 01 Apr, 2021)
8 Electrical assistant hr 60 2
9 Helper hr 60 10
10 Mazdoor hr 60 8
11 Welding m/c hr 400 2
12 Fabrication setup hr 4000 1
13 12 Ton Hydra Crane hr 1500 1
14 Structural steel Ton 60000 20
15 Cement bags 340 500
16 Aggregate Cum 2400 100
17 Sand Cum 2800 100
18 R-bar ton 45000 10
19 RMC Concrete Cum 5500 40
20 Roofing Sheets Sqm 1000 500
21 Flooring Tiles Sqm 250 500
22 Paint lit 600 100
23 Bricks Nos 5 10000
Roles:
Role Name Rate (Rs/hr)
Engineering (Engg)
Surveying (Sur) 170
Designing (Des)
Structural designing (Str-Des) 280
Proof reading of designs (Proof-Read) 280
Supervision (Sup)
Civil works supervision (Civil-Sup) 180
Mech works supervision (Mech-Sup) 200
Fabrication supervision (Fab-Sup) 200
Managerial (Mngr)
Procurement (Proc)
Vendor selection (Vend-Sel) 360
Procurement of materials (Mat-Proc) 200
Procurement of Plants & M/c (P&M-Proc) 200
Project management (PM)
Overall project management (OPM) 500
Planning (Pln) 220
Cost control (Cost-ctrl) 220
Progress monitoring (Monitor) 220
Quality assurance & Quality control (QA&QC)
Testing (Test) 180
Inspection (Insp) 200
Approval (Apprvl) 200